Area C - Classrooms and Bathrooms
Completed:
- Certificate of Occupancy
- Health Department Inspection
- Final Clean
- Owner/Architect Punchlist
Area D - Classrooms, Bathrooms, and Kitchen
Completed:
- Certificate of Occupancy
- Owner/Architect Punchlist
- Final Clean
Area E - Gymnasium, Bathrooms, and Storage
Completed:
- Certificate of Occupancy
- Final Clean
- Owner/Architect Punchlist
Exterior and Building Envelope Improvements
Completed:
- 2nd lift of Asphalt
- Concrete Driveway Entrance
- Exterior Metal Panels
Ongoing:
- Generator Rough-in
Weather:
Construction days lost to weather this month: 0
Total construction days lost to weather: 0
Safety:
Lost time days: 0
Days worked without lost time accident: 100
Photos:
Project Team
Kraus-Anderson Construction Company
Ben Bauman | Superintendent | ben.baumann@krausanderson.com
Michael Veaderko | Project Manager | Michael.veaderko@krausanderson.com
Evan VanEps | Project Engineer | evan.vaneps@krausanderson.com
ISG, Inc.
Justin Steffl | ISG Senior Project Manager | justinsteffl@isginc.com
Kalob Hays | ISG Assistant Project Manager | kalob.hays@isginc.com