Botanica Oak Hills August 2023

Progress Update

Construction at Botanica Oak Hills has continued steadily over the past few months. Notably, all Tyvek wrap installation is now complete on erected buildings, and stucco work has been finalized through building 18, leaving five buildings to go. Framing for all buildings, except those being adjusted to a 1-unit design, has been successfully finished. The door installation process is in progress for Phase 1, and exterior woodlook and black slate tile installation has been successfully carried out across Phases 1, 2, and parts of 3.

Additionally, electrical meter panels have been installed throughout Phase 1 and has started in Phase 2. Interior and exterior painting efforts are underway throughout Phase 1. Various installation tasks, including fins, flooring, fire protection, cabinets, countertops, and bathroom tiles, have reached notable completion milestones, reflecting steady advancement. Looking ahead, the Phase 5’s floor plans are complete and have been submitted for permits.

Progress Images

Location Images

Past Updates

Want to look back? Previous project updates are here for your convenience.

April 2022 - May 2022 - July 2022 - August 2022 - September 2022 - October 2022 - November 2022 - January 2023 - February 2023 - March 2023 - May 2023

If you would like to see more on the planned outcome of the project visit UrbanistUSA.

For more information contact: Rob Fuller at (707) 365-6891