White Bear Lake Area High School North Campus

WHAT IS HAPPENING

Major Building additions, renovations and approximately 82 acres of site development. 595,000 SF in building work that consists of 250,00 SF classroom addition, 92,000 SF of athletics addition, 37,000 SF of auditorium addition and about 216,000 SF of existing building renovations.

SCHEDULE

  • Start Construction – July 19th, 2021
  • Complete Construction – October 25th, 2024

WEEKLY UPDATES

Currently at 99% completion

Area P/Q (Main Gym & Athletic Spaces, Kitchen)

Completed
Speakers

Area G/H (Classroom Circle)

Completed

Area D (Music Circle)

Completed
Renovated choir room
Renovated band room

Area E (Continuation of Union)

Completed
Union

Area A (Front Entry & Office Renovation)

Completed
Wood Paneling

Area B/C (Performing Arts Center & Classroom Additions)

Completed

VIDEOS

11.03.2022
10.19.2022
10.14.2022
10.07.2022
09.30.2022
09.22.2022
09.16.2022
09.07.2022
09.01.2022
08.25.2022
08.15.2022
08.03.2022
07.28.2022
07.21.2022
07.14.2022
07.07.2022
06.30.2022
06.23.2022
06.14.2022
06.09.2022
06.02.2022
05.26.2022
05.18.2022
05.05.2022
04.21.2022
04.01.2022
03.18.2022
03.04.2022
02.25.2022
02.16.2021
02.07.2021
01.13.2021
12.08.2021
11.30.2021
10..26.2021

Kraus-Anderson

Jason Peterson, Senior Project Manage| jason.peterson@krausanderson.com

AJ Lillesve, Project Manager | AJ.lillesve@krausanderson.com

Alex Titterud, Project Manager | alex.titterud@krausanderson.com

Cody Darling, Assistant Project Manager | cody.darling@krausanderson.com

Joe Yerbich, Project Superintendent | joe.yerbich@krausanderson.com

Brad Kloos, Project Superintendent | brad.kloos@krausanderson.com

Jarrod Peterson, Assistant Superintendent | jarrod.peterson@krausanderson.com

Taylor Becker, Project Coordinator | taylor.becker@krausanderson.com

Wold Architects

Ben Beery, Associate | bbeery@woldae.com

Maria Kennedy, Architect | mkennedy@woldae.com

Cosette Hannula, Architect | channula@woldae.com