Construction Updates
Area A – Secure Entrance Addition
Completed
Building Structure & Exterior – All Levels
- Structural Steel Erection
- Joist and Decking Installation
- CMU Exterior Walls
- Vapor Barrier
- Joists and Decking
- Topping Slabs at Levels 2 & 3
- Fireproofing at Structural Steel
Level 1
- Underground Mechanical & Electrical
- Load Transfer Platform Placement
- Slab on Grade
- Interior Wall Framing
- Above Ceiling & In-Wall MEP Rough-ins
- In-Wall Backing Installation
- Sheetrock & Taping
- Paint
- Ceiling Grid
Level 2
- Fireproofing at Structural Steel
- Interior Wall Framing
- Sheetrock & Taping
- Paint
- Ceiling Grid
Level 3
- Interior Wall Framing
- Above Ceiling & In Wall MEP
Exterior
- Exterior Stone Veneer
- Window Installation
Ongoing
Level 1
- Interior Stone
- Casework
- MEP Ceiling Fixtures & Accessories
- Elevator Installation
Level 2
- Bathroom Tile
- MEP Ceiling Fixtures & Accessories
Level 3
- Sheetrock & Taping
- Ceiling Grid & Boarders
- Bathroom Tile
Exterior
- Framing & Insulation for Metal Panels
Upcoming
Level 1
- Flooring
- Terrazzo
Level 2
- Flooring
- Casework
Level 3
- Paint
- Ceiling Grid
- MEP Ceiling Fixtures & Lighting
- Install Ceiling Pads
- Flooring
Exterior
- Curtain Wall at Levels 2 & 3
- Metal Wall Panel Installation
Area B&C – Athletics Addition
Completed
- Foundations & Grade Beams
- Backfill & Compaction
- Rigid Inclusion Installation
- Rock Haul Roads for Precast Crane
- First Phase of Precast Installation
- First Floor Hollow Core Plank Topping Slab Pour
- Ground Thaw
- Phase 1 of Precast Installation
- Underground Plumbing at Locker Rooms
- Load Transfer Platform (LTP) Installation at Gym Area
Ongoing
- Structural Steel Joist & Decking Installation
- Phase 2 of Precast Installation
- Interior Wall Framing at Concessions Area
- MEP Rought-Ins at Concessions Area
- Load Transfer Platform (LTP) Installation at Locker Rooms
- Roofing Installation
- Electrical Underground
Upcoming
- Slab on Grade Pours at Gym & Storm Shelter Area
- Interior Wall Framing & Masonry
- Overhead MEP Rough-Ins at Gym & Storm Shelter Areas
- Sheetrock & Taping at Concessions Area
- Paint at Concessions Area
Secure Entrance Addition - Level 1
Secure Entrance Addition - Level 2
Secure Entrance Addition - Level 3
Secure Entrance Addition - Staff Workroom
Athletic Addition - Concessions Corridor
Athletics Addition - Locker Room LTP Install
Athletics Addition - Precast Phase 2
Athletics Addition - West Entrance
Videos
Last Month's Progress
Overall Site Progress
Weather
Construction Days Lost to Weather This Month: 0
Total Construction Days Lost to Weather: 12
Safety
Lost Time Days: 0
Days Worked Without Lost Time Accident: 280
Project Team
Kraus-Anderson Construction Company
Tyler Stadheim | Project Superintendent | Tyler.Stadheim@krausanderson.com
Rob Gemelke | Senior Project Manager | rob.gemelke@krausanderson.com
Evan VanEps | Project Engineer | evan.vaneps@krausanderson.com
LSE Architects
Matt Korus | Construction Administrator | Mkorus@lse-architects.com
Jennifer Anderson-Tuttle | Principal | Jtuttle@lse-architects.com