West Salem Elementary School Addition & Renovation

CONSTRUCTION UPDATES | MARCH 2026

CONSTRUCTION PROGRESs

  • Construction is approximately 45% complete, as billed through March (Pay App #7)

CONSTRUCTION ACTIVITIES

Work Completed

  • Roofing
  • Temporary enclosures and heating
  • Ground thaw interior slab subgrade
  • Interior concrete slabs
  • Interior remodel temporary partitions and floor protection

Work Ongoing

  • Biopond
  • CMU partition wall
  • Interior remodel demolition

Work Upcoming

  • Mezzanine stairs and railings
  • MEP overhead rough-ins
  • Caulk precast wall panels
  • Paint precast walls
  • Paint exposed ceilings and ductwork
  • Interior metal stud framing
  • Interior remodel underground plumbing

PROGRESS Photos

March 2026

Photography courtesy of BVisions Media

February 2026

Photography courtesy of BVisions Media

January 2026

Photography courtesy of BVisions Media

December 2025

Photography courtesy of BVisions Media

November 2025

Photography courtesy of BVisions Media

October 2025

Photography courtesy of BVisions Media

September 2025

Photography courtesy of BVisions Media

Project Team

Jon Bush, Lead Superintendent

Weston Gumbert, Project Manager

Mark Breidel, Project Manager

Mathea Gray, Project Coordinator

Michael Mattson, Project Accountant

Mike Hinderman, Director of Operations

Ryan Welke, Senior Architect

Morgan Anderson, Project Administrator

Kevin Bills, Vice President

Construction updates created and managed by Kraus-Anderson Construction