Westonka Middle School Construction Updates

Construction Updates

Work in August

Area A (Administrative Offices and Cafetorium)

  • Set plumbing fixtures
  • Flooring installation
  • Install doors and hardware
  • Mechanical, electrical, plumbing wall and ceiling finishes
  • Punch list and corrections

Area B (Gymnasium and Surrounding Classrooms)

  • Punch list and corrections

Area C (Media Center and Surrounding Classrooms)

  • Set plumbing fixtures
  • Mechanical, electrical, plumbing wall and ceiling finishes
  • Punch list and corrections

Roof

  • Install split system unit/condensing unit SS-1, SS-2, and SS-3
  • Parapet installation at canopy

Front Entry

  • Install drain tile and aggregate
  • Pour concrete sidewalk
  • Install canopy lights
  • Install ACM panels under canopy
  • Install new handrail
  • Landscaping installation

Safety

  • Lost Time Days: 0

Weather

  • Lost Time Days: 0

Photos

August 2025

Cafetorium
Entrance and Ramp
Gymnasiums
Hallway Murals
Media Center
Resource and DCD Rooms

July 2025

Area C
Front Entry

June 2025

Area A

May 2025

Prepping for work throughout the facility

Project Team

Kraus-Anderson Construction Company

Jason Peterson, Director of Business Development/Senior Project Manager

John Nordby, Project Manager

Fladger Phenix, Project Superintendent

Silvia Magana, Senior Project Coordinator

Wold Architects & Engineers

Paul Aplikowski, Partner

Andrew Dahlquist, Associate/Architect

Elizabeth Thordson, Architectural

Alex Ng, Mechanical Engineering

Sean McNamara, Electrical Engineering

Construction updates created and managed by Kraus-Anderson Construction