Lake Elmo School

Construction Activities Progress | April 2026

This Month's Progress

Overall Progress

Site Work

Work in Progress:

  • Final grading of site
  • Kickball field and site fencing

Work Completed:

Work Upcoming Next Month:

  • Playground construction
  • Monument sign
  • Irrigation starts

Classrooms

Work in Progress:

  • Doors and hardware
  • Decorative ceiling assemblies
  • Mechanical diffusers
  • Exterior metal panels
  • Carpet and resilient flooring
  • Light fixture installation
  • Cabinet installation
  • Terrazzo flooring
  • Interior painting
  • Installing glass operable walls

Work Completed:

  • Wall and floor tile
  • Bathroom plumbing finishes and accessories
  • Ceiling grid
  • Low voltage cable pulling
  • Interior windows
  • Markerboards

Work Upcoming Next Month:

  • Epoxy flooring
  • Architectural glass walls
  • Ceiling tile

Commons/Media Center

Work in Progress:

  • Low voltage cable pull
  • Ceiling grid
  • Exterior metal panels
  • Bathroom plumbing finishes
  • Toilet partitions
  • Wall and floor tile
  • Exterior and interior windows
  • Painting
  • Terrazzo flooring
  • Mechanical diffusers

Work Completed:

  • Mechanical, electrical, and plumbing rough-ins
  • Installing glass operable wall

Work Upcoming Next Month:

  • Cabinet installations
  • Epoxy flooring

Kitchen/Cafeteria

Work in Progress:

  • Main electrical and boiler room equipment rough-ins
  • Overhead coiling doors
  • Exterior windows
  • Terrazzo
  • Painting
  • Wall tile
  • Low voltage cable pulling

Work Completed:

  • Drywall taping and finishing
  • Exterior brick
  • Kitchen exhaust hoods

Work Upcoming Next Month:

  • Ceiling grid
  • Light fixtures
  • Mechanical diffusers
  • Acoustical panels
  • Kitchen flooring
  • Exterior metal panels
  • Epoxy flooring

Gym

Work in Progress:

  • Gym dividing wall
  • Wall and ceiling painting
  • Gym equipment
  • Electrical finishes

Work Completed:

  • Mechanical, electrical and plumbing rough-ins
  • Louver installation

Work Upcoming Next Month:

  • Interior precast caulking
  • Window blocking
  • Overhead coiling door installations
  • Epoxy flooring
  • Acoustical wall panels

Progress Photos

April 2025