West Salem Elementary School Addition & Renovation

CONSTRUCTION UPDATES | APRIL 2026

CONSTRUCTION PROGRESs

  • Construction is approximately 52% complete, as billed through April (Pay App #8)

CONSTRUCTION ACTIVITIES

Work Completed

  • CMU partition wall
  • Caulk precast wall panels 
  • Mezzanine stairs 
  • Gym MEP overhead rough-ins
  • Interior remodel demolition

Work Ongoing

  • Paint precast walls
  • Paint exposed ceilings and ductwork 
  • Interior metal stud framing 
  • Interior remodel underground plumbing
  • Interior remodel windows 
  • Biopond

Work Upcoming

  • Gym MEP ceiling and wall devicing
  • Gym acoustic wall panels
  • Corridor ceilings 
  • EIFS 
  • Interior remodel slab infill 
  • Interior remodel MEP overhead and wall rough-ins
  • Interior remodel drywall

PROGRESS Photos

April 2026

Photography courtesy of BVisions Media

March 2026

Photography courtesy of BVisions Media

February 2026

Photography courtesy of BVisions Media

January 2026

Photography courtesy of BVisions Media

December 2025

Photography courtesy of BVisions Media

November 2025

Photography courtesy of BVisions Media

October 2025

Photography courtesy of BVisions Media

September 2025

Photography courtesy of BVisions Media

Project Team

Jon Bush, Lead Superintendent

Weston Gumbert, Project Manager

Mark Breidel, Project Manager

Mathea Gray, Project Coordinator

Michael Mattson, Project Accountant

Mike Hinderman, Director of Operations

Ryan Welke, Senior Architect

Morgan Anderson, Project Administrator

Kevin Bills, Vice President

Construction updates created and managed by Kraus-Anderson Construction