Construction Updates
Work in August
Area A (Administrative Offices and Cafetorium)
- Set plumbing fixtures
- Flooring installation
- Install doors and hardware
- Mechanical, electrical, plumbing wall and ceiling finishes
- Punch list and corrections
Area B (Gymnasium and Surrounding Classrooms)
- Punch list and corrections
Area C (Media Center and Surrounding Classrooms)
- Set plumbing fixtures
- Mechanical, electrical, plumbing wall and ceiling finishes
- Punch list and corrections
Roof
- Install split system unit/condensing unit SS-1, SS-2, and SS-3
- Parapet installation at canopy
Front Entry
- Install drain tile and aggregate
- Pour concrete sidewalk
- Install canopy lights
- Install ACM panels under canopy
- Install new handrail
- Landscaping installation
Safety
- Lost Time Days: 0
Weather
- Lost Time Days: 0
Photos
August 2025
July 2025
June 2025
May 2025
Project Team
Kraus-Anderson Construction Company
Jason Peterson, Director of Business Development/Senior Project Manager
John Nordby, Project Manager
Fladger Phenix, Project Superintendent
Silvia Magana, Senior Project Coordinator
Wold Architects & Engineers
Paul Aplikowski, Partner
Andrew Dahlquist, Associate/Architect
Elizabeth Thordson, Architectural
Alex Ng, Mechanical Engineering
Sean McNamara, Electrical Engineering
Construction updates created and managed by Kraus-Anderson Construction