Gibbon-Fairfax-Winthrop CONSTRUCTION UPDATES

About the Project:

RENDERINGS

CONSTRUCTION ACTIVITIES

Previous Month:

Building Related Activities

  • Started windows
  • Started Casework
  • Started Tile
  • Finished storm shelter, kitchen and gym roofing
  • Slab pours at area F and kitchen
  • Hung drywall and started taping and sanding Area C
  • Masonry and air barrier assembly continues around building
  • Started prepping for framing on metal panels on perimeter of building
  • Started prepping slabs at commons area
  • Drywall and taping began

Site Related Activities

  • Resuming site balance and draintile activities

Upcoming Month:

Building Related Activities

  • Wrap up roofing at all areas of the building
  • Pour slab at commons area and work on gym slab
  • Wrap up building enclosure and masonry
  • Begin work on larger curtainwall windows
  • Paint and continue finishes at Area B offices
  • Paint and continue finishes at Area C High School Area
  • Build out locker room and music areas
  • Continue to build out main mechanical and electrical rooms
  • Continue to on permanent enclosure areas of the building and condition spaces

Site Related Activities

  • Start to prep and form stadium area
  • Continue site balance and final grading
  • Begin to prep on turn lane project

Weather

  • Total Affected Weather Working days: 74

Safety

  • Lost Time Days: 0

Photos

April 2025

February 2025

January 2025

October 2024

September 2024

August 2024

June 2024

Ground Breaking

Project Team

Kraus-Anderson Construction Company

Dustin Kempf, Senior Project Manager

Brian Johnson, Project Manager

Brian Kobow, Project Superintendent

Josh Prouty, Project Superintendent

Cassie Gillen, Project Coordinator

Wold Architects and Engineers

Lynae Schoen, Partner

Maria Kennedy, Project Manager

Amanda Moore, Architect