Office and Classroom
Completed:
- Final Clean
- Temporary Certificate of Occupancy
- Ceiling Grid
- Casework
- Flooring
- Storefronts
- Painting
- Wall & Floor Tile
Ongoing:
- Punchlist Items
Site Improvements
Completed:
- New Sidewalk
- Final Grade
- Curbs & Gutters
- Pavement
Ongoing:
- Trash Enclosure Fence/Gate
- Curb & Gutters
- Relocation of Flagpole
- Landscaping & Irrigation
- Canopy Finishes
- Salvage of Flag Pole
New Office Space and Secure Entry
Completed:
- Temporary Certificate of Occupancy
- Taping
- Painting
- Wall & Floor Tile
- Windows
- Casework
- Flooring
- Fiber Cement Siding
- Masonry
Ongoing:
- Punchlist
Weather
- Construction Days lost to Weather This Month: 0
- Total Construction Days lost to Weather: 0
Safety
- Lost Time Days: 0
- Days Worked Wihout Lost Time Accident: 6