PROJECT RENDERINGS
CONSTRUCTION PROGRESS
- Construction is approximately 29% complete, as billed through April (Pay App #8)
CONSTRUCTION ACTIVITIES
Work Completed
- Area H structural steel columns, beams, joists, and deck
- Area I pad footings, piers, and backfill
- Area H roof drains and pipingÂ
- Chiller installÂ
- Wrestling and Football Pads Storage demolitionÂ
- Wrestling CMU wall and infillÂ
- Football Pads Storage underground plumbing
Work Ongoing
- Area H underground MEPs
- Area H exterior framing, sheathing, and blockingÂ
- Area H roofingÂ
- Area I structural steel columns, beams, joists, and deck
Work Upcoming
- Area H/I CMU partition wall
- Area H concrete slab
- Area H MEP overhead rough-inÂ
- Area H interior wall framingÂ
- Area I exterior framing, sheathing, and blockingÂ
- Area I roof drains and pipingÂ
- Area I underground plumbing rough-inÂ
- Football Pads Storage wall framing, MEP rough-in, and drywall
Photos
April 2026
March 2026
February 2026
January 2026
December 2025
November 2025
October 2025
September 2025
Project Team
Jon Bush, Lead Superintendent
Weston Gumbert, Project Manager
Mark Breidel, Project Manager
Mathea Gray, Project Coordinator
Michael Mattson, Project Accountant
Mike Hinderman, Director of Operations
Ryan Welke, Senior Architect
Morgan Anderson, Project Administrator
Kevin Bills, Vice President
Construction updates created and managed by Kraus-Anderson Construction