Redwood Area School District #2897’s new $46.63 million construction project will showcase an expansive project comprising a multi-story P-K-4 school spanning 80,425 square feet. This state-of-the-art facility will incorporate Cardinal Kids Club, modern classrooms, flex spaces, administrative offices, a fully equipped kitchen, and a cafeteria complete with a music/stage area. Furthermore, an 8,523-square-foot game court capable of seating 160 individuals will double as a storm shelter, ensuring safety during adverse weather conditions. Outdoor amenities will encompass parking lots, retention ponds, walking paths, designated playground areas, and a playfield tailored for outdoor educational programs catering to all students.
RENDERING
MONTHLY UPDATES
Floor Plan
CONSTRUCTION ACTIVITIES
Progress This Month (January)
Overall Site
Work in Progress
- Site Grading - Ongoing to maintain site cleanliness.
- Snow clearing (as needed)
Work Completed
- Site grading and sub-base prepared on south-side staff parking lot.
- Re-staging fencing to school year locations.
- Storm water drainage pipe installation on west side of site.
- Underground storm system installation on west side of site.
- Installing box culvert/bridge between north and south sides of site.
- Winter Condition Preparations
- Temporary utilities connections (Gas & Electric).
Work Upcoming Next Month
Area A (Exterior)
Work In Progress
- Exterior framing and sheathing.
Work Completed
- Placing concrete footings and foundation walls.
- Placing foundation spread footings.
- Installing underground plumbing.
- Erecting structural steel beams, columns, and joists.
- Setting and grouting precast planking.
- Placing roof decking.
- Structural steel detailing/welding.
Work Upcoming Next Month
- Window bucking.
- Brick facade.
Area A (Interior)
Work in Progress
- Slab on grade prep (Ground thaw).
Work Completed
Work Upcoming Next Month
- Pouring slab on grade.
- Interior framing.
Area B (Exterior)
Work in Progress
- Structural steel detailing/welding.
Work Completed
- Storm shelter foundation footings and walls.
- Placing building foundation footings and walls.
- Setting and grouting storm shelter precast walls.
- Setting precast double-tees.
- Erecting structural steel columns, beams, and joists.
Work Upcoming Next Month
- Exterior framing and sheathing.
Area B (Interior)
Work in Progress
- Slab on grade prep (ground thaw).
Work Completed
- Underground plumbing and electrical rough-ins.
- Upper mechanical room topping/equipment slab.
- Setting AHU-5.
Work Upcoming Next Month
Area C (Exterior)
Work in Progress
- Setting roof decking.
Work Completed
- Elevator pit waterproofing installation.
- Placing concrete footings and foundation walls.
- Placing foundation piers.
- Installing underground plumbing.
- Setting and grouting precast planking.
- Erecting structural steel beams, columns, and joists.
- Structural steel detailing/welding.
Work Upcoming Next Month
- Installing curtainwalls.
Area C (1st Floor Interior)
Work in Progress
- Pouring slab on grade.
Work Completed
- Elevator pit waterproofing installation.
- Installing underground plumbing.
- Underground electrical rough-ins.
- Setting and grouting precast planking.
- Erecting structural steel beams, columns, and joists.
- Structural steel detailing/welding.
Work Upcoming Next Month
- Walk-In Fridge/Freezer Install.
- Interior framing.
- In-wall and overhead rough-ins.
Area C (2nd Floor Interior)
Work in Progress
Work Completed
Work Upcoming Next Month
Area D (Exterior)
Work in Progress
- Exterior cold-form framing & sheathing.
Work Completed
- Placing concrete foundations.
- Erecting structural steel beams, columns, and joists.
- Structural steel detailing/welding.
- Setting and grouting precast planking.
- Setting roof decking.
- Weather barrier installation.
- Window buck installation.
- Waterproofing installation.
- Setting roof decking.
- Exterior cold-form framing & sheathing.
- Slab on grade and topping slab prep.
Work Upcoming Next Month
- Mechanical room topping slab.
- EPDM Roofing.
Area D (1st Floor Interior)
Work in Progress
- Interior framing.
Work Completed
- Installing underground plumbing rough-ins.
- Underground electrical rough-ins.
- Placing concrete foundations.
- Erecting structural steel beams, columns, and joists.
- Structural steel detailing/welding.
- Setting and grouting precast planking.
- Weather barrier installation.
- Window buck installation.
- Waterproofing installation.
- Slab on grade and topping slab prep.
Work Upcoming Next Month
- MEP in-wall and overhead rough-ins.
Area D (2nd Floor Interior)
Work in Progress
Work Completed
Work Upcoming Next Month
- Mechanical room topping and equipment slab.
Area E (Exterior)
Work in Progress
- Setting roof decking.
- Exterior cold-form framing & sheathing.
- Slab on grade and topping slab prep.
Work Completed
- Placing concrete footings and foundations.
- Placing foundation spread footings.
- Installing underground plumbing.
- Erecting structural steel beams, columns, and joists.
- Structural steel detailing/welding.
- Setting and grouting precast planking.
- Underground electrical rough-ins.
Work Upcoming Next Month
- Slab on grade and topping slab pour and finish.
- Weather barrier installation.
- Window bucking.
- Spray foam installation.
- EPDM Roofing.
Area E (1st Floor Interior)
Work in Progress
- Exterior cold-form framing & sheathing.
- Installing window bucks.
- Interior framing.
- In-wall electrical rough-ins.
- Overhead MEP rough-ins.
Work Completed
- Placing concrete footings and foundations.
- Erecting structural steel beams, columns, and joists.
- Structural steel detailing/welding.
- Setting and grouting precast planking.
- Setting roof decking.
- Slab on grade poured.
- Underground MEP rough-ins.
- In-wall plumbing rough-ins.
Work Upcoming Next Month
- Drywall installation.
- Window installation.
Area E (2nd Floor Interior)
Work in Progress
- Exterior cold-form framing & sheathing.
Work Completed
- Placing concrete footings and foundations.
- Placing foundation spread footings.
- Installing underground plumbing.
- Erecting structural steel beams and columns.
- Structural steel detailing/welding.
- Grouting precast planking.
- Setting roof joists.
- Underground electrical rough-ins.
- Setting roof decking.
Work Upcoming Next Month
- Topping slab pour.
- Weather barrier installation.
- Window bucking.
- Waterproofing installation.
- Stair installation.
Photos and Videos
January 2025
December 2024
November 2024
October 2024
September 2024
August 2024
Schedule
- Bid and contract award: March 2024
- Estimated construction start of Spring / Summer 2024
Weather
- Construction Days Lost to Weather this Month: 5
- Total Construction Days Lost to Weather: 18
Safety
- Lost Time Days: 0
- Days Worked Without Lost Time Accident: 170
Project Team
Kraus-Anderson Construction Company
Mike Stafford, Project Manager | 507-649-3011 | mike.stafford@krausanderson.com
Marques Putnam, Project Superintendent | 612-247-1613 | marques.putnam@krausanderson.com
Brandon Lawson, General Superintendent | 507-421-9324 | brandon.lawson@krausanderson.com
Shawn Lortscher, Director of Operations | 507-208-5692 | shawn.lortscher@krausanderson.com
Emily Taylor, Project Coordinator | 507-218-3853 | emily.taylor@krausanderson.com
Connor McGraw, Project Engineer Intern | connor.mcgraw@krausanderson.com
Wold Architects and Engineers
Lynae Schoen, Partner | lschoen@woldae.com
Katelyn Chambers, Associate | kchambers@woldae.com
Bolton & Menk Inc.
Damian Erickson, Design Engineer | damian.erickson@bolton-menk.com
BKBM Engineers
Brady Shelbourn, Project Manager | bshelbourn@bkbm.com
Andrew Morgan, Structural Engineer | amorgan@bkbm.com
Sam Wetzel, Structural Engineer | swetzel@bkbm.com
Paulson & Clark Engineering
Scott Johnson, Mechanical Engineer | sjohnson@paulsonclark.com
Karl Bohnsack, Electrical Engineer | karlb@paulsonclark.com