About the Project:
RENDERINGS
CONSTRUCTION ACTIVITIES
Work Completed:
Building Related Activities
- Steel Began at Front Classroom Area
- Continued Concrete Foundations Around Building
- Continue Interior Plumbing Underground within Building
- Begin underground electrical within building
- Interior masonry began in bearing areas
- Prepared site for precast
- Continue submittal review and trade coordination
Site Related Activities
- Utilities at East Lot Areas mostly complete
- Shape road subgrade and parking lots at east and around building
- Continue Rough Grading of Site as Weather Conditions allow
- Continue Storm and Sanitary utility work at west and south
- Excavate storm pond on north end
- Place black dirt and begin to seed in some areas where weather conditions allow
Upcoming Work:
Building Related Activities
- Concrete Foundation work continues at storm shelter and performance arts center
- Steel continues north from classrooms into remaining building
- Precast concrete work begins.
- Plumbing Underground continues north within building
- Masonry continues at kitchen areas
- Roof steel at classroom areas to follow precast plank
- Continue building submittal and trade coordination
Site Related Activities
- Continue fine grading and shaping site
- Continue placing black dirt at site areas where grade complete
- Continue utilities west and connect into city water
- Xcel permanent power connection and coordination
Weather
- Total Affected Weather Working days: 45
Safety
- Lost Time Days: 0
Photos
September 2024
August 2024
June 2024
Ground Breaking
Project Team
Kraus-Anderson Construction Company
Dustin Kempf, Senior Project Manager
Brian Johnson, Project Manager
Brian Kobow, Project Superintendent
Josh Prouty, Project Superintendent
Cassie Gillen, Project Coordinator
Wold Architects and Engineers
Lynae Schoen, Partner
Maria Kennedy, Project Manager
Amanda Moore, Architect