CONSTRUCTION PROGRESs
Construction is approximately 20% complete, as billed through November (Pay App #3)
CONSTRUCTION ACTIVITIES
Work Completed
- Concrete footings and foundations
- Foundation insulation
- Underground storm sewer
- Drain tile
- Footings and foundations backfill
Work Ongoing
- CMU fire wall
Work Upcoming
- Structural steel columns and beams
- Precast wall panels
- Site utilities
- Biopond
Photos
November 2025
October 2025
September 2025
Project Team
Jon Bush, Lead Superintendent
Weston Gumbert, Project Manager
Mark Breidel, Project Manager
Mathea Gray, Project Coordinator
Michael Mattson, Project Accountant
Mike Hinderman, Director of Operations
Ryan Welke, Senior Architect
Morgan Anderson, Project Administrator
Kevin Bills, Vice President
Construction updates created and managed by Kraus-Anderson Construction