Oak-Land Middle School

Construction Activities Progress | April 1, 2026 - April 30, 2026

Overall Progress Drone Video

Sitework/Exterior

Work in Progress:

Work Completed:

Work Upcoming Next Month:

  • Aggregate Touch-Up
  • Rough Grading of Site

Gym Addition (Area J)

Work in Progress:

  • Gym Equipment
  • Bathroom Tile
  • Exterior Sheathing
  • Cold Formed Framing for Hallway
  • MEP Rough-ins/Finishes
  • Door Frames

Work Completed:

  • Painting
  • Structural Steel in Hallway

Work Upcoming Next Month:

  • Ship Ladder into Mezzanine
  • Metal Stud Framing in Hallway
  • Gym Flooring
  • Weather Barrier in Hallway
  • Storefronts & Vestibules
  • Drywall
  • Insulation
  • Exterior Brick in Hallway
  • MEP Rough-ins in Hallway
  • Terrazzo

New Media Center (Area E)

Work in Progress:

  • Framing Interior Walls

Work Completed:

  • Structural Steel Joists
  • MEP Ceiling Rough-ins
  • Pour Back Trenches
  • Pour 2” Topping Slab in Media Center

Work Upcoming Next Month:

  • In-wall Backing
  • MEP Rough-Ins
  • Roof Demo
  • Wall Cutting

Office Remodel (Area B - Office)

Work in Progress:

  • MEP Wall Rough-Ins
  • Drywall

Work Completed:

  • MEP Above Ceiling Rough-ins
  • Install of Bar Joists
  • Install Columns
  • Interior Framing
  • Door Frames

Work Upcoming Next Month:

  • Demo Out Hallway Wall
  • Roof Demo
  • Ceiling and Lighting Demo of Classroom
  • Install Remaining Joists

Band Remodel (Area B - Band)

Work in Progress:

Work Completed:

Work Upcoming Next Month:

  • Abatement
  • CMU Wall Demo
  • Concrete Riser Demo

Kitchen/Mechanical Room (Area D)

Work in Progress:

  • Roughing in Chiller
  • Boiler 2 Demolition
  • Freezer Pad Pour

Work Completed:

  • Tunnel & Boiler Work
  • Abatement
  • Boiler 1 Demolition
  • Excavation of Freezer Pad

Work Upcoming Next Month:

  • Demo of Housekeeping Pad
  • Mechanical Demo

Classroom Remodel (Area F Renovation)

Work in Progress:

Work Completed:

Work Upcoming Next Month:

  • MEP Demo

Classroom Addition (Area F Addition)

Work in Progress:

  • Cold Formed Framing

Work Completed:

  • Structural Steel
  • Metal Decking

Work Upcoming Next Month:

  • Interior Framing
  • Weather Barrier
  • MEP Wall and Ceiling Rough-Ins

Science Remodel (Area G Renovation)

Work In Progress:

Work Completed:

Work Upcoming Next Month:

  • MEP Demo

Science Addition (Area G Addition)

Work in Progress:

  • Weather Barrier

Work Completed:

  • Structural Steel
  • Cold Formed Framing
  • Sheathing

Work Upcoming Next Month:

  • Interior Framing
  • MEP Wall and Ceiling Rough-Ins

Interior Renovations (Area A, C, H)

Work in Progress:

Work Completed:

Work Upcoming Next Month:

  • MEP Demo
  • Ceiling Demo

Photos

March 2026 Progress
February 2026 Progress
January 2026 Progress