Gibbon-Fairfax-Winthrop CONSTRUCTION UPDATES

About the Project:

RENDERINGS

CONSTRUCTION ACTIVITIES

Work Completed:

Building Related Activities

  • Concrete foundation work started to wrap up
  • Precast concrete work began
  • Steel continued north from classrooms into remaining building
  • Plumbing Underground continues north within building
  • Classroom subbase installed
  • Masonry continued into at kitchen areas and elevator shaft
  • Roof steel and decking at classroom areas began
  • Cold form metal framing began at perimeter of classroom areas
  • Continue building submittal and trade coordination

Site Related Activities

  • Utilities at south and west mostly complete
  • Xcel brought power connections to the site.
  • Shape road subgrade and parking lots at east and south surrounding building
  • Continue Storm and Sanitary utility work at west and south
  • Tied into city water connections
  • Placed black dirt and grade where allows

Upcoming Work:

Building Related Activities

  • Finish backfilling within building area
  • Steel continues north from classrooms into remaining building
  • Precast concrete work continues north to gym and into storm shelter and performing arts
  • Plumbing Underground continues north within building
  • Masonry continues at kitchen areas
  • Roofing and parapet work to begin at classroom areas
  • Install sheathing at exterior cold form wall areas.
  • Begin to temp enclose areas of the building and condition spaces
  • Continue building submittal and trade coordination

Site Related Activities

  • Continue fine grading and shaping site
  • Continue placing black dirt at site areas where grade complete
  • Prep to stabilize site for winter
  • Bring gas line to building

Weather

  • Total Affected Weather Working days: 49

Safety

  • Lost Time Days: 0

Photos

October 2024

September 2024

August 2024

June 2024

Ground Breaking

Project Team

Kraus-Anderson Construction Company

Dustin Kempf, Senior Project Manager

Brian Johnson, Project Manager

Brian Kobow, Project Superintendent

Josh Prouty, Project Superintendent

Cassie Gillen, Project Coordinator

Wold Architects and Engineers

Lynae Schoen, Partner

Maria Kennedy, Project Manager

Amanda Moore, Architect