Construction Updates
Area A – Secure Entrance Addition
Completed
Building Structure – All Levels
- Structural Steel Erection
- Joist and Decking Installation
- CMU Exterior Walls
- Joists and Decking
- Topping Slabs at Levels 2 & 3
- Fireproofing at Structural Steel
Level 1
- Interior Stone
- In-Ceiling MEP Fixtures
- Paint
- Ceiling Grid
Level 2
- Sheetrock & Taping
- Paint
- Ceiling Pad Installation
Level 3
- Interior Wall Framing
- Ceiling Grid
- Above Ceiling & In Wall MEP
- Casework
Exterior
- Exterior Stone Veneer
- Window Installation
Ongoing
Level 1
- Flooring Installation
- Casework Installation
- Miscellaneous Metals
- Elevator Installation
- Existing Stair Demo
Level 2
- Bathroom Tile
- Countertops and Windowsills
Level 3
- Sheetrock & Taping
- Ceiling Grid & Borders
- Bathroom Tile
Exterior
- Framing & Insulation for Metal Panels
Upcoming
Level 1
- Acoustic Ceiling Baffles
- Terrazzo
Level 2
- Flooring
- Structural Steel to be Installed at Existing Stairwell
Level 3
- Install Ceiling Pads
- Flooring
Exterior
- Curtain Wall at Levels 2 & 3
- Canopy Structural Steel
- Metal Wall Panel Installation
Area B&C – Athletics Addition
Completed
- Slab on Grade Pours at Gym & Storm Shelter Area
- Sheetrocking & Taping at Concessions Area
- Concrete Pour at Storm Shelter Roof Deck
- Fireproofing Installation at Activities Corridor
- MEP Rough-Ins at Concessions Area
Ongoing
- MEP Rough-Ins at New Gym
- Furring and Insulation ahead of Metal Panels
- CMU Wall Installation in Storm Shelter Area
- Excavation for Exterior Chiller / Trash Enclosure
Upcoming
- Tiling at Concessions/Bathrooms Area
- Window Installation
- Trophy Case Installation at Concessions Area
- Paint at Concessions Area
- Gym Equipment & Flooring
Photos
Secure Entrance Addition - Level 1
Secure Entrance Addition - Level 2
Secure Entrance Addition - Level 3
Athletics Addition - Activities Entrance and Corridor
Athletics Addition - Concession Stand
Athletics Addition - New Gym
Athletics Addition - Exterior
Videos
Last Month's Progress
Overall Site Progress
Weather
Construction Days Lost to Weather This Month: 0
Total Construction Days Lost to Weather: 12
Safety
Lost Time Days: 0
Days Worked Without Lost Time Accident: 280
Project Team
Kraus-Anderson Construction Company
Tyler Stadheim | Project Superintendent | Tyler.Stadheim@krausanderson.com
Rob Gemelke | Senior Project Manager | rob.gemelke@krausanderson.com
Evan VanEps | Project Engineer | evan.vaneps@krausanderson.com
LSE Architects
Matt Korus | Construction Administrator | Mkorus@lse-architects.com
Jennifer Anderson-Tuttle | Principal | Jtuttle@lse-architects.com