About the Project:
RENDERINGS
CONSTRUCTION ACTIVITIES
Previous Month:
Building Related Activities
- Working to Wrap up structural steel and decking
- Finished Most of Area A, B, C Roof and started on at Gym and Kitchen Roof
- Slab pours at area B and north further into building
- Underground at kitchen and mechanical areas started
- Masonry and air barrier assembly continues around building
- Framing and MEP rough in continues at area C and started at D and E
- Drywall and taping began
- Continue to temp enclose areas of the building and condition spaces
- Continue building submittal and trade coordination
Site Related Activities
- Site mostly on hold until spring warmer temps
Upcoming Month:
Building Related Activities
- Wrap up decking and steel detail work throughout commons area
- Continue roofing at D Kitchen, E Gym and Begin on the commons area
- Slab pours at north area B and north further into building including kitchen and mechanical toom
- Wrap up Underground at kitchen and mechanical areas
- Masonry and air barrier assembly continues around building
- Framing and MEP rough in continues
- Drywall to continue following rough in
- Interior painting to begin
- Continue to temp enclose areas of the building and condition spaces
- Continue building submittal and trade coordination
Site Related Activities
- Site mostly on hold until spring warmer temps
Weather
- Total Affected Weather Working days: 66
Safety
- Lost Time Days: 0
Photos
February 2025
January 2025
October 2024
September 2024
August 2024
June 2024
Ground Breaking
Project Team
Kraus-Anderson Construction Company
Dustin Kempf, Senior Project Manager
Brian Johnson, Project Manager
Brian Kobow, Project Superintendent
Josh Prouty, Project Superintendent
Cassie Gillen, Project Coordinator
Wold Architects and Engineers
Lynae Schoen, Partner
Maria Kennedy, Project Manager
Amanda Moore, Architect