About the Project:
RENDERINGS
CONSTRUCTION ACTIVITIES
Previous Month:
Building Related Activities
- Started windows
- Started Casework
- Started Tile
- Finished storm shelter, kitchen and gym roofing
- Slab pours at area F and kitchen
- Hung drywall and started taping and sanding Area C
- Masonry and air barrier assembly continues around building
- Started prepping for framing on metal panels on perimeter of building
- Started prepping slabs at commons area
- Drywall and taping began
Site Related Activities
- Resuming site balance and draintile activities
Upcoming Month:
Building Related Activities
- Wrap up roofing at all areas of the building
- Pour slab at commons area and work on gym slab
- Wrap up building enclosure and masonry
- Begin work on larger curtainwall windows
- Paint and continue finishes at Area B offices
- Paint and continue finishes at Area C High School Area
- Build out locker room and music areas
- Continue to build out main mechanical and electrical rooms
- Continue to on permanent enclosure areas of the building and condition spaces
Site Related Activities
- Start to prep and form stadium area
- Continue site balance and final grading
- Begin to prep on turn lane project
Weather
- Total Affected Weather Working days: 74
Safety
- Lost Time Days: 0
Photos
April 2025
February 2025
January 2025
October 2024
September 2024
August 2024
June 2024
Ground Breaking
Project Team
Kraus-Anderson Construction Company
Dustin Kempf, Senior Project Manager
Brian Johnson, Project Manager
Brian Kobow, Project Superintendent
Josh Prouty, Project Superintendent
Cassie Gillen, Project Coordinator
Wold Architects and Engineers
Lynae Schoen, Partner
Maria Kennedy, Project Manager
Amanda Moore, Architect