130,000 SF, two-story new PK-12 school.
Construction Updates
Current Updates: Building Exterior
- Permanent Power has been brought to the building and has been distributed to each area.
- We are targeting our Air Handling Unit start up for September 9th.
- Flooring will resume in area B and A starting this week.
- Lockers and Auditorium Seating are scheduled to start 9/16/24.
- Learning Stairs will be installed 9/23/24, then moving to the stage install.
- We are final cleaning areas of the building that are complete. (Area C&D)
- Parking lot paving, lighting, markings, signage, and outdoor equipment is on-going.
- We are currently grading the practice football field.
Weather
- Construction Days lost to Weather This Month: 0 in January
- Total Construction Days lost to Weather: 8 total