Oak-Land Middle School

Construction Activities Progress | March 1, 2026 - March 31, 2026

Overall Progress Drone Video

Sitework/Exterior

Work in Progress:

  • Exterior mansard panels

Work Completed:

Work Upcoming Next Month:

Gym Addition

Work in Progress:

  • Gym equipment
  • Bathroom tile
  • Structural steel in hallway

Work Completed:

  • Precast patching on damaged areas
  • Drywall in bathroom group
  • Storm shelter windows

Work Upcoming Next Month:

  • Painting
  • Ceiling grid
  • Metal stud framing in hallway
  • Gym flooring

New Media Center

Work in Progress:

  • Structural Steel Joists
  • MEP Ceiling Rough-ins

Work Completed:

  • Mobilization
  • Abatement
  • MEP selective demo
  • Floor cutting

Work Upcoming Next Month:

  • Pour back trenches
  • Pour 2” topping slab in media center
  • Framing interior walls
  • In-wall backing

Office Remodel

Work in Progress:

  • MEP rough-ins and above ceiling rough-ins

Work Completed:

  • Mobilization
  • MEP selective demolition
  • Selective demolition
  • Cut out floor for new columns

Work Upcoming Next Month:

  • Install of bar joists
  • Install columns
  • Framing

Kitchen/Mechanical Room

Work in Progress:

  • Roughing in chiller
  • Tunnel & boiler work

Work Completed:

  • Poured slab for new chiller
  • Install new chiller

Work Upcoming Next Month:

  • Abatement
  • Boiler demolition
  • Demo of housekeeping pad

Classroom Remodel - Starting in May

Work in Progress:

Work Completed:

Work Upcoming Next Month:

Science Addition

Work in Progress:

  • Structural Steel

Work Completed:

Work Upcoming Next Month:

  • Cold Formed Framing

Classroom Addition

Work In Progress:

  • Structural steel

Work Completed:

Work Upcoming Next Month:

Photos

March 2026 Progress
February 2026 Progress
January 2026 Progress
December 2025 Progress
November 2025 Progress
October 2025 Progress
September 2025 Progress
August 2025 Progress
July 2025 Progress
June 2025 Progress
May 2025 Progress