West Salem Elementary School Addition & Renovation

CONSTRUCTION UPDATES | FEBRUARY 2026

CONSTRUCTION PROGRESs

  • Construction is approximately 42% complete, as billed through February (Pay App #6)

CONSTRUCTION ACTIVITIES

Work Completed

  • Roof drains and storm piping
  • Exterior wood blocking
  • Exterior framing and sheathing
  • Weather barrier and spray foam

Work Ongoing

  • Biopond
  • Roofing
  • Temporary enclosures
  • Ground thaw interior slab subgrade
  • Caulk precast wall panels

Work Upcoming

  • Temporary heating
  • Interior concrete slabs
  • Mezzanine stairs and railings
  • CMU partition wall
  • MEP overhead rough-ins
  • Interior remodel temporary partitions and floor protection

PROGRESS Photos

February 2026

Photography courtesy of BVisions Media

January 2026

Photography courtesy of BVisions Media

December 2025

Photography courtesy of BVisions Media

November 2025

Photography courtesy of BVisions Media

October 2025

Photography courtesy of BVisions Media

September 2025

Photography courtesy of BVisions Media

Project Team

Jon Bush, Lead Superintendent

Weston Gumbert, Project Manager

Mark Breidel, Project Manager

Mathea Gray, Project Coordinator

Michael Mattson, Project Accountant

Mike Hinderman, Director of Operations

Ryan Welke, Senior Architect

Morgan Anderson, Project Administrator

Kevin Bills, Vice President

Construction updates created and managed by Kraus-Anderson Construction