Construction Updates
Work in Progress
- Overall Site
- Phase 1 (1st Floor): Flooring (large play and treatment area), hang and hardware doors
- Phase 1 (2nd Floor): Interior windows, flooring, painting
- Phase 2 (1st Floor)
- Phase 2 (2nd Floor)
Work Completed Since Last Update
- Overall Site
- Phase 1 (1st Floor): Swing hook steel framing, playscape installation (by Intermountain Playscapes), floor and wall tile (bathrooms and kitchen/dining), ceiling grid, taping and mudding walls, painting, casework and countertops, electrical fixtures, plumbing fixtures, HVAC fixtures
- Phase 1 (2nd Floor): Casework and countertops
- Phase 2 (1st Floor)
- Phase 2 (2nd Floor)
Work Upcoming Next Month
- Overall Site
- Phase 1 (1st Floor): Wall protection, pad out rooms, punch list
- Phase 1 (2nd Floor): Punch list
- Phase 2 (1st Floor): Selective demolition
- Phase 2 (2nd Floor): Selective demolition
This Month's Progress Photos
Previous Progress Photos
Weather
- Construction days lost to weather this month: 0 days
- Total construction days lost to weather: 0 days
Safety
- Lost time days: 0
- Days worked without lost time accident: 57
Project Timeline
- Bid and contract award: September 2025
- Construction start: October 2025
- Estimated construction completion: February 2026
Project Team
Kraus-Anderson Construction
Mike Stafford, Project Manager | 507-649-3011 | mike.stafford@krausanderson.com
Matt Mills, Project Foreman | matt.mills@krausanderson.com
Connor McGraw, Project Engineer | 507-910-1994 | connor.mcgraw@krausanderson.com
Katie Adelman, Project Coordinator | katie.adelman@krausanderson.com
Brandon Lawson, General Superintendent | brandon.lawson@krausanderson.com