View Screen Reader-Friendly Version

Mankato West High School

JUNE 2026

Construction Updates

Area A – Secure Entrance Addition

Completed

Building Structure – All Levels

  • Existing Stair Demo
  • Curtain Wall Structure at Levels 2 & 3
  • Glass Installation at Curtain Wall

Level 1

  • Terrazzo Logo Inlay
  • Door Frame Installation
  • Secure Entrance Office Flooring

Level 2

  • Ceiling Clouds
  • Steel Handrail
  • Interior Framing at Curtain Wall

Level 3

  • Ceiling Pad Installation
  • Above Ceiling & In Wall MEP
  • Casework

Exterior

  • Canopy Structural Steel
  • Metal Wall Panel Installation
  • East Parking Lot Utilities

Ongoing

Level 1

  • Paint at Elevator Fronts
  • Miscellaneous Metals
  • Upper Lobby Floor Framing

Level 2

  • Fixtures at Ceiling Clouds
  • Countertops and Windowsills

Level 3

  • Low Voltage Fixtures
  • Flooring Installation

Exterior

  • Retaining Wall Pour & Backfill
  • Framing at Canopy

Upcoming

Level 1

  • Acoustic Ceiling Baffles
  • Upper Lobby Topping Pour
  • Flooring Installation in Nurses Area

Level 2

  • Flooring at Commons
  • Structural Steel to be Installed at Existing Stairwell

Level 3

  • Interior Classroom Windows
  • Ceiling Finishes at Main Stairwell

Exterior

  • Remaining Underground Utilities
  • Site Concrete

Area B&C – Athletics Addition

Completed

  • MEP Rough-Ins at New Gym
  • Concessions Bathroom Tile
  • Excavation for Exterior Chiller/Trash Enclosure
  • Fire Suppression Rough-Ins

Ongoing

  • Gym Sound Panel Installation
  • Ceiling/Wall Paint at Gym
  • CMU Wall Installation in Storm Shelter Area
  • Metal Panel Installation at Gym Exterior
  • Tiling at Concessions Area

Upcoming

  • Concessions Bathroom Fixtures
  • Window Installation
  • Gym Corridor Terrazzo
  • Sheetrock/Tape & Sand in Locker Rooms
  • Gym Equipment & Flooring

Photos

Secure Entrance Addition - Ceiling Clouds

Secure Entrance Addition - Lobby

Terrazzo

Secure Entrance Addition - Classrooms

Flex Classroom and Level 3 Classroom

Secure Entrance Addition - Commons

Level 3 Commons

Secure Entrance Addition - Elevator

Level 3 Elevator Front

Secure Entrance Addition - Exterior

Front Entrance and Retaining Wall Location

Athletic Addition - Locker Room

Area B

Athletics Addition - Mechanical Room

Area B

Athletics Addition - Activities and Gym Corridors

Area C Activities Corridor and Gym Corridor

Athletics Addition - Chiller and Trash Enclosure

Area C

Athletics Addition - Concessions Bathroom

Area C

Athletics Addition - Gym

Area C

Videos

Last Month's Progress

Overall Site Progress

Weather

Construction Days Lost to Weather This Month: 0

Total Construction Days Lost to Weather: 12

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 280

Project Team

Kraus-Anderson Construction Company

Tyler Stadheim | Project Superintendent | Tyler.Stadheim@krausanderson.com

Rob Gemelke | Senior Project Manager | rob.gemelke@krausanderson.com

Evan VanEps | Project Engineer | evan.vaneps@krausanderson.com

LSE Architects

Matt Korus | Construction Administrator | Mkorus@lse-architects.com

Jennifer Anderson-Tuttle | Principal | Jtuttle@lse-architects.com