Progress Update
We have made substantial progress in October and November. The right of way work is underway for Covington Creek 2. The mass grading is complete but we continue to have major rock issues and have to blast every cut area on the site. The installation of retaining walls and storm is complete and the work in the ROW is underway. The bore pits, jack and bore and sewer taps are scheduled for the first week of December.