About George T. Nasuti Elementary
The Woonsocket Education Department, in collaboration with the Rhode Island Department of Education is proud to advance a design-build project that will bring a new elementary school to Barry Field at 44 Smithfield Road in Woonsocket, Rhode Island. This thoughtfully planned 133,000-square-foot facility will occupy approximately half of the Barry Field site, balancing educational needs with preservation of community open space. Designed as a welcoming hub for students, families, and the broader Woonsocket community, the new school will support high-quality learning while also providing shared spaces for gatherings, performances, and events. The building program includes modern academic classrooms, staff and administrative areas, a music room, a media center, a medical suite, and student support spaces. Community-oriented features such as a cafeteria with an integrated stage and a full gymnasium will offer flexible spaces that can serve both school and neighborhood activities. A complete kitchen and back-of-house operations will support daily use and special events alike. Sustainability and student wellness are central to the project’s vision. The school will be designed in accordance with NE-CHPS Version 4.0 standards, promoting energy efficiency, healthy indoor environments, and long-term operational savings that benefit the entire community. Additionally, Woonsocket’s commitment to creating a safe, inspiring, and enduring learning environment—one that strengthens neighborhood connections and supports generations of students and families to come.
Project Highlights
- Project Type: Design-Build
- Construction Budget: $80,791,559
- Grade Levels: Pre-Kindergarten through 4th Grade
- Building Size: Approx. 133,000 ft²
- Location: Barry Field, 44 Smithfield Road, Woonsocket, RI
- Overall Project Schedule: May 23, 2024 - August 28, 2027
- Current Phase: Construction
The Woonsocket Education Department, in collaboration with the Rhode Island Department of Education, and Downes Construction Company (acting as the Owner's Project Manager), has established the Woonsocket Capital Planning Team. This dedicated team convenes weekly on Mondays at 9:15 AM to comprehensively review and discuss every facet of the ongoing project. Their agenda covers a wide array of critical topics, including the project schedule, requests for proposals, requests for information, budget considerations, documentation requirements, and much more, ensuring thorough oversight and strategic planning at every stage. Below is a list of the team members who are integral to this collaborative effort.
Significant Milestones:
- Groundwork started on October 22, 2025.
- Footings are being poured for the foundation.
- Steel work to start in early April 2026.
- Beam signing and Topping-Off Ceremony occurred in June 2026
- Steel to be completed during the second week of June 2026
Beam Signing Ceremony
6/4/26 George T. Nasuti's family and friends signing the beam
6/10/26 Bernon Heights Elementary School
6/11/26 Topping-Off Ceremony
Speakers included Woonsocket Education Department Superintendent Dr. Patrick McGee, Woonsocket School Committee Chairman Paul Bouret, Woonsocket City Counsel President Daniel Gendron, RIDE Commissioner Angelica Infante-Green, and the Mayor of Woonsocket Christopher Beauchamp.
Project Updates
Summer 2026
June 2026
The current construction progress consists of the completion of structural steel in wings A and B, installation on wing C is ongoing with an expected completion at the end of the 2nd week of June 2026 with a Topping-Off ceremony scheduled for Thursday June 12, 2026. Concrete slab placement is completed in wings A and B, with wing C receiving metal deck in preparation for slab placement during the 3rd week of June 2026. Masonry installation for stairwell in wing A is ongoing, with the completion of scaffolding and the installation of the first several courses of masonry, construction of the scaffolding for the stairwell in wing B is ongoing. Roofing for wing A has been installed with penetrations and edge detailing to follow, roofing for wing B has started and is ongoing. Interior framing for wing A is nearly complete with exterior framing ongoing. Rough-in MEPFP is ongoing in wing A.
Spring 2026
May 2026
Winter 2025/2026
January 2026
December 2025
- The team has mobilized to begin site work and foundations as a critical milestone for project completion.
Renderings
Interior Renderings
Exterior Renderings
Meet The Team
- Dr. Patrick McGee - Woonsocket Education Department
- Brad Peryea - Woonsocket Education Department
- Alfred Notarianni - Woonsocket Education Department
- Dr. Joseph Da Silva - Rhode Island Department of Education
- Keelia Kentor - Rhode Island Department of Education