PROJECT RENDERINGS
CONSTRUCTION PROGRESS
Construction is approximately 3% complete, as billed through November (Pay App #3)
CONSTRUCTION ACTIVITIES
Work Completed
- Erosion control
- Long/triple jump and pole vault runs (BP-1)
- Sod at BP-1 locations
- Retaining wall East half excavation
Work Ongoing
- Selective site demolition
- Area H excavation and soil corrections
- Area H sanitary sewer main and tie-ins to existing
- Retaining wall East half footings
Work Upcoming
- Grease interceptor replacement
- Area H building pad preload
- Retaining wall East half foundation wall, drain tile, and backfill
- Retaining wall West half excavation, footings, and foundation wall
- Area I excavation
Photos
November 2025
October 2025
September 2025
Project Team
Jon Bush, Lead Superintendent
Weston Gumbert, Project Manager
Mark Breidel, Project Manager
Mathea Gray, Project Coordinator
Michael Mattson, Project Accountant
Mike Hinderman, Director of Operations
Ryan Welke, Senior Architect
Morgan Anderson, Project Administrator
Kevin Bills, Vice President
Construction updates created and managed by Kraus-Anderson Construction