Roosevelt Elementary CONSTRUCTION UPDATES

Addition

Area A - Storm Shelter Classrooms

Completed:

  • Roofing
  • Gypsum Wall Board
  • Exterior Face Brick

Upcoming:

  • Sand, Tape, Finish
  • Interior Painting
  • Installation of Casework

Area B - New Entry

Completed:

  • Aluminum Storefront Frames and Glazing
  • Casework
  • Flooring

Upcoming:

  • Space Complete

Renovation

Area B- Bathrooms

Completed:

  • All interior restrooms are complete

Upcoming:

  • Space Complete

Exterior & Building Envelope Improvements

Completed:

  • Asphalt Parking Lot Patching
  • Sod and Landscape Plantings

Weather:

Construction days lost to weather this month: 2

Total construction days lost to weather: 4

Safety:

Lost Time Days: 0

Days Worked Without Lost Time Accident: 119

Photos:

Area A - Exterior
Area A Smart Room
EArea A Kindergarten
Area A Corridor
Area A Storage
Area A Bathroom

Project Team

Kraus-Anderson Construction Company

Bob Gavin | Superintendent | robert.gavin@krausanderson.com

John Nordby | Project Manager | robert.gavin@krausanderson.com

ISG, Inc.

Justin Steffl | ISG Senior Project Manager | justinsteffl@isginc.com

Kalob Hays | ISG Assistant Project Manager | kalob.hays@isginc.com