Westonka Tennis Courts 2025 Construction updates

Construction Updates

Work in May

  • Punch list items (sidewalk/concrete repairs)
  • Perimeter and joint caulking
  • Tennis court surface leveling and grinding
  • Court surfacing applications

Work in June

  • Continue tennis court surfacing applications
  • 5 day cure time
  • Scoreboard installation
  • Final walkthrough with Westonka Public Schools, Wold, Larson Engineering, and Kraus-Anderson

Weather

Construction Days lost to Weather This Month: 2

Total Construction Days lost to Weather: 3

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 114

Construction updates created and managed by Kraus-Anderson Construction