Redwood Valley Elementary School CONSTRUCTION UPDATES

Redwood Area School District #2897’s new $46.63 million construction project will showcase an expansive project comprising a multi-story P-K-4 school spanning 80,425 square feet. This state-of-the-art facility will incorporate Cardinal Kids Club, modern classrooms, flex spaces, administrative offices, a fully equipped kitchen, and a cafeteria complete with a music/stage area. Furthermore, an 8,523-square-foot game court capable of seating 160 individuals will double as a storm shelter, ensuring safety during adverse weather conditions. Outdoor amenities will encompass parking lots, retention ponds, walking paths, designated playground areas, and a playfield tailored for outdoor educational programs catering to all students.

RENDERING

MONTHLY UPDATES

Floor Plan

CONSTRUCTION ACTIVITIES

Overall Site

Work in Progress

  • Site Grading - Ongoing to maintain site cleanliness.
  • Snow clearing (As Needed)
  • Temporary utilities connections (Gas & Electric).

Work Completed

  • Site grading and sub-base prepared on south-side staff parking lot.
  • Re-staging fencing to school year locations.
  • Storm water drainage pipe installation on west side of site.
  • Underground storm system installation on west side of site.
  • Installing box culvert/bridge between north and south sides of site.
  • Winter condition preparations.

Work Upcoming Next Month

  • Snow removal as needed.

Area A

Work In Progress

  • Setting roof joists.
  • Placing roof decking.
  • Structural steel detailing/welding.

Work Completed

  • Placing concrete footings and foundation walls.
  • Placing foundation spread footings.
  • Installing underground plumbing.
  • Erecting structural steel beams and columns.
  • Setting and grouting precast planking.

Work Upcoming Next Month

  • Exterior metal framing and sheathing.

Area B

Work in Progress

  • Erecting structural steel beams and joists.
  • Structural steel detailing/welding..

Work Completed

  • Storm shelter foundation footings and walls.
  • Placing building foundation footings and walls.
  • Setting storm shelter precast walls.

Work Upcoming Next Month

  • Setting and grouting precast planking.
  • Grouting storm shelter precast walls.

Area C

Work In Progress

  • Erecting structural steel beams and columns.
  • Structural steel detailing/welding.

Work Completed

  • Elevator pit waterproofing installation.
  • Placing concrete footings and foundation walls.
  • Placing foundation piers.
  • Installing underground plumbing.
  • Underground electrical rough-ins.
  • Setting roof joists.
  • Setting precast planking.

Work Upcoming Next Month

  • Grouting precast planking.

Area D

Work in Progress:

  • Exterior cold-form framing & sheathing.
  • Slab on grade and topping slab prep
  • Setting roof decking.

Work Completed

  • Installing underground plumbing.
  • Placing concrete footings and foundation walls.
  • Placing foundation piers.
  • Erecting structural steel beams and columns.
  • Structural steel detailing/welding.
  • Setting and grouting precast planking.
  • Setting roof joists.
  • Underground electrical rough-ins.

Work Upcoming Next Month

  • Slab on grade and topping slab pour and finish.
  • Weather barrier installation.
  • Window buck installation.
  • Waterproofing installation.

Area E

Work in Progress:

  • Setting roof decking.
  • Exterior cold-form framing & sheathing.
  • Slab on grade and topping slab prep.

Work Completed

  • Placing concrete footings and foundations.
  • Placing foundation spread footings.
  • Installing underground plumbing.
  • Erecting structural steel beams and columns.
  • Structural steel detailing/welding.
  • Grouting precast planking.
  • Setting roof joists.
  • Underground electrical rough-ins.

Work Upcoming Next Month

  • Slab on grade and topping slab pour and finish.
  • Weather barrier installation.
  • Window buck installation.
  • Waterproofing installation.

Photos and Videos

December 2024

November 2024

October 2024

September 2024

August 2024

Schedule

  • Bid and contract award: March 2024
  • Estimated construction start of Spring / Summer 2024

Weather

  • Construction Days Lost to Weather this Month: 1
  • Total Construction Days Lost to Weather: 13

Safety

  • Lost Time Days: 0
  • Days Worked Without Lost Time Accident: 148

Project Team

Kraus-Anderson Construction Company

Mike Stafford, Project Manager | 507-649-3011 | mike.stafford@krausanderson.com

Marques Putnam, Project Superintendent | 612-247-1613 | marques.putnam@krausanderson.com

Brandon Lawson, General Superintendent | 507-421-9324 | brandon.lawson@krausanderson.com

Shawn Lortscher, Director of Operations | 507-208-5692 | shawn.lortscher@krausanderson.com

Emily Taylor, Project Coordinator | 507-218-3853 | emily.taylor@krausanderson.com

Connor McGraw, Project Engineer Intern | connor.mcgraw@krausanderson.com

Wold Architects and Engineers

Lynae Schoen, Partner | lschoen@woldae.com

Katelyn Chambers, Associate | kchambers@woldae.com

Bolton & Menk Inc.

Damian Erickson, Design Engineer | damian.erickson@bolton-menk.com

BKBM Engineers

Brady Shelbourn, Project Manager | bshelbourn@bkbm.com

Andrew Morgan, Structural Engineer | amorgan@bkbm.com

Sam Wetzel, Structural Engineer | swetzel@bkbm.com

Paulson & Clark Engineering

Scott Johnson, Mechanical Engineer | sjohnson@paulsonclark.com

Karl Bohnsack, Electrical Engineer | karlb@paulsonclark.com