About the Project:
RENDERINGS
CONSTRUCTION ACTIVITIES
Previous Month:
Building Related Activities
- Finish installation on larger curtainwall windows
- Continue install of cabinets, glass, ceilings and other finishes at elementary classrooms
- Paint and continue finishes at Area C High School Area
- Paint and continue finishes at Commons and gym areas
- Begin exterior door frame installation
- Continue finishes in commons area
- Install hangar door frame at shop areas
- Continue to Build out locker room and music areas
- Continue to Build out kitchen areas with ongoing finishes
- Continue to build out main mechanical and electrical rooms
- Continue to infill exterior openings areas of the building and condition spaces
Site Related Activities
- Install curb and sidewalks around south road and lot
- Wrap up grandstand installation
- Install stadium lighting
- Continue base prep of stadium area
- Start grading at east lot and east walks
- Continue site balance and final grading
- Started work on turn lane
Upcoming Month:
Building Related Activities
- Install of exterior door assemblies
- Final paint and wrap up finishes in elementary areas
- Paint and wrap up finishes at Area B Offices
- Paint and continue finishes and cabinet install at Area C High School Area
- Paint and wrap up finishes at Commons and gym areas
- Prep slab at performing arts center
- Continue to Build out locker room and music areas
- Continue to Build out kitchen areas
- Fire up main mechanical and electrical rooms and systems
- Continue to infill exterior openings areas of the building and condition spaces
- Wrap up overhead work in gym and begin painting
Site Related Activities
- Turf installation at stadium
- Continue site walks, curb and gutter as well as asphalt
- Continue site final grading
- Wrap up work on turn lane project
Weather
- Total Affected Weather Working Days: 88
Safety
- Lost Time Days: 0
Photos
July 2025
June 2025
May 2025
April 2025
February 2025
January 2025
October 2024
September 2024
August 2024
June 2024
Ground Breaking
Project Team
Kraus-Anderson Construction Company
Dustin Kempf, Senior Project Manager
Brian Johnson, Project Manager
Brian Kobow, Project Superintendent
Josh Prouty, Project Superintendent
Cassie Gillen, Project Coordinator
Wold Architects and Engineers
Lynae Schoen, Partner
Maria Kennedy, Project Manager
Amanda Moore, Architect