Construction Updates
Work in Progress
Overall Site
Phase 1 (1st Floor)
- Punch List Completion
Phase 1 (2nd Floor)
- Punch List Completion
Phase 2 (1st Floor)
- Taping/Sanding Walls
- Painting/Priming Walls
Phase 2 (2nd Floor)
- Taping/Sanding Walls
- Painting/Priming Walls
Phase 2 (Small Play)
- Taping/Sanding Walls
- Painting/Priming Walls
- Painting Ceiling
Work Completed Since Last Update
Overall Site
Phase 1 (1st Floor)
- Tile
- Hang & Hardware Doors
- Flooring
- Plumbing Fixtures
- Bathroom Accessories
- Ceiling Tile
- Punch List
- Wall Protection
Phase 1 (2nd Floor)
- Casework & Countertops
- Hang & Hardware Doors
- Painting
- Interior Windows
- Flooring
- Punch List
Phase 2 (1st Floor)
- Interior Demolition
- Frame Walls & Soffit
- In-Wall MEP Rough-Ins
Phase 2 (2nd Floor)
- Interior Demolition
- Frame Soffits
- Drywall
Phase 2 (Small Play)
- Interior Demolition
- Wall Framing
- In-Wall MEP Rough-Ins
- Drywall
Work Upcoming Next Month
Overall Site
Phase 1 (1st Floor)
Phase 1 (2nd Floor)
Phase 2 (1st Floor)
Phase 2 (2nd Floor)
Phase 2 (Small Play)
This Month's Progress Photos
Previous Progress Photos
Weather
- Construction days lost to weather this month: 0 days
- Total construction days lost to weather: 0 days
Safety
- Lost time days: 0
- Days worked without lost time accident: 75
Project Timeline
- Bid and contract award: September 2025
- Construction start: October 2025
- Estimated construction completion: February 2026
Project Team
Kraus-Anderson Construction
Mike Stafford, Project Manager | 507-649-3011 | mike.stafford@krausanderson.com
Matt Mills, Project Foreman | matt.mills@krausanderson.com
Connor McGraw, Project Engineer | 507-910-1994 | connor.mcgraw@krausanderson.com
Katie Adelman, Project Coordinator | katie.adelman@krausanderson.com
Brandon Lawson, General Superintendent | brandon.lawson@krausanderson.com