Lake Elmo School

Construction Activities Progress | June 2026

This Month's Progress

Overall Progress

Site Work

Work in Progress:

  • Monument sign base
  • Playground construction
  • Final grading of site
  • Site fencing
  • Tree installation
  • Mulch
  • Irrigation
  • Rubber surface infill at playground

Work Completed:

  • Kickball field aggregate
  • Parking lot curbs
  • Asphalt trails along County Roads
  • Chiller enclosure/screen wall
  • Sidewalks on north of building
  • Outdoor learning wall
  • Sidewalks on south of building

Work Upcoming Next Month:

  • Installing Sod
  • Parking lot prep
  • Parking lot signage
  • Seed storm ponds

Classrooms

Work in Progress:

  • Casework installation
  • Door’s installation
  • Exterior metal panels

Work Completed:

  • Interior painting
  • Epoxy flooring
  • Light fixture installation
  • Mechanical diffusers
  • Ceiling tile
  • Decorative ceiling assemblies
  • Carpet and resilient flooring
  • Installing glass operable walls
  • Terrazzo flooring
  • Small classroom wallpaper
  • Acoustic wallboard

Work Upcoming Next Month:

  • Punchlist items
  • Final cleaning
  • Window trim
  • Final polishing of terrazzo
  • Fire rated door frame installation

Commons/Media Center

Work in Progress:

  • Cabinet installations
  • Light fixture installation
  • Low voltage cable pull
  • Wall and floor tile
  • Painting
  • Terrazzo flooring
  • Mechanical diffusers
  • Ceiling tile
  • Doors and hardware
  • Light fixtures
  • Architectural ceiling sun
  • Aluminum entrances

Work Completed:

  • Exterior metal panels
  • Exterior windows
  • Epoxy flooring
  • Ceiling grid
  • Interior windows
  • Bathroom plumbing finishes
  • Toilet partitions

Work Upcoming Next Month:

  • Carpet and resilient flooring
  • Painting
  • Install entry doors

Kitchen/Cafeteria

Work in Progress:

  • Epoxy flooring
  • Kitchen equipment
  • Terrazzo flooring
  • Light fixtures
  • Acoustical panels
  • Exterior metal panels

Work Completed:

  • Kitchen flooring
  • Overhead coiling doors
  • Main electrical and boiler room equipment finishes
  • Exterior windows
  • Painting
  • Low voltage cable pulling
  • Main electrical and boiler room equipment rough ins
  • Ceiling grid
  • Mechanical diffusers

Work Upcoming Next Month:

  • Cabinet installations
  • Final polishing of terrazzo

Gym

Work in Progress:

  • Doors and hardware
  • Leveling the concrete

Work Completed:

  • Windows
  • Acoustical wall panels
  • Wall and ceiling painting
  • Electrical finishes
  • Gym equipment
  • Overhead coiling door installation
  • Toilet partitions and accessories

Work Upcoming Next Month:

  • Wood flooring

Progress Photos

April 2025