Otis Public Library building project web page | Updated October 23, 2025

This site is centered on communicating the status of the library project with the community. Updates will be posted as soon as they become available. If you have any questions, please post them in the public Q&A section.

Project Summary & Current Status

The project entails constructing a new library to support the community. We are currently in the feasibility phase. The OPM, Downes Construction, was selected in April, and the architect, TSKP Studio, was selected in late-July. The architect is currently working on an analysis of the potential library sites.

August 26, 2025 - The selectboard unanimously voted to move forward with the site on East Otis Road, also known as the Crandall site. The site is not owned by the Town, and must be purchased.

September 9, 2025 - The Crandall site is no longer available. The selectboard held on a decision regarding the other two town-owned properties. Additionally, a citizen's petition was put forward to stop the feasibly phase of the project. If successful, the town may be liable to the State for grant money used to date, and potentially interest.

September 23, 2025 - The selectboard unanimously voted to move forward with West Center Road site. The OPM and Design team are now mobilizing for the next phase of the study.

Citizen Petition - Get Out and Vote

On October 23rd the Town of Otis is holding a Special Town Meeting to vote on a citizens' petition. The petition is intended to withdraw from the MBLC grant. This petition, if approved, would either stop this phase directly after the vote or directly after the scheduled design report is submitted at the end of December. Additionally, if the grant is withdrawn early, the Town could be liable to reimburse the State for monies used to date, with the potential for interest. It is in the best financial interest of the Town to allow for the completion of this phase of the grant and hold a Town vote in the Spring of 2026 to proceed with the next phase of design and construction. Please note that this phase of the grant only allows the team to complete the Schematic Design; it does not guarantee that the project moves forward. Below is the warrant for review and how to vote:

Community Engagement

More dates coming soon. In the meantime, stop by the library, say hello, and let's talk about the project!

Site Review Information

Site Selection Information

First Glance Community Meeting

Current Project Schedule

Current Project Schedule

The feasibility phase will be completed by December 5, 2025 and submitted to the Massachusetts Board of Library Commissioners before December 31, 2025 for review. Below is the current milestone schedule:

Dates are conceptual and may be adjusted.
Questions & Answers
Informational Documents