CONSTRUCTION PROGRESs
- Construction is approximately 58% complete, as billed through May (Pay App #9)
CONSTRUCTION ACTIVITIES
Work Completed
- Paint precast walls, exposed ceilings, and ductwork
- Interior remodel underground plumbing and slab infill
- Interior metal stud framing
- Gym acoustic wall panels
- EIFS
Work Ongoing
- Gym MEP ceiling and wall devicing
- Interior remodel MEP overhead and wall rough-ins
- Curtain wall and storefront
- Exterior concrete patio
Work Upcoming
- Gym door hardware
- Gym equipment
- Interior remodel drywall
- Interior remodel paint
- Corridor PLAM panels
- Suspended ceilings
PROGRESS Photos
May 2026
April 2026
March 2026
February 2026
January 2026
December 2025
November 2025
October 2025
September 2025
Project Team
Jon Bush, Lead Superintendent
Weston Gumbert, Project Manager
Mark Breidel, Project Manager
Mathea Gray, Project Coordinator
Michael Mattson, Project Accountant
Mike Hinderman, Director of Operations
Ryan Welke, Senior Architect
Morgan Anderson, Project Administrator
Kevin Bills, Vice President
Construction updates created and managed by Kraus-Anderson Construction