Construction Updates
Area A – Secure Entrance Addition
Completed:
- Underground Mechanical/Electrical Rough-Ins
- Soil Compaction & Backfill
- Load Transfer Platform Installation
- Second Level Decking
- Level 1 Vapor Barrier & Rebar Installation
- First & Second Level Exterior CMU Shell
- Scaffolding Install at Exterior of Building
- Temp Weather Enclosure
Ongoing:
- CMU Exterior Walls
- Structural Steel Erection & Detailing
Upcoming:
- Level 1 Above Ceiling and In-Wall MEP Rough-Ins
- Structural Steel Fireproofing
- Steel Joist & Decking at Roof
- Level 1 Slab on Grade Pour
- Level 2 Concrete Slab Pour
- Level 1 Interior Framing
Area B&C - Athletics Addition
Completed:
- Exterior Spray Foam Insulation at Existing Walls
- Emergency Egress Back Fill at Existing Gymnasium
Ongoing:
- Exterior Footings and Foundation Walls – Reinforce, Form, & Pour
- Pile Cap & Grade Beams – Reinforce, Form, & Pour
- Steel Embed Installations for Precast
- Foundation Excavations & Backfill as Necessary for Crew Access
Upcoming:
- Rigid Inclusion Pile Installation
- Precast Hollow-Core Plank Installation at Level 1
- Underground Mechanical & Electrical
- Complete Backfill
- Precast Erection
Photos
Videos
Last Month's Progress
Overall Site Progress
Weather
Construction Days Lost to Weather This Month: 2
Total Construction Days Lost to Weather: 8
Safety
Lost Time Days: 0
Days Worked Without Lost Time Accident: 180
Project Team
Kraus-Anderson Construction Company
Tyler Stadheim | Project Superintendent | Tyler.Stadheim@krausanderson.com
Michael Veaderko | Project Manager | michael.veaderko@krausanderson.com
Evan VanEps | Project Engineer | evan.vaneps@krausanderson.com
LSE Architects
Matt Korus | Construction Administrator | Mkorus@lse-architects.com
Jennifer Anderson-Tuttle | Principal | Jtuttle@lse-architects.com