Bayport Elementary School

Construction Activities Progress | May 1, 2026 - May 31, 2026

May Progress Drone Video

Overall Progress Drone Video

Classrooms

Work in Progress:

  • Nora Rubber - Lower-Level C
  • Terrazzo - Lower-Level C
  • Interior Stone – Area C

Work Completed:

  • Painted Concrete - Lower-Level D, Lower-Level C, Lower-Level B
  • Nora Rubber - Lower-Level D, Lower-Level B
  • Mud Room Casework - Lower-Level D, Lower-Level C
  • Paint ACT - Upper-Level D, Upper-Level B
  • Casework - Upper-Level D, Upper-Level C, Upper-Level B
  • Carpet - Upper-Level D, Lower-Level B, Upper-Level B
  • Operable Walls - Upper-Level D, Lower-Level C, Lower-Level B
  • Doors & Hardware - Upper-Level D, Lower-Level C, Upper-Level C, Lower-Level B, Upper-Level B
  • Elevator Install - Lower-Level C
  • Terrazzo - Upper-Level C
  • Miscellaneous Specialties - Upper-Level C
  • MEP Finishes - Upper-Level B

Work Upcoming Next Month:

  • Miscellaneous Specialties - Lower-Level D, Lower-Level C, Lower-Level B
  • Cloud Baffles - Upper-Level D, Lower-Level C, Upper-Level C, Lower-Level B, Upper-Level B
  • Mud Room Casework - Upper-Level D, Upper-Level C, Lower-Level B, Upper-Level B
  • Nora Rubber - Upper-Level D, Upper-Level C
  • Circulation Grid - Lower-Level C
  • MEP in Gird - Lower-Level C
  • Specialty Ceilings - Lower-Level C, Upper-Level C
  • MEP in Specialty Ceilings - Lower-Level C
  • Carpet - Upper-Level C
  • Painted Concrete - Upper-Level C, Upper-Level B
  • ACT Pad Out - Upper-Level C
  • Traffic Topping - Upper-Level C, Upper-Level B

Commons/Office

Work in Progress:

  • Stone Work
  • Main Entry Baffle Ceiling

Work Completed:

  • MEP Finishes in Grid
  • Toilets and Lavatories
  • Interior Glass
  • Nora Rubber

Work Upcoming Next Month:

  • Wall Coverings
  • Display Cases
  • Final Clean

Kitchen/Cafeteria

Work in Progress:

  • Acoustical Wall Paneling

Work Completed:

  • MEP Finishes in Grid
  • Doors & Hardware
  • Ceiling Tiles
  • Kitchen Equipment

Work Upcoming Next Month:

  • AHU Start-up
  • Chiller Start-up
  • Final Clean

Gym

Work in Progress:

  • Volleyball Sleeves

Work Completed:

  • Gym Flooring
  • Mechanical in Mezzanine

Work Upcoming Next Month:

  • Traffic Topping in Mezzanine
  • Bleachers
  • Storm Coiling Doors
  • Final Clean

Sitework & Exterior

Work in Progress:

  • Aggregate Base - South Site
  • Fence Footings & Posts - South Site
  • Cast Stone Veneer

Work Completed:

  • Aggregate Base – Turn Lane, North Site
  • Curbs – Turn Lane
  • Base Course – Turn Lane
  • Wear Course – Turn Lane
  • Striping – Turn Lane
  • Fence – South Site
  • Grading - South Site

Work Upcoming Next Month:

  • Grading - North Site
  • Sidewalks - North Site, South Site
  • Remaining Curbs - North Site, South Site
  • Chain Link Fence - South Site
  • Playground
  • Outdoor Learning Pad

Photos

May 2026 Progress
April 2026 Progress
March 2026 Progress
February 2026 Progress
January 2026 Progress
December 2025 Progress
November 2025 Progress
October 2025 Progress
September 2025 Progress
August 2025 Progress
June 2025 Progress
May 2025 Progress
April 2025 Progress
March 2025 Progress