Covington Creek 2 September 2023

Progress Update

We have made substantial progress. The right of way work is underway. The mass grading is complete. The installation of retaining walls and storm has begun. We have encountered substantial rock and are working through VE measures to address while we install utilities.

Construction Video

Progress Photos

Closer Aerial

Past Updates

Want to look back? Past project updates are listed here for your convenience:

May 2023 - June 2023 - July 2023 - August 2023

For more information contact: Rob Fuller at (707) 365-6891