Bayport Elementary School

Construction Activities Progress | April 1, 2026 - April 30, 2026

March Progress Drone Video

Overall Progress Drone Video

Classrooms

Work in Progress:

  • Install Stone Walls Around Media
  • Elevator Install
  • Doors and Hardware - Lower-Level C
  • Install ACT – Upper-Level C & Upper-Level B
  • Nanawalls - Upper-Level C
  • Carpet - Lower-Level B
  • Painted Concrete - Lower-Level B

Work Completed:

  • Tile – Lower-Level B & Upper-Level B
  • Install Toilets and Lavatories – Lower-Level D, Lower-Level C, Lower-Level B
  • Install Grid – Lower-Level D, Upper-Level C, Upper-Level B
  • Install ACT – Lower-Level D, Upper-Level D, Lower-Level C, Lower-Level B
  • Casework – Lower-Level D, Lower-Level C
  • Carpet - Lower-Level D & Lower-Level C
  • Nanawalls - Lower-Level D & Lower-Level B
  • Painted Concrete - Lower-Level D & Lower-Level C
  • Doors and Hardware - Lower-Level D
  • Wall Panels - Lower-Level D
  • Acoustic Ceilings – Lower-Level D
  • MEP Finish in Grid - Upper-Level D, Lower-Level C, Upper-Level C, Lower-Level B, Upper-Level B
  • Stairs - Learning Commons & Area B
  • Tile - Learning Commons & Upper-Level C

Work Upcoming Next Month:

  • Carpet - Upper-Level D & Upper-Level C
  • Casework –Upper-Level D, Upper-Level C, Upper-Level B
  • Painted Concrete - Upper-Level D & Upper-Level C
  • Doors and Hardware - Upper-Level D, Lower-Level C, Lower-Level B
  • Nora Rubber – Lower-Level D, Upper-Level D, Lower-Level C, Lower-Level B
  • Terrazzo – Lower-Level C

Commons/Office

Work in Progress:

  • MEP Finishes in Grid
  • Toilets and Lavatories

Work Completed:

  • Doors & Hardware
  • Ceiling Grid ACT in Office
  • Carpet
  • Curtainwalls and Storefronts

Work Upcoming Next Month:

  • Interior Glass
  • Kitchen Equipment

Kitchen/Cafeteria

Work in Progress:

  • MEP Finishes in Grid

Work Completed:

  • Kitchen Flooring
  • Ceiling Grid in Kitchen
  • Drywall Clouds
  • Install of Toilets and Sinks

Work Upcoming Next Month:

  • Set Kitchen Equipment

Gym

Work in Progress:

  • Gym Flooring
  • Mechanical in Mezzanine

Work Completed:

  • Basketball Hoops
  • Ceiling Grid in Bathroom
  • Install Toilets and Lavatories

Work Upcoming Next Month:

Sitework & Exterior

Work in Progress:

  • Install Missing Glass

Work Completed:

Work Upcoming Next Month:

  • Start-up Mechanical Units
  • Turn Lane Grading
  • Turn Lane Curbs
  • Turn Lane Tolerancing
  • Turn Lane Paving
  • Sout Site Grading
  • Aggregate Base

Photos

April 2026 Progress
March 2026 Progress
February 2026 Progress
January 2026 Progress
December 2025 Progress
November 2025 Progress
October 2025 Progress
September 2025 Progress
August 2025 Progress
June 2025 Progress
May 2025 Progress
April 2025 Progress
March 2025 Progress