Redwood Area School District #2897’s new $46.63 million construction project will showcase an expansive project comprising a multi-story P-K-4 school spanning 80,425 square feet. This state-of-the-art facility will incorporate Cardinal Kids Club, modern classrooms, flex spaces, administrative offices, a fully equipped kitchen, and a cafeteria complete with a music/stage area. Furthermore, an 8,523-square-foot game court capable of seating 160 individuals will double as a storm shelter, ensuring safety during adverse weather conditions. Outdoor amenities will encompass parking lots, retention ponds, walking paths, designated playground areas, and a playfield tailored for outdoor educational programs catering to all students.
RENDERING
MONTHLY UPDATES
Floor Plan
CONSTRUCTION ACTIVITIES
Overall Site
Work in Progress
- Site Grading - Ongoing to maintain site cleanliness
- Re-staging fencing to school year locations.
- Underground plumbing installation within building footprint.
Work Completed
- Site grading and sub-base prepared on south-side staff parking lot
- Aggregate Piers beneath building pad
Work Upcoming Next Month
- Placing storm structures and drainage tanks
Area A
Work Upcoming Next Month:
- Placing building foundation footings and walls
Area B
Work Upcoming Next Month:
- Placing building foundation footings and walls
Area C
Work Upcoming Next Month:
- Placing building foundation footings and walls
Area D
Work in Progress:
- Placing building foundation footings and walls
Work Upcoming Next Month:
- Structural Steel Erection
Area E
Work in Progress:
- Placing building foundation footings and walls
Work Upcoming Next Month:
- Structural Steel Erection
Photos and Videos
August 2024
Schedule
- Bid and contract award: March 2024
- Estimated construction start of Spring / Summer 2024
Weather
- Construction Days Lost to Weather this Month: 0
- Total Construction Days Lost to Weather: 9
Safety
- Lost Time Days: 0
- Days Worked Without Lost Time Accident: 84
Project Team
Kraus-Anderson Construction Company
Mike Stafford, Project Manager | 507-649-3011 | mike.stafford@krausanderson.com
Bob Bolles, Project Superintendent | 612 849-7200 | bob.bolles@krausanderson.com
Brandon Lawson, General Superintendent | (507) 421-9324 | brandon.lawson@krausanderson.com
Shawn Lortscher, Director of Operations | (507) 208-5692 | shawn.lortscher@krausanderson.com
Emily Taylor, Project Coordinator | 507-218-3853 | emily.taylor@krausanderson.com
Connor McGraw, Project Engineer Intern | connor.mcgraw@krausanderson.com
Wold Architects and Engineers
Lynae Schoen, Partner | lschoen@woldae.com
Katelyn Chambers, Associate | kchambers@woldae.com
Bolton & Menk Inc.
Damian Erickson, Design Engineer | damian.erickson@bolton-menk.com
BKBM Engineers
Brady Shelbourn, Project Manager | bshelbourn@bkbm.com
Andrew Morgan, Structural Engineer | amorgan@bkbm.com
Sam Wetzel, Structural Engineer | swetzel@bkbm.com
Paulson & Clark Engineering
Scott Johnson, Mechanical Engineer | sjohnson@paulsonclark.com
Karl Bohnsack, Electrical Engineer | karlb@paulsonclark.com