Construction Updates (through May 22, 2026)

This image is a project rendering and does not depict the completed facility. Actual construction may vary.

Construction Updates

Work in Progress

Overall Site

Area A1 (CTE Addition)

Area A2 (Locker Rooms & Welding Shop)

Area B1 (Lobby Addition)

Area B2 (Existing Hallway & Woodshop Renovations)

Area B3 (Gymnasium)

Area D (2nd Floor Classrooms)

Work Completed Since Last Update

Overall Site

Area A1 (CTE Addition)

Area A2 (Locker Rooms & Welding Shop)

Area B1 (Lobby Addition)

Area B2 (Existing Hallway & Woodshop Renovations)

Area B3 (Gymnasium)

Area D (2nd Floor Classrooms)

Work Upcoming Next Month

Overall Site

Area A1 (CTE Addition)

  • Foundation Excavation, Form, & Pour
  • Masonry Walls

Area A2 (Locker Rooms & Welding Shop)

  • Abatement
  • Demolition (Interior & Rooftop)
  • Set Rooftop Mechanical Curbs
  • Roofing Insulation, Membrane, & Flashing
  • Interior Framing
  • Masonry Walls
  • MEP Rough-Ins
  • Drywall, Taping, and Sanding
  • Painting
  • Ceramic Tile

Area B1 (Lobby Addition)

  • Foundation Excavation, Form, & Pour
  • Underground MEP Installation
  • Foundation Backfill
  • Structural Steel
  • Roofing Insulation & Membrane
  • Slab on Grade

Area B2 (Existing Hallway & Woodshop Renovations)

  • Abatement
  • Demolition (Interior & Rooftop)
  • Set Rooftop Mechanical Curbs
  • Roofing Insulation, Membrane, & Flashing
  • Set Masonry Walls
  • MEP Rough-Ins
  • Prime/Paint
  • Ceiling Grid
  • Flooring

Area B3 (Gymnasium)

  • Floor Protection Installation
  • Abatement
  • Demolition
  • Set Masonry Walls
  • MEP Rough-Ins

Area D (2nd Floor Classrooms)

  • Abatement
  • Demolition (Interior & Rooftop)
  • Set Rooftop Mechanical Curbs
  • Roofing Insulation, Membrane, & Flashing
  • Interior Framing
  • MEP Rough-Ins

Project Progress Photos

April 2026

North and South Views of Existing Building

Project Rendering Photos

Lobby and CTE Addition

Construction Phasing Schedule

  • Bid and contract award: February 2026
  • Construction start: May 2026
  • Estimated construction completion: November 2026

Weather

  • Construction days lost to weather this month: 0
  • Total construction days lost to weather: 0

Safety

  • Lost time days: 0
  • Days worked without lost time accident: 0 working days

Project Team

Kraus-Anderson Construction Company

Charlie Sweeney, Project Manager | 507-316-4380 | charlie.sweeney@krausanderson.com

Ryan Ramaker, Project Superintendent | 507-208-2869 | ryan.ramaker@krausanderson.com

Connor McGraw, Project Engineer | 507-910-1994 | connor.mcgraw@krausanderson.com

Katie Reinhart, Project Coordinator | katie.reinhart@krausanderson.com

ISG

Charlotte Nienhaus, Senior Architect | charlotte.nienhaus@ isginc.com

Justin Steffl, Business Unit Executive, Education | justin.steffl@isginc.com

Zach Hoeth, Assistant Project Manager | zach.hoeth@isginc.com

Morgan Anderson, Education Planning Specialist | morgan.anderson@isginc.com

Construction updates created and managed by Kraus-Anderson Construction