Monroe Elementary School CONSTRUCTION UPDATES | SEPTEMBER 2025

Construction Updates

Addition/Renovation

Completed:

  • Mobilization
  • Abatement
  • Demo
  • Temp Enclosure
  • Frame Walls/Ceiling
  • Backing/Blocking
  • MEP Rough-in Walls
  • MEP Above Ceiling
  • Insulation/Drywall
  • Taping/Mudding
  • Fire Caulking
  • Mech & Plumbing IN Crawl Space
  • Carpet/LVT
  • Ceiling Grid
  • Doors/Hardware
  • Store Front Install
  • Casework
  • Mechanical Finishes
  • Electrical Finishes
  • Plumbing Finishes
  • Bollard Signs
  • Paint
  • TAB
  • Punch List Walk
  • Punchlist Completion
  • Final Clean

Upcoming:

  • Tile Correction (MEA Break)
  • 11-Month Warranty Walk

Photos

Front Entry
Main Entry and Vestibule
Main Entrance Storefront
Main Office
Nurse's Office
Back Office

Weather

Construction Days Lost to Weather This Month: 0

Total Construction Days Lost to Weather: 0

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 30

Project Team

Kraus-Anderson Construction Company

Randy Hancock | Project Superintendent | randy.hancock@krausanderson.com

Dale Sonnichsen | Project Manager | dale.sonnichsen@krausanderson.com

Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com

I&S Group

Carter Burroughs | Carter.Burroughs@ISGInc.com

Kyle Fisel | Kyle.Fisel@ISGInc.com