Stillwater High School Construction Activities Progress | April 2025

Office Addition

Work in Progress:

  • Pouring Footings and Foundation Walls

Work Completed:

  • Demolition, including Mechanical and Electrical
  • Excavated for Footings

Work Upcoming Next Month:

  • Backfill Foundations
  • Underground Plumbing
  • Lay Exterior Concrete Masonry Units (CMU)
  • Pour Concrete Slab
  • Spray Weather Barrier
  • Lay Exterior Brick
  • Erect Structural Steel, Joists and Decking
  • Complete Roof Blocking
  • Begin Roofing
  • Begin Interior Metal Stud Framing

Office Renovation

Work in Progress:

Work Completed:

Work Upcoming Next Month:

Summer Renovations

Work in Progress:

Work Completed:

Work Upcoming Next Month:

Stadium Improvements

Work in Progress:

Work Completed:

Work Upcoming Next Month: