What is Happening?
- Construction of a 81,000 square foot hospital & clinic
Schedule
- Construction Start June 6/8/2023
- Completion Early 2025
Work Completed
- Exterior Finishes
- Curtainwall Installation
- Site Concrete
- Landsaping
- Outbuilding Structure Erection
Work Ongoing
- Interior drywall finishing and painting
- Door and hardware installation
- Casework and millwork installation
- Flooring installation
- Acoustical ceiling installation
- MEP finishes and devicing
Work Upcoming
- Completion of exterior masonry veneer
- Completion of exterior metal panel system
- Ongoing MEP above ceiling and in-wall rough in
- Ongoing non-priority wall framing
- Interior drywall installation and finishing
October 2024
September 2024
August 2024
July 2024
June 2024
May 2024
April 2024
March 2024
February 2024
January 2024
December 2023
November 2023
October 2023
September 2023 Update
August 2023 Update
July 2023 Update
June 2023 Update
MHLC staff thanking Senator Baldwin for $4Million in Congressional Directed Spending for our replacement hospital
Megan Geiser, Project Manager