Lake Elmo School Construction Activities Progress | December 2025

November Progress

Overall Progress

Site Work

Work in Progress:

  • Site work paused for the winter

Work Completed:

  • Country road striping

Work Upcoming Next Month:

  • Site work paused for the winter

Classrooms

Work in Progress:

  • Mechanical, electrical and plumbing rough-ins
  • Interior wall framing
  • Weather barrier
  • Exterior brick
  • Drywall hanging and taping
  • Exterior windows

Work Completed:

  • Roofing

Work Upcoming Next Month:

  • Operable glass wall installation
  • Wall and ceiling painting
  • Stair and railing installation

Commons/Media Center

Work in Progress:

  • Mechanical, electrical, and plumbing rough-ins
  • Interior wall framing
  • Weather barrier
  • Drywall hanging and taping
  • Exterior brick

Work Completed:

  • Roofing

Work Upcoming Next Month:

  • Stair and railing installation
  • Wall and ceiling painting

Kitchen/Cafeteria

Work in Progress:

  • Mechanical, electrical, and plumbing rough-ins
  • Roofing
  • Interior wall framing
  • Weather barrier

Work Completed:

  • Pour mechanical housekeeping pads
  • Interior masonry walls

Work Upcoming Next Month:

  • Set mechanical equipment
  • Set walk-in cooler and freezer

Gym

Work in Progress:

  • Exterior precast caulking
  • Roof carpentry

Work Completed:

  • Roof topping slab

Work Upcoming Next Month:

  • Window blocking
  • Roofing
  • Start mechanical rough-ins
  • Interior wall framing
  • Wall and ceiling painting
  • Set mechanical equipment