Progress Update
Vertical Construction is moving well. The clearing, fine grading, and formation of the building pads for buildings 1, 2, and 9 is complete. We are still waiting for concrete and plumbing to be released as soon as the financing is in place. Installation of underground lines and transformers is underway..
Progress Photos
Past Updates
Want to look back? Previous project updates will are here for your convenience.
April 2022 - May 2022 - June 2022 - July 2022 - August 2022 - September 2022 - October 2022 - November 2022 - December 2022 - January 2023 - February 2023 - March 2023 - May 2023 - June 2023 - July 2023 - August 2023
For more information contact: Rob Fuller at (707) 365-6891