The Hayward High School additions and remodeling project includes two separate additions; a gymnasium addition (with an elevated track and associated aerobic/strength training) and a secure entry office addition. Additionally, general renovations throughout the existing school, including casework, flooring, and access control/security upgrades.
Construction Activities this Month
Hayward High School - Current Drone Video
Area A - Office Addition
Completed
- Site clearing and demolition
- Excavate and pour foundation footings to support new addition
- Construction of new foundation walls
- Began erection of structural steel
- Delivery and placement of precast wall panels.
- Installation and placement of joist and deck.
Upcoming
- Mechanical and Electrical Rough-ins to include underground plumbing
- Structural stud framing
- Roofing
- Exterior enclosure of addition
Area B - Gymnasium Addition
Completed
- Site clearing and demolition
- Back fill and reach grade for slab to be poured
- Excavate and pour foundation footings to support new addition
- Delivery and erection of structural steel.
- Delivery and placement of precast wall panels.
- Installation and placement of joist and deck.
- Installation of running track steel
Upcoming
- Lay block walls for new elevator shaft
- Final grade of gym floor
- Pour slab on grade for new gym floor
- Mechanical and Electrical Rough Ins
Area B - Locker Rooms & Kitchen Renovation
Completed
- Mechanical and Electrical Rough Ins to include underground plumbing modifications in locker rooms.
- Began interior selective demolition of existing upper-level gymnasium
- Tile installation in locker rooms.
- Paint locker rooms.
- Finish installation of new epoxy floor finish.
- Installation of new lockers in locker rooms.
- Construction cleaning
- Installation of new lockers in locker rooms.
- Construction cleaning
- Owner Move In!
Upcoming
- Completion of Punch List Items
Area C - CTE Renovation
Completed
- Selective demo including walls, ceiling, flooring and miscellaneous casework.
- Initial shoring
- Mechanical and Electrical Rough Ins and undergrounds
- Delivery and erection of structural steel and new CMU walls
- Elevator shaft excavation and placement
- Interior foundations
- Shoring removed for new load bearing walls
- Continue corridor floor grinding for future bomanite finish
- Installation and completion of ceiling grid
- Final installation of MEP finishes
- Final paint and construction cleaning
- Owner Move In!
Upcoming
- Completion of Punch List Items
Area C - Classrooms & Corridors (Science, Math, Business & FACE/CNA) Renovation
Completed
- Selective demo including walls, ceiling, flooring and miscellaneous casework.
- Corridor floor grinding for future bomanite finish
- Mechanical and Electrical Rough Ins and undergrounds
- Construction of framing and drywall for new walls
- Installation of interior finishes to include new ACT (acoustical ceiling tile) – currently in progress.
- Laying of new carpet in classrooms.
- Complete bathroom finishes to include tile and mechanical fixture upgrades.
- Final paint and construction cleaning
- Owner Move-In!
Upcoming
- Completion of Punch List Items
Area D - Classrooms & Restrooms Renovation
Completed
- Painting
- Installation of interior finishes to include new ACT (acoustical ceiling tile)
- Polishing Concrete at finished floors
- Framing and drywall new walls
- Laying of new carpet in classrooms.
- Complete bathroom finishes to include tile and mechanical fixture upgrades.
- Construction cleaning
- Owner Move-In!
Upcoming
- Completion of Punch List Items
Building Envelope and Canopy Renovations
Completed
- Removal of brick facade for the installation of new brick facade and metal panel exterior finish.
Upcoming
- Installation of weather barrier and metal panel on exterior of building.
Weather
Construction Days lost to Weather This Month: 0
Total Construction Days lost to Weather: 0
Safety
Lost Time Days: 0
Days Worked Without Lost Time Accident: 122
Schedule
Construction starting in May 2023 with final completion in August 2024.
Renderings
Project team
Kraus-Anderson
Dustin Phillips, Senior Project Manager | dustin.phillips@krausanderson.com
Mike Phillips, Project Manager | mike.phillips@krausanderson.com
Cole Tobin, Project Superintendent | cole.tobin@krausanderson.com
Laurie Fronk, Senior Project Coordinator | laurie.fronk@krausanderson.com