Gibbon-Fairfax-Winthrop CONSTRUCTION UPDATES

About the Project:

RENDERINGS

CONSTRUCTION ACTIVITIES

Work Completed:

Building Related Activities

  • Steel Began at Front Classroom Area
  • Continued Concrete Foundations Around Building
  • Continue Interior Plumbing Underground within Building
  • Begin underground electrical within building
  • Interior masonry began in bearing areas
  • Prepared site for precast
  • Continue submittal review and trade coordination

Site Related Activities

  • Utilities at East Lot Areas mostly complete
  • Shape road subgrade and parking lots at east and around building
  • Continue Rough Grading of Site as Weather Conditions allow
  • Continue Storm and Sanitary utility work at west and south
  • Excavate storm pond on north end
  • Place black dirt and begin to seed in some areas where weather conditions allow

Upcoming Work:

Building Related Activities

  • Concrete Foundation work continues at storm shelter and performance arts center
  • Steel continues north from classrooms into remaining building
  • Precast concrete work begins.
  • Plumbing Underground continues north within building
  • Masonry continues at kitchen areas
  • Roof steel at classroom areas to follow precast plank
  • Continue building submittal and trade coordination

Site Related Activities

  • Continue fine grading and shaping site
  • Continue placing black dirt at site areas where grade complete
  • Continue utilities west and connect into city water
  • Xcel permanent power connection and coordination

Weather

  • Total Affected Weather Working days: 45

Safety

  • Lost Time Days: 0

Photos

September 2024

August 2024

June 2024

Ground Breaking

Project Team

Kraus-Anderson Construction Company

Dustin Kempf, Senior Project Manager

Brian Johnson, Project Manager

Brian Kobow, Project Superintendent

Josh Prouty, Project Superintendent

Cassie Gillen, Project Coordinator

Wold Architects and Engineers

Lynae Schoen, Partner

Maria Kennedy, Project Manager

Amanda Moore, Architect