Full Potential Therapy Construction Managed by Kraus-Anderson

Construction Updates

Work in Progress

  • Overall Site
  • Phase 1 (1st Floor): Flooring (large play and treatment area), hang and hardware doors
  • Phase 1 (2nd Floor): Interior windows, flooring, painting
  • Phase 2 (1st Floor)
  • Phase 2 (2nd Floor)

Work Completed Since Last Update

  • Overall Site
  • Phase 1 (1st Floor): Swing hook steel framing, playscape installation (by Intermountain Playscapes), floor and wall tile (bathrooms and kitchen/dining), ceiling grid, taping and mudding walls, painting, casework and countertops, electrical fixtures, plumbing fixtures, HVAC fixtures
  • Phase 1 (2nd Floor): Casework and countertops
  • Phase 2 (1st Floor)
  • Phase 2 (2nd Floor)

Work Upcoming Next Month

  • Overall Site
  • Phase 1 (1st Floor): Wall protection, pad out rooms, punch list
  • Phase 1 (2nd Floor): Punch list
  • Phase 2 (1st Floor): Selective demolition
  • Phase 2 (2nd Floor): Selective demolition

This Month's Progress Photos

Previous Progress Photos

November 2025
October 2025

Weather

  • Construction days lost to weather this month: 0 days
  • Total construction days lost to weather: 0 days

Safety

  • Lost time days: 0
  • Days worked without lost time accident: 57

Project Timeline

  • Bid and contract award: September 2025
  • Construction start: October 2025
  • Estimated construction completion: February 2026

Project Team

Kraus-Anderson Construction

Mike Stafford, Project Manager | 507-649-3011 | mike.stafford@krausanderson.com

Matt Mills, Project Foreman | matt.mills@krausanderson.com

Connor McGraw, Project Engineer | 507-910-1994 | connor.mcgraw@krausanderson.com

Katie Adelman, Project Coordinator | katie.adelman@krausanderson.com

Brandon Lawson, General Superintendent | brandon.lawson@krausanderson.com