Redwood Valley Elementary School CONSTRUCTION UPDATES

Redwood Area School District #2897’s new $46.63 million construction project will showcase an expansive project comprising a multi-story P-K-4 school spanning 80,425 square feet. This state-of-the-art facility will incorporate Cardinal Kids Club, modern classrooms, flex spaces, administrative offices, a fully equipped kitchen, and a cafeteria complete with a music/stage area. Furthermore, an 8,523-square-foot game court capable of seating 160 individuals will double as a storm shelter, ensuring safety during adverse weather conditions. Outdoor amenities will encompass parking lots, retention ponds, walking paths, designated playground areas, and a playfield tailored for outdoor educational programs catering to all students.

RENDERING

MONTHLY UPDATES

Floor Plan

Upper Level Floor Plan
Main Level Floor Plan

CONSTRUCTION ACTIVITIES

Progress This Month (Through May 28, 2025)

Overall Site

Work in Progress

  • Install remaining stormwater utilities north of county ditch.

Work Completed

  • Site grading and sub-base prepared on south-side staff parking lot.
  • Re-staging fencing to school year locations.
  • Storm water drainage pipe installation on west side of site.
  • Underground storm system installation on west side of site.
  • Installing box culvert/bridge between north and south sides of site.
  • Winter Condition Preparations.
  • Temporary utilities connections (Gas & Electric).
  • Pouring south teacher parking lot curb, gutter, and sidewalk.

Work Upcoming Next Month

  • Reede Gray Demolition.

Area A (Exterior)

Work In Progress

  • Window installation.
  • Exterior brick.
  • Windows.

Work Completed

  • Placing foundation footings, walls, and piers.
  • Erecting and detailing/welding structural steel beams, columns, joists, and decking.
  • Setting and grouting precast planking.
  • Underground MEP rough-ins.
  • Exterior cold-form framing & sheathing.
  • Weather barrier installation.
  • Window bucking.
  • Parapet blocking, insulation and roofing.

Work Upcoming Next Month

  • Metal panel installation.

Area A (Interior)

Area A Classroom

Work in Progress

  • Drywall taping and mudding.

Work Completed

  • Slab on grade prep and pour.
  • MEP overhead and in-wall rough-ins.
  • Interior framing.
  • Drywall.

Work Upcoming Next Month

Area B (Exterior)

Work in Progress

  • Exterior equipment pads.

Work Completed

  • Placing storm shelter and non-storm shelter foundation footings, walls, and piers.
  • Erecting and detailing/welding structural steel beams, columns, joists, and decking.
  • Setting and grouting precast planking.
  • Underground MEP rough-ins.
  • Exterior cold-form framing & sheathing.
  • Weather barrier installation.
  • Window bucking.
  • Storm shelter and non-storm shelter parapet blocking, insulation and roofing.

Work Upcoming Next Month

  • Exterior stone façade.
  • Windows.

Area B (Interior)

Area B Admin

Work in Progress

  • Boiler room equipment install.
  • MEP overhead and in-wall rough-ins.
  • Gym painting.
Area B Boiler Room
Area B Electrical Room

Work Completed

  • Slab on grade prep and pour.
  • Set air handler.
  • Mechanical pad pours.
  • Interior framing.
  • Gym overhead conduit and sprinklers.
Area B Gym East
Area B Gym Restroom

Work Upcoming Next Month

  • In-wall blocking and backing.
  • Drywall install, taping, and mudding.
  • Painting.
  • Gym lights and diffusers.
  • Gym scoreboard.
  • Gym basketball hoops.
  • Gym flooring and striping.
Area B Gym West

Area C (Exterior)

Work in Progress

  • Windows.
  • Exterior Brick.

Work Completed

  • Elevator pit waterproofing.
  • Placing foundation footings, walls, and piers.
  • Erecting and detailing/welding structural steel beams, columns, joists, and decking.
  • Setting and grouting precast planking.
  • Underground MEP rough-ins.
  • Exterior cold-form framing & sheathing.
  • Weather barrier installation.
  • Window bucking.
  • Parapet blocking, insulation and roofing installation.
  • Exterior brick.
  • Courtyard curtain walls.

Work Upcoming Next Month

  • Mechanical room metal panel installation.

Area C (1st Floor Interior)

Area C 1st Floor Classroom

Work in Progress

  • Drywall taping and mudding.
  • Painting.
Area C 1st Floor Corridor

Work Completed

  • Slab on grade prep and pour.
  • Cooler/freezer recessed slab install.
  • Stair B install.
  • Interior framing.
  • MEP in-wall and overhead rough-ins.
  • In-wall blocking and backing.
  • MEP insulation.
  • Drywall.
Area C 1st Floor Flex Space

Work Upcoming Next Month

  • Elevator install.
  • Pull wire and cabling.
  • Ceiling grid and border.
  • Storefronts.
  • Freezer/cooler install.
  • Tiling.
  • Casework.
  • Grills and diffusers.
  • Lighting and ceiling devices.
  • Sprinkler heads.
  • Flooring and base.
Area C 1st Floor Reading Title

Area C (2nd Floor Interior)

Area C 2nd Floor Corridor
Area C 2nd Floor Flex Space

Work in Progress

  • Drywall.
Area C 2nd Floor Media Center

Work Completed

  • Topping slab prep and pour.
  • Interior framing.
  • MEP in-wall and overhead rough-ins.
  • MEP insulation.
  • In-wall blocking and backing.
Area C 2nd Floor Indian Ed

Work Upcoming Next Month

  • Drywall taping and mudding.
  • Painting.
  • Pull wire and cabling.
  • Ceiling grid and border.
  • Storefronts.
  • Tiling.
  • Casework.
Area C 2nd Floor Music Room

Area D (Exterior)

Work in Progress

  • Windows.

Work Completed

  • Placing foundation footings, walls, and piers.
  • Erecting and detailing/welding structural steel beams, columns, joists, and decking.
  • Setting and grouting precast planking.
  • Underground MEP rough-ins.
  • Exterior cold-form framing & sheathing.
  • Weather barrier installation.
  • Window bucking.
  • Parapet blocking, insulation and roofing installation.
  • Exterior brick.

Work Upcoming Next Month

  • Mechanical room metal panel installation.

Area D (1st Floor Interior)

Area D Classroom

Work in Progress

  • Pull wire and cabling.
  • Ceiling grid and border.
  • Tiling.
  • Casework.

Work Completed

  • Slab on grade prep and pour.
  • Spray foam exterior walls.
  • Interior framing.
  • MEP in-wall and overhead rough-ins.
  • MEP insulation.
  • In-wall blocking and backing.
  • Storefronts and windows.
  • Drywall install, taping, and mudding.
  • Painting.
  • Tiling.

Work Upcoming Next Month

  • Ceiling grid and border.
  • Tiling.
  • Devicing.
  • Plumbing fixtures.
  • Grills and diffusers.
  • Lighting and ceiling devices.
  • Sprinkler heads.
  • Flooring and base.
  • Doors and hardware.
  • Interior glazing.
  • Bathroom/kitchen accessories.
  • Visual display boards.
  • Room signage.
  • Window treatments.
  • Sills.
  • Ceiling pad.

Area D (2nd Floor Interior)

Work in Progress

  • Drywall install, taping, and mudding.

Work Completed

  • Mechanical room topping and equipment slab pour.
  • Air handlers installed.
  • Interior framing.
  • MEP in-wall and overhead rough-ins.

Work Upcoming Next Month

Area E (Exterior)

Work in Progress

  • Windows.

Work Completed

  • Placing foundation footings, walls, and piers.
  • Erecting and detailing/welding structural steel beams, columns, joists, and decking.
  • Setting and grouting precast planking.
  • Underground MEP rough-ins.
  • Exterior cold-form framing & sheathing.
  • Weather barrier installation.
  • Window bucking.
  • Parapet blocking, insulation and roofing installation.
  • Exterior brick.

Work Upcoming Next Month

  • Canopy sheet metal installation.
  • Canopy roofing.

Area E (1st Floor Interior)

Area E 1st Floor Classroom

Work in Progress

  • Flooring and base.
  • Pull wire and cabling.
  • Storefronts.
  • Devicing.
  • Plumbing fixtures.
  • Grills and diffusers.
  • Lighting and ceiling devices.
Area E 1st Floor Mud Room

Work Completed

  • Slab on grade prep and pour.
  • Stair A install.
  • Interior framing.
  • MEP in-wall and overhead rough-ins.
  • MEP insulation.
  • In-wall blocking and backing.
  • Window installation.
  • Drywall install, taping, and mudding.
  • Painting.
  • Ceiling grid and border.
  • Tiling.
  • Casework.
  • Sprinkler head fittings.
Area E 1st Floor Special Education Room

Work Upcoming Next Month

  • Doors and hardware.
  • Interior glazing.
  • Bathroom/Kitchen Accessories.
  • Visual display boards.
  • Room signage.
  • Window treatments.
  • Sills.
  • Ceiling pad.

Area E (2nd Floor Interior)

Area E 2nd Floor Classroom

Work in Progress

  • Above ceiling sprinkler.
  • Pull wire and cabling.
  • Ceiling grid and border.
  • Storefronts.
  • Casework.
Area E 2nd Floor Mud Room

Work Completed

  • Topping slab prep and pour.
  • Interior framing.
  • Overhead and in-wall MEP rough-ins.
  • MEP insulation.
  • In-wall blocking and backing.
  • Window installation.
  • Drywall install, taping, and mudding.
  • Painting.
  • Tiling.
Area E 2nd Floor Special Education Room

Work Upcoming Next Month

  • Devicing.
  • Grills and diffusers.
  • Lighting and ceiling devices.
  • Sprinkler heads.
  • Flooring and base.
  • Doors and hardware.
  • Interior glazing.
  • Bathroom/kitchen accessories.
  • Visual display boards.
  • Room signage.
  • Window treatments.
  • Sills.
  • Ceiling pad.

Photos and Videos

May 2025

Area A Classroom 1
L-R: Area B Admin, Area B Boiler Room, Area B Boiler Room
L-R: Area B Gym East, Area B Gym West
Area C 1st Floor Corridor
L-R, T-B: Area C Cafeteria, Area C Cafeteria, Area C South Bathroom Pod, Area C Stairs
L-R: Area E 1st Floor Classroom, Area E 1st Floor Mud Room
L-R, T-B: Filtration Pond, South Lot

February 2025

January 2025

December 2024

November 2024

October 2024

September 2024

August 2024

Schedule

  • Bid and contract award: March 2024
  • Estimated construction start of Spring / Summer 2024

Weather

  • Construction Days Lost to Weather this Month: 1
  • Total Construction Days Lost to Weather: 21.5

Safety

  • Lost Time Days: 0
  • Days Worked Without Lost Time Accident: 238.5

Project Team

Kraus-Anderson Construction Company

Mike Stafford, Project Manager | 507-649-3011 | mike.stafford@krausanderson.com

Marques Putnam, Project Superintendent | 612-247-1613 | marques.putnam@krausanderson.com

Brandon Lawson, General Superintendent | 507-421-9324 | brandon.lawson@krausanderson.com

Shawn Lortscher, Director of Operations | 507-208-5692 | shawn.lortscher@krausanderson.com

Emily Taylor, Project Coordinator | 507-218-3853 | emily.taylor@krausanderson.com

Connor McGraw, Project Engineer Intern | connor.mcgraw@krausanderson.com

Wold Architects and Engineers

Lynae Schoen, Partner | lschoen@woldae.com

Katelyn Chambers, Associate | kchambers@woldae.com

Bolton & Menk Inc.

Damian Erickson, Design Engineer | damian.erickson@bolton-menk.com

BKBM Engineers

Brady Shelbourn, Project Manager | bshelbourn@bkbm.com

Andrew Morgan, Structural Engineer | amorgan@bkbm.com

Sam Wetzel, Structural Engineer | swetzel@bkbm.com

Paulson & Clark Engineering

Scott Johnson, Mechanical Engineer | sjohnson@paulsonclark.com

Karl Bohnsack, Electrical Engineer | karlb@paulsonclark.com