PROJECT RENDERINGS
CONSTRUCTION PROGRESS
- Construction is approximately 14% complete, as billed through February (Pay App #6)
- Productivity has been limited due to encountering unsuitable soils requiring soil corrections
CONSTRUCTION ACTIVITIES
Work Completed
- Retaining wall drain tile and backfill
- Area I building pad preload
Work Ongoing
- Auto shop roof and roof drain rework
- Area H CMU fire walls
- Area H pad footings, piers, and backfill
- Area I excavation and soil corrections
- Area I footings, foundation walls, and backfill
- Storm sewer site utility
Work Upcoming
- Area I pad footings, piers, and backfill
- Area H structural steel columns and beams
- Area I sanitary sewer mains
Photos
February 2026
January 2026
December 2025
November 2025
October 2025
September 2025
Project Team
Jon Bush, Lead Superintendent
Weston Gumbert, Project Manager
Mark Breidel, Project Manager
Mathea Gray, Project Coordinator
Michael Mattson, Project Accountant
Mike Hinderman, Director of Operations
Ryan Welke, Senior Architect
Morgan Anderson, Project Administrator
Kevin Bills, Vice President
Construction updates created and managed by Kraus-Anderson Construction