Wabasha-kellogg school district

Construction Updates

Wabasha-Kellogg Schools, located at 2113 Hiawatha Drive East in Wabasha, Minnesota, is undergoing a comprehensive $16.2 million renovation aimed at enhancing both safety and educational opportunities for students. The project features major updates to several key areas of the school building, including a full remodel of the Career and Technical Education (CTE) labs and science labs to support hands-on learning and modern curriculum needs. Restrooms and the media center will also be upgraded to provide more accessible, comfortable, and technologically equipped spaces for students and staff.

In addition to academic spaces, the renovation will include the installation of a partially new roof and a state-of-the-art fire alarm system to improve overall building safety. A secure entry system will be implemented to enhance school security and ensure controlled access to the facility. The heating, ventilation, and air conditioning (HVAC) systems will also be upgraded, improving energy efficiency and climate control throughout the building. These updates reflect the district’s ongoing commitment to providing a safe, innovative, and future-ready learning environment for all students.

Floor Plan

30-Day Construction Activities Progress (June/July)

Area A (High School Front Entry)

Work in progress

  • Front entry way demolition has started

completed work

  • Fire shutters in high school office have been installed
Area A Fire Shutter Door

planned for next month

Area C

work in progress

  • MEP rough-ins have started
  • Wall/sofit framing has started
  • Demolition of common area and wood sofit
  • Refinishing of the gym floor is in process
Refinished Gym Floor

completed work

  • Kitchen equipment demolition has been completed
  • MEP demolition has been completed
  • Kitchen flooring abatement has wrapped up
  • Restrooms/Corridors demolition has been completed
  • Refinishing of the gym floor has been completed

planned for next month

  • Drywall/Tape/Sanding/Paint will all start next month
  • MEP finishes will be installed
  • Ceiling installation will be started
  • Flooring in the kitchen will start
  • Kitchen equipment installation
  • Restroom tile to start
High School Gym Sofit

Area D

work in progress

  • Concrete floor removals
  • MEP rough installation
Area D Flex Room

completed work

  • Existing demolition has been completed

planned for next month

  • Concrete floor in-fills
  • Drywall patching
  • Paint touch-ups
  • MEP finishes
  • Ceiling installation
  • Floor installation

Area E: Lower Level Elementary

Work in Progress

  • The new masonry wall installation has started
  • Classroom refresh (New Flooring/Painting) has started
  • MEP above-grade rough installation has started
Area E Bathrooms

Completed Work

  • Concrete slab cutting has been completed
  • MEP in floor rough-ins have been completed
  • All existing demolition has been completed
Area E Library
Area E Offices

Planned for Next Month

  • New metal stud wall framing will be installed
  • MEP rough-in installation will start
  • Drywall and wall finishes will start
  • Storefronts will start to be installed
  • Ceilings will be installed/re-installed

Area F

Work in progress

  • Reinstall process of salvaged MEP and Partitions is underway
  • Framing/Drywall installation started
  • Ceramic tile installation has started

completed work

  • Wall/MEP/Casework/Flooring demolition has all been completed
  • Classroom refinishes (New flooring/Paint) Has been completed

planned for next month

  • New metal stud wall framing will be installed
  • MEP rough-in installation will start
  • Drywall and wall finishes will start
  • Storefronts will start to be installed
  • Ceilings will be installed/re-installed

Roof

Work in progress

  • Area A - reroofing next to auditorium
  • Area C - reroofing over the kitchen and commons area
  • Area D – Reroofing over CTE

completed work

  • Roof rock removal has been completed
  • Old roof top units have been removed

planned for next month

  • Install new roofing
  • Install new roof top units

Schedule

  • Bid and contract award: March 2024
  • Phase 1 construction completion: August 2025
  • Phase 2 construction start date: June 2026
  • Phase 2 estimated construction end date: August 2026

Weather Impact

  • Construction days lost this month: 0
  • Total construction days lost due to weather: 0

Safety

  • Lost time incidents: 0
  • Days worked without a lost time accident: 19

Project Team

Kraus-Anderson Construction Company

Shawn Lortscher, Director of Operations | (507) 208-5692 | shawn.lortscher@krausanderson.com

Chad Pike, Director, Project Planning & Development | (507) 450-8232 | chad.pike@krausanderson.com

Brad Schoeppner, Senior Project Manager | (507) 316-2770 | brad.schoppner@krausanderson.com

Matt Hollermann, Project Manager | (507) 910-4701 | matt.hollermann@krausanderson.com

Brandon Lawson, General Superintendent | (507) 421-9324 | brandon.lawson@krausanderson.com

Micah Davis, Project Superintendent | (507) 316-5173 | micah.davis@krausanderson.com

Katie Reinhart, Project Coordinator | (507) 218-3857 | katie.reinhart@krausanderson.com

Ben Leimer, Project Engineer Intern | (507) 993-0961 | ben.leimer@krausanderson.com

ISG Architects and Engineers

Carter Burroughas, Project Administrator | (507) 779-9921 | carter.burroughas@ISGinc.com

Luke Papillion, Assistant Project Manager | (952) 426-0699 | luke.papillion@ISGinc.com

Courtney Rosenthal, Interior Design | (952) 426-0699 | courtney.rosenthal@ISGinc.com

Chad Martin, Senior Mechanical Engineer | (952) 426-0699 | chad.martin@ISGinc.com

Casey Larsen, Electrical Engineer | (605) 274-6401) | casey.larsen@ISGinc.com

Construction updates created and managed by Kraus-Anderson Construction