Gibbon-Fairfax-Winthrop CONSTRUCTION UPDATES

About the Project:

RENDERINGS

CONSTRUCTION ACTIVITIES

Previous Month:

Building Related Activities

  • Finish installation on larger curtainwall windows
  • Continue install of cabinets, glass, ceilings and other finishes at elementary classrooms
  • Paint and continue finishes at Area C High School Area
  • Paint and continue finishes at Commons and gym areas
  • Begin exterior door frame installation
  • Continue finishes in commons area
  • Install hangar door frame at shop areas
  • Continue to Build out locker room and music areas
  • Continue to Build out kitchen areas with ongoing finishes
  • Continue to build out main mechanical and electrical rooms
  • Continue to infill exterior openings areas of the building and condition spaces

Site Related Activities

  • Install curb and sidewalks around south road and lot
  • Wrap up grandstand installation
  • Install stadium lighting
  • Continue base prep of stadium area
  • Start grading at east lot and east walks
  • Continue site balance and final grading
  • Started work on turn lane

Upcoming Month:

Building Related Activities

  • Install of exterior door assemblies
  • Final paint and wrap up finishes in elementary areas
  • Paint and wrap up finishes at Area B Offices
  • Paint and continue finishes and cabinet install at Area C High School Area
  • Paint and wrap up finishes at Commons and gym areas
  • Prep slab at performing arts center
  • Continue to Build out locker room and music areas
  • Continue to Build out kitchen areas
  • Fire up main mechanical and electrical rooms and systems
  • Continue to infill exterior openings areas of the building and condition spaces
  • Wrap up overhead work in gym and begin painting

Site Related Activities

  • Turf installation at stadium
  • Continue site walks, curb and gutter as well as asphalt
  • Continue site final grading
  • Wrap up work on turn lane project

Weather

  • Total Affected Weather Working Days: 88

Safety

  • Lost Time Days: 0

Photos

July 2025

June 2025

May 2025

April 2025

February 2025

January 2025

October 2024

September 2024

August 2024

June 2024

Ground Breaking

Project Team

Kraus-Anderson Construction Company

Dustin Kempf, Senior Project Manager

Brian Johnson, Project Manager

Brian Kobow, Project Superintendent

Josh Prouty, Project Superintendent

Cassie Gillen, Project Coordinator

Wold Architects and Engineers

Lynae Schoen, Partner

Maria Kennedy, Project Manager

Amanda Moore, Architect