PROJECT RENDERINGS
CONSTRUCTION PROGRESS
- Construction is approximately 18% complete, as billed through March (Pay App #7)
CONSTRUCTION ACTIVITIES
Work Completed
- Auto shop roof and roof drain rework
- Area H CMU fire walls
- Area H pad footings, piers, and backfill
- Area I excavation and soil corrections
- Area I footings, foundation walls, and backfill
- Storm sewer site utility
Work Ongoing
- Area H structural steel columns, beams, joists, and deck
- Area I pad footings, piers, and backfill
- Wrestling and Football Pads Storage interior remodel demolition
Work Upcoming
- Area H roof drains and piping
- Area H underground MEPs
- Area H exterior metal framing and sheathing
- Area H exterior blocking
- Area H roofing
- Chiller install
- Football Pads Storage underground plumbing
- Area I structural steel columns and beams
Photos
March 2026
February 2026
January 2026
December 2025
November 2025
October 2025
September 2025
Project Team
Jon Bush, Lead Superintendent
Weston Gumbert, Project Manager
Mark Breidel, Project Manager
Mathea Gray, Project Coordinator
Michael Mattson, Project Accountant
Mike Hinderman, Director of Operations
Ryan Welke, Senior Architect
Morgan Anderson, Project Administrator
Kevin Bills, Vice President
Construction updates created and managed by Kraus-Anderson Construction