Construction Updates
Area A – Secure Entrance Addition
Completed
Building Structure & Exterior – All Levels
- Structural Steel Erection
- Joist and Decking Installation
- CMU Exterior Walls
- Vapor Barrier
- South Elevation of Exterior Stone Veneer
Level 1
- Underground Mechanical & Electrical
- Load Transfer Platform Placement
- Slab on Grade
- Interior Wall Framing
- Above Ceiling & In-Wall MEP Rough-ins
- In-Wall Backing Installation
- Sheetrock & Taping
Level 2
- Slab on Deck Pour
- Fireproofing at Structural Steel
- Interior Wall Framing
Level 3
- Slab on Deck Pour
- Joist & Deck Detail Welding
Ongoing
Level 1
- Interior Wall & Ceiling Paint
Level 2
- Sheetrock & Taping
- Above Ceiling MEP Rough-Ins
Level 3
- Interior Wall Framing
- Overhead & In Wall MEP Rough-Ins
Exterior
- Exterior Stone Veneer
- Window Installation
Upcoming
Level 1
- Ceiling Grid Installation
- Tile
- Pad Out Ceilings
- Casework
- MEP Finishes & Lighting Fixtures
- Flooring
Level 2
- Firestopping Installation
- Paint
- Ceiling Grid Installation
- Tile
- MEP Finishes & Lighting Fixtures
- Flooring
Level 3
- Interior Wall Framing
- Above Ceiling & In-Wall MEP Installation
- Sheetrock & Taping
- Paint
Exterior
- Structural Steel Installation for Canopy at Entryway
Area B&C – Athletics Addition
Completed
- Foundations & Grade Beams
- Backfill & Compaction
- Rigid Inclusion Installation
- Rock Haul Roads for Precast Crane
- First Phase of Precast Installation
- First Floor Hollow Core Plank Topping Slab Pour
Ongoing
- Structural Steel Joist & Decking Installation
- Ground Thaw
- Underground Plumbing at Locker Rooms
Upcoming
- Underground Mechanical & Electrical
- Load Transfer Platform Placement
- Slab on Grade Pours
Secure Entrance Addition - Level 2
Storm Shelter
Mechanical Mezzanine
Videos
Last Month's Progress
Overall Site Progress
Weather
Construction Days Lost to Weather This Month: 0
Total Construction Days Lost to Weather: 11
Safety
Lost Time Days: 0
Days Worked Without Lost Time Accident: 250
Project Team
Kraus-Anderson Construction Company
Tyler Stadheim | Project Superintendent | Tyler.Stadheim@krausanderson.com
Rob Gemelke | Senior Project Manager | rob.gemelke@krausanderson.com
Evan VanEps | Project Engineer | evan.vaneps@krausanderson.com
LSE Architects
Matt Korus | Construction Administrator | Mkorus@lse-architects.com
Jennifer Anderson-Tuttle | Principal | Jtuttle@lse-architects.com