City of Otsego Otsego Fire Department

Otsego Fire Department

Why: To serve and protect the citizens of Otsego by providing high quality public safety services through minimized response times, public safety outreach, and community risk reduction for the citizens and surrounding regions.
Project Timeline
  • Construction Begins - June 2025
  • Construction Complete - June 2026
  • Recruitment Event - June 2026
  • Final 2 Fire Trucks Delivered - August 2026
  • Open House Event - September 2026
  • Station Operational - Fourth Quarter 2026
  • Department Operational - January 1, 2027
Construction Updates

Site Footage

January Drone Footage

December 2025

  • Plumbing, HVAC, fire suppression, and electrical rough-ins in progress throughout
  • Mechanical room equipment installations started
  • Overhead sectional doors delivered and installed in place
  • Four-fold doors delivered and installed in place
  • In-floor heat pump stations started in 4-bay
  • CMU walls completed on main level in decontamination area and mezzanine
  • Ceiling and soffit framing in progress throughout
  • Drywall in progress throughout
  • Curtainwall and windows completed
  • Weather barrier finished
  • Thermally modified wood siding install in progress
  • Front entrance vestibule roof completed
Office: Mechanical Room In Progress
Office: Mechanical Room Equipment In Progress
Office: Electrical Room Equipment In Progress
Office: Electrical Room Work In Progress
Office: Corridors Drywall and Rough-Ins In Progress
App Bays: Four-Fold Doors Delivered to Site
App Bays: Four-Fold Door Installed and Open
App Bays: Four Fold Doors Installed
App Bays: Sectional Doors Installed
App Bays: In-Floor Heat Pump Systems In 4-Bay
App Bays: CMU Block Walls In Progress Decon Area
App Bays: Corridor Between 4-Bay and 2-Bay CMU Walls Complete
App Bays: Decon Bathroom CMU Walls Built
App Bays: Decon Showers CMU Rough-Ins Complete
App Bays: Gear Wash Area CMU Walls Complete
Mezzanine: CMU Block Walls In Progress Mezzanine
Exterior: TMW Siding Complete at West Elevation of Training Tower

Work Upcoming

  • Finish MEP rough-ins in office area
  • Continue MEP rough-ins in apparatus bays and mezzanine
  • Start concrete floor polishing
  • Finish drywall in office area
  • Painting in office area
  • Start install of ceiling grid in office area
  • Install front entry curtainwall and storefront
  • Install training tower staircase and roof ladder
  • Complete epoxy flooring on mezzanine
  • Install HM frames in precast and CMU openings
Exterior: Front Vestibule Curtainwall & Storefront
Office: Polished Floor Sample
Office: Front Entry Lobby In Progress
Office: Corridors Ready for Paint
Office: Ceiling Grid Upcoming
App Bays: Training Tower Staircase Erection to Start
Mezzanine: Epoxy Flooring and 2x2 Unistrut Grid System
HM Frames Staged for Install

Weather

  • Construction Days Lost to Weather Past Month: 2 days
  • Total Construction Days Lost to Weather: 10 days

Safety

  • Lost Time Days: 0
  • Days Worked Without Lost Time Accident: 224
Project Progress

Home of the new Otsego Fire Department

June 2025
Concept Renderings
Dayroom and Kitchen Rendering
Office Rendering
Dayroom & Training Room rendering
Contact Information

For more information on the New Otsego Fire & Emergency Services Department, contact Mike Scott, Interim Fire Department Director at 763-441-4414 or email at fire@otsegomn.gov.

Project Architect
Construction Manager