View Static Version

Gibbon-Fairfax-Winthrop CONSTRUCTION UPDATES

About the Project:

RENDERINGS

CONSTRUCTION ACTIVITIES

Previous Month:

Building Related Activities

  • Working to Wrap up structural steel and decking
  • Finished Most of Area A, B, C Roof and started on at Gym and Kitchen Roof
  • Slab pours at area B and north further into building
  • Underground at kitchen and mechanical areas started
  • Masonry and air barrier assembly continues around building
  • Framing and MEP rough in continues at area C and started at D and E
  • Drywall and taping began
  • Continue to temp enclose areas of the building and condition spaces
  • Continue building submittal and trade coordination

Site Related Activities

  • Site mostly on hold until spring warmer temps

Upcoming Month:

Building Related Activities

  • Wrap up decking and steel detail work throughout commons area
  • Continue roofing at D Kitchen, E Gym and Begin on the commons area
  • Slab pours at north area B and north further into building including kitchen and mechanical toom
  • Wrap up Underground at kitchen and mechanical areas
  • Masonry and air barrier assembly continues around building
  • Framing and MEP rough in continues
  • Drywall to continue following rough in
  • Interior painting to begin
  • Continue to temp enclose areas of the building and condition spaces
  • Continue building submittal and trade coordination

Site Related Activities

  • Site mostly on hold until spring warmer temps

Weather

  • Total Affected Weather Working days: 66

Safety

  • Lost Time Days: 0

Photos

February 2025

January 2025

October 2024

September 2024

August 2024

June 2024

Ground Breaking

Project Team

Kraus-Anderson Construction Company

Dustin Kempf, Senior Project Manager

Brian Johnson, Project Manager

Brian Kobow, Project Superintendent

Josh Prouty, Project Superintendent

Cassie Gillen, Project Coordinator

Wold Architects and Engineers

Lynae Schoen, Partner

Maria Kennedy, Project Manager

Amanda Moore, Architect

NextPrevious