Wabasha-kellogg school district Construction Updates

Wabasha-Kellogg Schools, located at 2113 Hiawatha Drive East in Wabasha, Minnesota, is undergoing a comprehensive $16.2 million renovation aimed at enhancing both safety and educational opportunities for students. The project features major updates to several key areas of the school building, including a full remodel of the Career and Technical Education (CTE) labs and science labs to support hands-on learning and modern curriculum needs. Restrooms and the media center will also be upgraded to provide more accessible, comfortable, and technologically equipped spaces for students and staff.

In addition to academic spaces, the renovation will include the installation of a partially new roof and a state-of-the-art fire alarm system to improve overall building safety. A secure entry system will be implemented to enhance school security and ensure controlled access to the facility. The heating, ventilation, and air conditioning (HVAC) systems will also be upgraded, improving energy efficiency and climate control throughout the building. These updates reflect the district’s ongoing commitment to providing a safe, innovative, and future-ready learning environment for all students.

Floor Plan

30-Day Construction Activities Progress (July/August)

Area A

Work in progress

  • Dry wall, taping, sanding, and painting are approximately 90% complete
  • Flooring is in progress throughout Area A - approximately 95% complete
  • Casework is being installed - approximately 45% complete
  • Final cleaning is ongoing - approximately 75% complete
Main High School Office
High School Office Corridor

completed work

  • All new windows have been installed
  • Light fixtures are installed
  • Furniture has been installed/placed in classrooms as needed
  • Ceiling grid/tile has been completed
  • Lockers have been installed
Area A Media Center Corridor

planned for next month

  • School starts

Area B

work in progress

  • Dry wall, taping, sanding, and painting are approximately 90% complete
  • New flooring and wall base installation in progress - approximately 90% complete
  • Casework is being installed - approximately 45% complete
  • Final cleaning is ongoing - approximately 75% complete
Media Center
Science Room

Completed work

  • Locker installation is complete
  • Acoustical ceiling grid/tile has been installed
  • New windows are installed
  • Framing of new interior walls are complete
  • New door frames/storefronts are installed
  • Ceramic tile installation has been completed
  • Light Fixtures have been installed
  • Furniture has been install/placed in classrooms as needed
Area B Skylight
Area B Classroom
Area B Bathroom

planned for next month

  • School starts
Locker Bay
District Office

Area C - Choir Room

work in progress

  • Taping/Sanding/Painting - approximately 95% complete

completed work

  • All demolition of existing finishes
  • Framing of new walls
  • Installation of new door frames
  • MEP rough-ins
Choir Room
Staff Workroom

planned for next month

  • Ceiling panel installation

Roof

work in progress

  • Roof cleanup and construction debris removal

completed work

  • Install of roof hatch
  • Skylight installation
  • Installation of new curbs
  • Roof structural steel reinforcement for skylight and new mechanical equipment
  • Installation of skylights are complete
  • Roof Area C work in progress
  • Area B1 roof complete
  • Area B2 roof complete

planned for next month

  • Hoisting and setting of new RTU equipment

Schedule

  • Bid and contract award: March 2024
  • Estimated construction start: Spring/Summer 2024
  • Estimated construction completion: August 2025

Weather Impact

  • Construction days lost this month: 4
  • Total construction days lost due to weather: 5

Safety

  • Lost time incidents: 0
  • Days worked without a lost time accident: 63

Project Team

Kraus-Anderson Construction Company

Shawn Lortscher, Director of Operations | (507) 208-5692 | shawn.lortscher@krausanderson.com

Chad Pike, Director, Project Planning & Development | (507) 450-8232 | chad.pike@krausanderson.com

Brad Schoeppner, Senior Project Manager | (507) 316-2770 | brad.schoppner@krausanderson.com

Matt Hollermann, Project Manager | (507) 910-4701 | matt.hollermann@krausanderson.com

Brandon Lawson, General Superintendent | (507) 421-9324 | brandon.lawson@krausanderson.com

Heath Loy, Project Superintendent | (507) 316-7916 | heath.loy@krausanderson.com

Katie Reinhart, Project Coordinator | (507) 218-3857 | katie.reinhart@krausanderson.com

Ben Leimer, Project Engineer Intern | ben.leimer@krausanderson.com

ISG Architects and Engineers

Carter Burroughas, Project Administrator | (507) 779-9921 | carter.burroughas@ISGinc.com

Luke Papillion, Assistant Project Manager | (952) 426-0699 | luke.papillion@ISGinc.com

Courtney Rosenthal, Interior Design | (952) 426-0699 | courtney.rosenthal@ISGinc.com

Chad Martin, Senior Mechanical Engineer | (952) 426-0699 | chad.martin@ISGinc.com

Casey Larsen, Electrical Engineer | (605) 274-6401) | casey.larsen@ISGinc.com

Construction updates created and managed by Kraus-Anderson Construction