May Progress Drone Video
Overall Progress Drone Video
Classrooms
Work in Progress:
- Nora Rubber - Lower-Level C
- Terrazzo - Lower-Level C
- Interior Stone – Area C
Work Completed:
- Painted Concrete - Lower-Level D, Lower-Level C, Lower-Level B
- Nora Rubber - Lower-Level D, Lower-Level B
- Mud Room Casework - Lower-Level D, Lower-Level C
- Paint ACT - Upper-Level D, Upper-Level B
- Casework - Upper-Level D, Upper-Level C, Upper-Level B
- Carpet - Upper-Level D, Lower-Level B, Upper-Level B
- Operable Walls - Upper-Level D, Lower-Level C, Lower-Level B
- Doors & Hardware - Upper-Level D, Lower-Level C, Upper-Level C, Lower-Level B, Upper-Level B
- Elevator Install - Lower-Level C
- Terrazzo - Upper-Level C
- Miscellaneous Specialties - Upper-Level C
- MEP Finishes - Upper-Level B
Work Upcoming Next Month:
- Miscellaneous Specialties - Lower-Level D, Lower-Level C, Lower-Level B
- Cloud Baffles - Upper-Level D, Lower-Level C, Upper-Level C, Lower-Level B, Upper-Level B
- Mud Room Casework - Upper-Level D, Upper-Level C, Lower-Level B, Upper-Level B
- Nora Rubber - Upper-Level D, Upper-Level C
- Circulation Grid - Lower-Level C
- MEP in Gird - Lower-Level C
- Specialty Ceilings - Lower-Level C, Upper-Level C
- MEP in Specialty Ceilings - Lower-Level C
- Carpet - Upper-Level C
- Painted Concrete - Upper-Level C, Upper-Level B
- ACT Pad Out - Upper-Level C
- Traffic Topping - Upper-Level C, Upper-Level B
Commons/Office
Work in Progress:
- Stone Work
- Main Entry Baffle Ceiling
Work Completed:
- MEP Finishes in Grid
- Toilets and Lavatories
- Interior Glass
- Nora Rubber
Work Upcoming Next Month:
- Wall Coverings
- Display Cases
- Final Clean
Kitchen/Cafeteria
Work in Progress:
Work Completed:
- MEP Finishes in Grid
- Doors & Hardware
- Ceiling Tiles
- Kitchen Equipment
Work Upcoming Next Month:
- AHU Start-up
- Chiller Start-up
- Final Clean
Gym
Work in Progress:
Work Completed:
- Gym Flooring
- Mechanical in Mezzanine
Work Upcoming Next Month:
- Traffic Topping in Mezzanine
- Bleachers
- Storm Coiling Doors
- Final Clean
Sitework & Exterior
Work in Progress:
- Aggregate Base - South Site
- Fence Footings & Posts - South Site
- Cast Stone Veneer
Work Completed:
- Aggregate Base – Turn Lane, North Site
- Curbs – Turn Lane
- Base Course – Turn Lane
- Wear Course – Turn Lane
- Striping – Turn Lane
- Fence – South Site
- Grading - South Site
Work Upcoming Next Month:
- Grading - North Site
- Sidewalks - North Site, South Site
- Remaining Curbs - North Site, South Site
- Chain Link Fence - South Site
- Playground
- Outdoor Learning Pad