View Static Version

Covington Creek 2 November 2023

Progress Update

We have made substantial progress in October and November. The right of way work is underway for Covington Creek 2. The mass grading is complete but we continue to have major rock issues and have to blast every cut area on the site. The installation of retaining walls and storm is complete and the work in the ROW is underway. The bore pits, jack and bore and sewer taps are scheduled for the first week of December.

Construction Video

Progress Photos

November 2023

Past Updates

Want to look back? Past project updates are listed here for your convenience:

May 2023 - June 2023 - July 2023 - August 2023 - September 2023 - October 2023

NextPrevious