Oak-Land Middle School

Construction Activities Progress | February 1, 2026 - February 28, 2026

Overall Progress Drone Video

Sitework/Exterior

Work in Progress:

  • Exterior mansard panels

Work Completed:

Work Upcoming Next Month:

Gym Addition

Work in Progress:

  • Precast patching on damaged areas
  • Drywall in bathroom group
  • Storm shelter windows

Work Completed:

  • MEP above ceiling rough-ins inside storm structure
  • Louvers inside gym

Work Upcoming Next Month:

  • Painting
  • Ceiling grid
  • Gym equipment
  • Bathroom tile
  • Structural steel in hallway
  • Metal stud framing in hallway
  • Gym equipment
  • Gym flooring

Science Addition

Work in Progress:

Work Completed:

Work Upcoming Next Month:

  • Structural steel

Classroom Addition

Work in Progress:

Work Completed:

Work Upcoming Next Month:

  • Structural steel

New Media Center

Work in Progress:

Work Completed:

Work Upcoming Next Month:

  • Mobilization
  • Abatement
  • MEP selective demo

Classroom Remodel

Work in Progress:

Work Completed:

Work Upcoming Next Month:

Kitchen / Mechanical Room

Work in Progress:

  • Poured slab for new freezer

Work Completed:

Work Upcoming Next Month:

  • Tunnel & boiler work

Photos

February 2026 Progress
January 2026 Progress
December 2025 Progress
November 2025 Progress
October 2025 Progress
September 2025 Progress
August 2025 Progress
July 2025 Progress
June 2025 Progress
May 2025 Progress