View Screen Reader-Friendly Version

Hoover Elementary School

CONSTRUCTION UPDATES | JUNE 2026

Construction Updates

Area C – New Addition

Completed:

Interior Work

  • Painting
  • Ceramic Tile
  • Fire Suppression Rough-In
  • Ceiling Grid
  • Drywall Mudding and Taping
  • Bathroom Accessories

Exterior Work

  • Window Frame Installation
  • Sheet Metal Flashing at Rooftop

Ongoing:

  • MEP Finishes
  • Site Utilities Tie-In

Upcoming:

Interior Work

  • Casework
  • Door & Hardware
  • Flooring

Exterior Work

  • Glazing Installation

Area - Existing Building

Completed:

Interior Work

  • Casework Demolition
  • Interior Wall Demolition
  • Air Handling Unit Installation
  • CMU Block Infill
  • Existing Boiler Pad Demolition
  • New Boiler Pad Pour Back

Exterior Work

  • Solar Tube Installation
  • Chimney Demolition
  • Existing Roof Top Equipment Demolition
  • Roof Patching at Existing Equipment Demolition

Ongoing:

  • Structural Steel Support
  • MEP Rough-Ins
  • Mechanical/Plumbing Insulation
  • Interior Wall Framing
  • Drywall Hanging, Taping, Mudding
  • Ceiling Grid Installation
  • Painting
  • Boiler Installation

Upcoming:

Interior Work

  • Flooring
  • Ships Ladder

Exterior Work

  • Roof Top Unit Placement
  • Roof Top Curb Installation

Area - Tunnel

Completed:

  • Plumbing Demolition
  • Electrical Wiring

Ongoing:

  • HVAC Piping Installation

Photos

Existing Building Exterior

Chimney Demolition and Solar Tube Installation

Existing Building Interior

Wall Demolition; Interior Wall Framing; CMU Wall Infill; and Drywall Hanging
Above-Ceiling Mechanical Duct Insulation; Air Handling Units & AHU Piping; Ceiling Grid Installation; Drywall, Taping and Mudding; Existing Boiler Pad Demolition and Concrete Boiler Pad Pour Back

New Addition Exterior

Sheet Metal Trim

New Addition Interior

Bathroom Accessories & Ceramic Tiling; Ceiling Grid and MEP Ceiling Finishes; Drywall, Taping and Mudding

Weather

Construction Days Lost to Weather This Month: 0

Total Construction Days Lost to Weather: 4

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 100

Project Team

Kraus-Anderson Construction Company

Jared Sammon | Project Superintendent | jared.sammon@krausanderson.com

Mike Stafford | Project Manager | mike.stafford@krausanderson.com

Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com

I&S Group

Carter Burroughs | Carter.Burroughs@ISGInc.com

EDI-Dolejs

Mike Dolejs | mdolejs@edi-dolejs.com

Ronda Natysin | rnatysin@edi-dolejs.com