View Screen Reader-Friendly Version

Mankato West High School

APRIL 2026

Construction Updates

Area A – Secure Entrance Addition

Completed

Building Structure & Exterior – All Levels

  • Structural Steel Erection
  • Joist and Decking Installation
  • CMU Exterior Walls
  • Vapor Barrier
  • Joists and Decking
  • Topping Slabs at Levels 2 & 3
  • Fireproofing at Structural Steel

Level 1

  • Underground Mechanical & Electrical
  • Load Transfer Platform Placement
  • Slab on Grade
  • Interior Wall Framing
  • Above Ceiling & In-Wall MEP Rough-ins
  • In-Wall Backing Installation
  • Sheetrock & Taping
  • Paint
  • Ceiling Grid

Level 2

  • Fireproofing at Structural Steel
  • Interior Wall Framing
  • Sheetrock & Taping
  • Paint
  • Ceiling Grid

Level 3

  • Interior Wall Framing
  • Above Ceiling & In Wall MEP

Exterior

  • Exterior Stone Veneer
  • Window Installation

Ongoing

Level 1

  • Interior Stone
  • Casework
  • MEP Ceiling Fixtures & Accessories
  • Elevator Installation

Level 2

  • Bathroom Tile
  • MEP Ceiling Fixtures & Accessories

Level 3

  • Sheetrock & Taping
  • Ceiling Grid & Boarders
  • Bathroom Tile

Exterior

  • Framing & Insulation for Metal Panels

Upcoming

Level 1

  • Flooring
  • Terrazzo

Level 2

  • Flooring
  • Casework

Level 3

  • Paint
  • Ceiling Grid
  • MEP Ceiling Fixtures & Lighting
  • Install Ceiling Pads
  • Flooring

Exterior

  • Curtain Wall at Levels 2 & 3
  • Metal Wall Panel Installation

Area B&C – Athletics Addition

Completed

  • Foundations & Grade Beams
  • Backfill & Compaction
  • Rigid Inclusion Installation
  • Rock Haul Roads for Precast Crane
  • First Phase of Precast Installation
  • First Floor Hollow Core Plank Topping Slab Pour
  • Ground Thaw
  • Phase 1 of Precast Installation
  • Underground Plumbing at Locker Rooms
  • Load Transfer Platform (LTP) Installation at Gym Area

Ongoing

  • Structural Steel Joist & Decking Installation
  • Phase 2 of Precast Installation
  • Interior Wall Framing at Concessions Area
  • MEP Rought-Ins at Concessions Area
  • Load Transfer Platform (LTP) Installation at Locker Rooms
  • Roofing Installation
  • Electrical Underground

Upcoming

  • Slab on Grade Pours at Gym & Storm Shelter Area
  • Interior Wall Framing & Masonry
  • Overhead MEP Rough-Ins at Gym & Storm Shelter Areas
  • Sheetrock & Taping at Concessions Area
  • Paint at Concessions Area

Photos

Secure Entrance Addition - Exterior Stone

Secure Entrance Addition - Interior Stone and Bathroom Tile

Secure Entrance Addition - Level 1

Commons and Main Office

Secure Entrance Addition - Level 2

Classrooms and Commons

Secure Entrance Addition - Level 3

Classrooms and Commons

Secure Entrance Addition - Staff Workroom

Athletic Addition - Concessions Corridor

Athletics Addition - Gym LTP

Athletics Addition - Underground Electrical

Athletics Addition - Locker Room LTP Install

Athletics Addition - Precast Phase 2

Athletics Addition - West Entrance

Videos

Last Month's Progress

Overall Site Progress

Weather

Construction Days Lost to Weather This Month: 0

Total Construction Days Lost to Weather: 12

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 280

Project Team

Kraus-Anderson Construction Company

Tyler Stadheim | Project Superintendent | Tyler.Stadheim@krausanderson.com

Rob Gemelke | Senior Project Manager | rob.gemelke@krausanderson.com

Evan VanEps | Project Engineer | evan.vaneps@krausanderson.com

LSE Architects

Matt Korus | Construction Administrator | Mkorus@lse-architects.com

Jennifer Anderson-Tuttle | Principal | Jtuttle@lse-architects.com