West Salem High School Addition & Renovation CONSTRUCTION UPDATES | NOVEMBER 2025

PROJECT RENDERINGS

CONSTRUCTION PROGRESS

Construction is approximately 3% complete, as billed through November (Pay App #3)

CONSTRUCTION ACTIVITIES

Work Completed

  • Erosion control
  • Long/triple jump and pole vault runs (BP-1)
  • Sod at BP-1 locations
  • Retaining wall East half excavation

Work Ongoing

  • Selective site demolition
  • Area H excavation and soil corrections
  • Area H sanitary sewer main and tie-ins to existing
  • Retaining wall East half footings

Work Upcoming

  • Grease interceptor replacement
  • Area H building pad preload
  • Retaining wall East half foundation wall, drain tile, and backfill
  • Retaining wall West half excavation, footings, and foundation wall
  • Area I excavation

Photos

November 2025

Photography courtesy of BVisions Media

October 2025

Photography courtesy of BVisions Media

September 2025

Photography courtesy of BVisions Media

Project Team

Jon Bush, Lead Superintendent

Weston Gumbert, Project Manager

Mark Breidel, Project Manager

Mathea Gray, Project Coordinator

Michael Mattson, Project Accountant

Mike Hinderman, Director of Operations

Ryan Welke, Senior Architect

Morgan Anderson, Project Administrator

Kevin Bills, Vice President

Construction updates created and managed by Kraus-Anderson Construction