CONSTRUCTION PROGRESs
- Construction is approximately 45% complete, as billed through March (Pay App #7)
CONSTRUCTION ACTIVITIES
Work Completed
- Roofing
- Temporary enclosures and heating
- Ground thaw interior slab subgrade
- Interior concrete slabs
- Interior remodel temporary partitions and floor protection
Work Ongoing
- Biopond
- CMU partition wall
- Interior remodel demolition
Work Upcoming
- Mezzanine stairs and railings
- MEP overhead rough-ins
- Caulk precast wall panels
- Paint precast walls
- Paint exposed ceilings and ductwork
- Interior metal stud framing
- Interior remodel underground plumbing
PROGRESS Photos
March 2026
February 2026
January 2026
December 2025
November 2025
October 2025
September 2025
Project Team
Jon Bush, Lead Superintendent
Weston Gumbert, Project Manager
Mark Breidel, Project Manager
Mathea Gray, Project Coordinator
Michael Mattson, Project Accountant
Mike Hinderman, Director of Operations
Ryan Welke, Senior Architect
Morgan Anderson, Project Administrator
Kevin Bills, Vice President
Construction updates created and managed by Kraus-Anderson Construction