This image is a project rendering and does not depict the completed facility. Actual construction may vary.
Construction Updates
Work in Progress
Overall Site
- Site removals and sitework demo
Area A1 (CTE Addition)
Area A2 (Locker Rooms & Welding Shop)
- Abatement
- Plumbing demolition
- Interior demolition
Area B1 (Lobby Addition)
Area B2 (Existing Hallway & Woodshop Renovations)
Area B3 (Gymnasium)
- Floor protection installation
- Abatement
Area D (2nd Floor Classrooms)
Work Completed Since Last Update
Overall Site
Area A1 (CTE Addition)
Area A2 (Locker Rooms & Welding Shop)
- Locker and bench salvage
- MEP removals
Area B1 (Lobby Addition)
Area B2 (Existing Hallway & Woodshop Renovations)
Area B3 (Gymnasium)
Area D (2nd Floor Classrooms)
- Abatement
Work Upcoming Next Month
Overall Site
Area A1 (CTE Addition)
- Foundation Excavation, Form, & Pour
- Masonry Walls
Area A2 (Locker Rooms & Welding Shop)
- Abatement
- Demolition (Rooftop)
- Set Rooftop Mechanical Curbs
- Roofing Insulation, Membrane, & Flashing
- Interior Framing
- Masonry Walls
- MEP Rough-Ins
- Drywall, Taping, and Sanding
- Painting
- Ceramic Tile
Area B1 (Lobby Addition)
- Foundation Excavation, Form, & Pour
- Underground MEP Installation
- Foundation Backfill
- Structural Steel
- Roofing Insulation & Membrane
- Slab on Grade
Area B2 (Existing Hallway & Woodshop Renovations)
- Abatement
- Demolition (Interior & Rooftop)
- Set Rooftop Mechanical Curbs
- Roofing Insulation, Membrane, & Flashing
- Set Masonry Walls
- MEP Rough-Ins
- Prime/Paint
- Ceiling Grid
- Flooring
Area B3 (Gymnasium)
- Floor Protection Installation
- Abatement
- Demolition
- Set Masonry Walls
- MEP Rough-Ins
Area D (2nd Floor Classrooms)
- Abatement
- Demolition (Interior & Rooftop)
- Set Rooftop Mechanical Curbs
- Roofing Insulation, Membrane, & Flashing
- Interior Framing
- MEP Rough-Ins
Project Progress Photos
May 2026
Area B1
Area B2
Project Rendering Photos
Construction Phasing Schedule
- Bid and contract award: February 2026
- Construction start: May 2026
- Estimated construction completion: November 2026
Weather
- Construction days lost to weather this month: 0
- Total construction days lost to weather: 0
Safety
- Lost time days: 0
- Days worked without lost time accident: 3 working days
Project Team
Kraus-Anderson Construction Company
Charlie Sweeney, Project Manager | 507-316-4380 | charlie.sweeney@krausanderson.com
Ryan Ramaker, Project Superintendent | 507-208-2869 | ryan.ramaker@krausanderson.com
Connor McGraw, Project Engineer | 507-910-1994 | connor.mcgraw@krausanderson.com
Katie Reinhart, Project Coordinator | katie.reinhart@krausanderson.com
ISG
Charlotte Nienhaus, Senior Architect | charlotte.nienhaus@ isginc.com
Justin Steffl, Business Unit Executive, Education | justin.steffl@isginc.com
Zach Hoeth, Assistant Project Manager | zach.hoeth@isginc.com
Morgan Anderson, Education Planning Specialist | morgan.anderson@isginc.com
Construction updates created and managed by Kraus-Anderson Construction