Westonka Public Schools 2024 Construction updates

Primary Schools Security Improvements

Shirley Hills Primary School

Completed

  • Walls with Doors/Frames/Hardware
  • Door Security
  • Ceilings at Doors/Frames/Hardware
Tech and Security New Door and Frames Installed
Tech and Security at Shirley Hills Primary School

Hilltop Primary School

Completed

  • Door Security

Upcoming

  • Replacement Panels for Security Glazing Replacement

Westonka Tennis Courts and Bus Garage

Tennis Courts

Completed

  • Post Tension Concrete Courts
  • Site Concrete
  • Tree Plantings
  • Sheds
  • Asphalt Paving
  • Shade Structure Framing
  • Landscaping

Upcoming

  • Fence and Fencing Slats
  • Punch List
  • Electrical Panel

Bus Garage

Completed

  • Masonry Lintel replacement at Bus Garage
  • Light Fixture Replacement at Existing Bus Garage
  • Exterior Painting of South Elevation
New Asphalt, Looking at Existing Bus Garage
New Asphalt, Looking Toward Sunnyfield Rd
New Electrical Transformer set by Xcel Energy
New Light Fixtures, at Bus Garage
Parking Lot Stripes are Completed.
Post Tension Concrete Tennis Courts
Shed
Sidewalk Leading to Tennis Courts and Parking Lot Boundry
Site Concrete Between Courts and Fence Posts
Site Concrete, Walkable Area Between Courts

Weather

Construction Days lost to Weather This Month: 2

Total Construction Days lost to Weather: 3

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 114

Construction updates created and managed by Kraus-Anderson Construction