PROJECT RENDERINGS
CONSTRUCTION PROGRESS
- Construction is approximately 35% complete, as billed through May (Pay App #9)
CONSTRUCTION ACTIVITIES
Work Completed
- Area H/I underground MEPs
- Area H/I CMU partition wall
- Area H concrete slab
- Area H exterior framing, sheathing, and blocking
- Area H weather barrier
- Area I structural steel columns, beam, joists, and deck
- Area I roof drains and piping
Work Ongoing
- Area H roofing
- Area H interior wall framing and MEP overhead rough-in
- Area I exterior framing, sheathing, and blocking
- Interior remodel demo
- Courtyard window demo and infill
Work Upcoming
- Area H MEP wall rough-in
- Area H masonry veneer
- Area I concrete slab
- Area I interior wall framing and MEP overhead rough-in
- Area I roofing
- Area I weather barrier
- Interior remodel wall framing and MEP overhead rough-in
- Courtyard demo and evacuation
- Water main tie-in
Photos
May 2026
April 2026
March 2026
February 2026
January 2026
December 2025
November 2025
October 2025
September 2025
Project Team
Jon Bush, Lead Superintendent
Weston Gumbert, Project Manager
Mark Breidel, Project Manager
Mathea Gray, Project Coordinator
Michael Mattson, Project Accountant
Mike Hinderman, Director of Operations
Ryan Welke, Senior Architect
Morgan Anderson, Project Administrator
Kevin Bills, Vice President
Construction updates created and managed by Kraus-Anderson Construction