Lake Elmo School

Construction Activities Progress | May 2026

This Month's Progress

Overall Progress

Site Work

Work in Progress:

  • Parking lot curbs
  • Pavement trails
  • Concrete sidewalks
  • Monument sign base
  • Chiller enclosure/screen wall
  • Outdoor learning wall
  • Playground construction
  • Final grading of site
  • Site fencing

Work Completed:

  • Kickball field aggregate

Work Upcoming Next Month:

  • Irrigation starts

Classrooms

Work in Progress:

  • Doors and hardware
  • Decorative ceiling assemblies
  • Mechanical diffusers
  • Carpet and resilient flooring
  • Light fixture installation
  • Cabinet installation
  • Terrazzo flooring
  • Installing glass operable walls
  • Ceiling tile

Work Completed:

  • Exterior metal panels
  • Interior painting
  • Epoxy flooring

Work Upcoming Next Month:

  • Final cleaning

Commons/Media Center

Work in Progress:

  • Cabinet installations
  • Light fixture installation
  • Low voltage cable pull
  • Ceiling grid
  • Bathroom plumbing finishes
  • Toilet partitions
  • Wall and floor tile
  • Interior windows
  • Painting
  • Terrazzo flooring
  • Mechanical diffusers

Work Completed:

  • Exterior metal panels
  • Exterior windows
  • Epoxy flooring

Work Upcoming Next Month:

  • Ceiling tile
  • Carpet and resilient flooring
  • Doors and hardware

Kitchen/Cafeteria

Work in Progress:

  • Ceiling grid
  • Mechanical diffusers
  • Epoxy flooring
  • Kitchen equipment
  • Main electrical and boiler room equipment finishes
  • Terrazzo flooring
  • Wall tile

Work Completed:

  • Exterior metal panels
  • Kitchen flooring
  • Overhead coiling doors
  • Exterior windows
  • Painting
  • Low voltage cable pulling
  • Main electrical and boiler room equipment rough-ins

Work Upcoming Next Month:

  • Light fixtures
  • Acoustical panels
  • Cabinet installations

Gym

Work in Progress:

  • Toilet partitions and accessories
  • Epoxy flooring
  • Gym dividing wall
  • Wall and ceiling painting
  • Gym equipment
  • Electrical finishes
  • Interior precast caulking

Work Completed:

  • Windows
  • Acoustical wall panels

Work Upcoming Next Month:

  • Wood flooring
  • Doors and hardware
  • Overhead coiling door installations

Progress Photos

April 2025