Bond Work & Sinking Fund Project Update: June 2025
With the passing of the August 2023 Bond, Berkley Schools teams are busy planning for upcoming construction projects. In addition to the Bond projects, the District has a list of Sinking Fund projects that are also in the works to improve and update our facilities. The Sinking Fund was approved by voters in 2018. Because both Bond and Sinking Fund projects are ongoing, these monthly updates will include details on both.
The June update includes construction and timeline updates on the Burton and Pattengill, Berkley High School’s Performing Arts, Pool and Science Wing construction projects, updates on The BEAR Complex project and updates on Phase II projects.
These monthly Bond & Sinking Fund updates will be maintained on the District’s website. See below for updates on the Phase I projects that are taking place in 2025-2026.
Bond & Sinking Fund Projects - Phase I Timeline
The following is an estimated Phase I timeline for the 2025 projects. These dates may change due to the nature of construction including weather delays, supply chain delays, etc.
- Underway: Black Box Theatre Construction
- Underway: Pool Construction
- Underway: The BEAR Complex Construction
- Underway: The Den Construction
- Underway: Auditorium Construction
- Underway: Science Wing Construction
- Underway: Burton & Pattengill - New Additions, Gym Remodel, Playgrounds, Parking Lots
- August 2025: Pool Grand Opening
- Fall 2025: Burton & Pattengill Multi-Purpose Addition Grand Opening
- Fall 2025: BHS Science, Band and Orchestra Classrooms Open
- October 2025: Science Labs Grand Opening
- Spring 2026: Performing Arts Center Grand Opening (Auditorium, Black Box Theatre, Instrument Commons)
- Fall 2026: The BEAR Complex Grand Opening
Project Updates: Phase I
Burton & Pattengill Multi-Purpose Additions - Bond
Burton & Pattengill multi-purpose/cafeteria additions are underway. Due to some construction delays, the additions will not open prior to school starting, but the gyms and playgrounds are expected to be open by the end of August. Lunch service will continue in the gyms until the new additions and kitchens are complete later in the fall.
Burton
Burton’s new multi-purpose/cafeteria addition will be attached to the building at the northeast corner of the playground by the gym. It will house a new lunchroom, a new kitchen, storage rooms, restrooms and will be a wonderful space for collaboration. In addition, Burton’s gym is receiving a makeover, replacing the floor, backboards, padding as well as painting the ceiling.
Construction Update:
- Interior and exterior masonry walls are complete. The floor slab work has begun.
- Steel structural work is complete and roof work is underway
- The waterproof membrane is installed and brick layers are adding the final outside brick.
- The new playground area inside of the track is nearly complete, and will open as soon as additional pieces arrive for installation.
- Inside the building, the gym floor has been removed and temporary walls were installed to separate the construction zone from the rest of the school.
- The new addition is connected to the existing building through the Burton staff lounge. That room is now fully under construction while the crew reconfigures that area.
Pattengill
Pattengill’s new multi-purpose/cafeteria addition will be attached to the building at the north doors, in the current concrete area. It will house a new lunchroom, a new kitchen, storage rooms, restrooms and will be a wonderful space for collaboration. In addition, Pattengill’s gym is receiving a makeover, replacing the floor, backboards, padding as well as painting the ceiling.
Construction Update:
- Interior and exterior masonry wall construction is complete.
- Steel installation is nearly complete and the roof is being installed.
- Electrical and plumbing work continues.
- The floor pad will be installed after the plumbing is complete.
- In addition to the multi-purpose addition, the District is adding parking spaces near the baseball field on Royal as part of the construction.
- The Pattengill playground will close June 30-July 3 to remove old pipes that were discovered under the playground area.
BHS Performing Arts Wing - Bond
Timing Update: Due to delays with permitting and surprises discovered during demolition, both the Black Box Theatre and Performing Arts Center are behind schedule. Contractors are working to make up time, but it’s too soon for the District to announce new expected openings.
Black Box Theatre/Choir Room
The Black Box Theatre/Choir Room is being added to complete the Performing Arts Wing. The space will be used during the day for choir classes and after school for performances and rehearsals, to complement the auditorium.
Construction Update:
- Footings for the addition are complete.
- Masons will begin working to form the walls next.
- Work will begin on the water retention systems in the parking lot area in 6-8 weeks.
Performing Arts Center
Construction Update:
- Auditorium demolition is complete.
- Electrical continues in the auditorium and backstage.
- The foundation for the auditorium lobby addition is complete.
- Masonry work has begun to form the new lobby addition.
- Demolition has begun in the Orchestra classroom.
- Masons have closed doorways backstage to prepare for the new dressing rooms.
BHS Science Wing - Bond
The BHS Science Wing work includes a complete renovation and redesign for the lab spaces, updates to chemical storage rooms and creating new lab spaces.
Construction Update:
- Demolition has begun, removing old fixtures, cabinets, ceilings, walls and floors where applicable.
- Ceilings in classrooms and hallways below the science wing have been removed to help with plumbing and electrical work.
BHS BEAR Complex - Bond
The District Field House project is now named The BEAR Complex (The Berkley Education, Athletics and Recreation Complex). The BEAR Complex includes a 60-yard indoor fieldhouse that includes a new weight room, team room and trainer room, an outdoor 120-yard turf performance field with lights, parking lot expansion and new configuration and a grass field north of the turf field.
Construction Update:
- All the maintenance buildings on the property are demolished.
- The construction fencing installation is complete.
- Soil abatement is taking place to prepare the site for additional leveling of the property.
- Tree trimming is complete.
- As a reminder for the public: All construction sites are not for public access.
BHS Pool - Bond
The pool scope includes: a new HVAC system, new starting blocks, new diving board, updating tile areas, redoing the pool office and restroom and updates to the chemical system. In addition to this work, the team is adding a new filter system, a new timing system and scoreboard, upgrading lighting and additional plumbing work including replacing the water main leading to the pool. Additional mechanical work (filtration and chemical systems) will be completed in spring/summer 2026.
The pool work was a little delayed due to the roofing project, and back-up plans are being made for the swim team in case the pool is not ready by the season opening practice.
Construction Update:
- The old HVAC unit on the pool roof has been removed and the new one is in place.
- Painters are working to finish painting the ceiling and walls (leaving the student artwork intact).
- Electricians are installing new conduit, lighting and power for the new scoreboard system.
- The Crow’s Nest area will be decommissioned and a new scorers table will be installed next to the bleachers on the north side once the pool is complete.
- After the painting is complete, the tile work will begin to repair tile throughout the deck and then the new starting blocks will be installed.
The Den - ATP and Robotics - Sinking Fund
The former Cana Lutheran Church has a new name - The Den! The Den will house The Adult Transition Program (ATP) and Robotics programs.
Construction Update:
- Demolition is complete and wall framing is underway in both the ATP and Robotics spaces.
- HVAC and electrical work continue.
- Fireproofing is complete.
- Site work continues.
Phase II: 2025-2026
Angell & Rogers Multi-Purpose Additions - Bond - Fall 2025
Both multi-purpose additions will resemble the Burton and Pattengill designs and function, and will have playground or outside space adjustments to accommodate the new additions.
Construction Update:
- Contractors are working on both buildings to prepare electrical and gas lines for the new additions. This work will take place in hallway ceilings and a few classrooms.
- Construction fencing is expected at both locations in late August/early September.
- As the new school year approaches, principals will communicate with their school communities about construction impacts on drop off, pick up and parking.
Norup, AMS & Hurley Field - Bond - Spring 2026
The design phase for the Norup, AMS and Hurley Field work has begun. The project includes updating the school gym floors, paint and equipment. Hurley Field work includes updating team rooms, restrooms, field lighting, press box, flow and fence lines, discus area and expanding the parking lot to improve available spaces as well as traffic flow.
Burton & Tyler Park Fields - Sinking Fund - 2026
Burton Field
The District project to improve Burton’s field with its professional partners is solidified. The work will include fixing the ponding, replacing the dirt infields with grass infields and preparing the site to have a multi-purpose use as well as include two diamonds to host t-ball games. The plan is to have this work begin in Fall 2025, once the Burton playground is reopened. This project is being funded by Berkley Schools, Huntington Woods Men’s Club as well as the City of Huntington Woods and supported by the Berkley Dads Club. Bids were opened on June 26 and contractors will be reviewed and sent to the Board of Education for approval.
Tyler Park - Softball Field Update
The District Bond/Sinking Fund team is working to finalize the plans for updating Tyler Park with City of Oak Park officials. On the District side, a new Varsity softball field will be built with lights, permanent fence, dugouts, stands, scoreboard, bullpens and batting cages. The District property will also have a practice softball/baseball field for middle school students. On the Oak Park side, a multipurpose field will be updated to improve the drainage issues. A walking path will also be added to both properties to allow for a full path connecting the parking lots to the fields and for the community to enjoy. On the District side of the property a small restroom facility will be built as well. The plan is to have construction begin in Spring of 2026.
Join the Berkley Schools Family - Now Hiring!
The Berkley School District is hiring! We are looking for talented individuals to fill a variety of positions. Visit our website to apply and share our postings with your networks!
Open Positions
- Elementary Principal - Rogers Elementary
- Special Education Coordinator - 2025-26 School Year - Administrative Offices
- School Psychologist - 2025-26 School Year
- Lead Teacher - Tuition Programs - BBB
- Head Custodian (2 positions) - Angell, Pattengill
- Accounts Payable Clerk - Administrative Offices
- GSRP Associate Teacher (multiple positions) - BBB
- Special Education Paraeducator (4 positions) - BHS, Burton, Pattengill, Rogers
- Permanent Building Substitute Teacher - Anderson
- Permanent Substitute Custodian - District
- Kids’ Zone Assistant Teachers (3 positions) - Angell, Pattengill, Rogers
- Middle School Football Coach - Anderson
- JV Girls Golf Coach - BHS
- Sideline Cheer JV Coach - BHS
Follow us on Social Media
Did you know the District has Facebook, Instagram, LinkedIn and YouTube pages? Follow us to see the latest news and photos!