CONSTRUCTION PROGRESs
- Construction is approximately 42% complete, as billed through February (Pay App #6)
CONSTRUCTION ACTIVITIES
Work Completed
- Roof drains and storm piping
- Exterior wood blocking
- Exterior framing and sheathing
- Weather barrier and spray foam
Work Ongoing
- Biopond
- Roofing
- Temporary enclosures
- Ground thaw interior slab subgrade
- Caulk precast wall panels
Work Upcoming
- Temporary heating
- Interior concrete slabs
- Mezzanine stairs and railings
- CMU partition wall
- MEP overhead rough-ins
- Interior remodel temporary partitions and floor protection
PROGRESS Photos
February 2026
January 2026
December 2025
November 2025
October 2025
September 2025
Project Team
Jon Bush, Lead Superintendent
Weston Gumbert, Project Manager
Mark Breidel, Project Manager
Mathea Gray, Project Coordinator
Michael Mattson, Project Accountant
Mike Hinderman, Director of Operations
Ryan Welke, Senior Architect
Morgan Anderson, Project Administrator
Kevin Bills, Vice President
Construction updates created and managed by Kraus-Anderson Construction