Jordan Public Schools CONSTRUCTION UPDATES

About the Project:

Elementary School:

This portion of the project involves the construction of 2 separate additions (totaling 28,000 SF) with the gymnasium space of the addition being constructed as a storm shelter space (8,500 SF). The additions are designed for classrooms, cafeteria, kitchen, gymnasium, loading dock and a secure front entry. This project also includes extensive interior renovations to the classrooms, storage spaces, media center, cafeteria/kitchen reconfigurations, exterior window replacements, bathroom upgrades, & mechanical and electrical system upgrades. The exterior will include the reconstruction of the parking lots, playground spaces, along with other exterior site improvements. This is designed to improve bus and parent drop-off zones and parking areas are being modified to improve safety for students and minimize traffic impacts to the neighborhood.

High School:

This portion of the project involves the construction of a new secured front entry configuration that will incorporate a new reception area as well as office spaces.

Ground Breaking

RENDERINGS

CONSTRUCTION ACTIVITIES

Work Completed, in July

Elementary Classroom Addition

  • Complete

Cafeteria and Kitchen

  • Complete

Gym Addition

  • Complete

Offices

  • Complete

Area A – Existing Offices

  • Complete

Area A – Existing Gym and Cafeteria

  • Complete

Area B – K-1 Wing, Bathrooms, Early Learning Services Classrooms, and Office Space

  • Wall sheet rocking and taping
  • Painting
  • Roofing
  • MEP rough-ins
  • MEP finishes
  • Casework deliveries and installation
  • Flooring installation
  • Markerboard and tackboard installation
  • Floor and wall tile installation
  • Ceiling grid and tile installation

Exterior Parking Lot and Pond

  • Poured curbs
  • Poured sidewalk
  • Grading

Upcoming Work, in August:

Area B – K-1 Wing, Bathrooms, Early Learning Services Classrooms, and Office Space

  • Carpet installation
  • Casework installation
  • Final cleaning

Exterior Parking Lot and Pond

  • Asphalt paving
  • Striping

Summer 2025 Interior School Renovations:

Summer 2025 interior renovations will include the K-1 wing of the building, existing kitchen and cafeteria, new bathrooms, and renovations to the Early Learning Services classrooms and office space.

Weather

  • Construction Days Lost to Weather this Month: 0
  • Total Construction Days Lost to Weather: 7

Safety

  • Lost Time Days: 0
  • Days Worked Without Lost Time Accident: 0

Photos

July 2025

June 2025

May 2025

March 2025

February 2025

January 2025

November-December 2024

August-October 2024

June + July 2024

May 2024

April 2024

Project Team

Kraus-Anderson Construction Company

Dustin Kempf, Senior Project Manager

Jon Roemhildt, Project Manager

Christ Baus, Project Superintendent

Silvia Magana, Senior Project Coordinator

ISG, Inc.

Justin Steffl, Senior Project Manager

Nickisha Vander Wyst, Architect