Hoover Elementary School

CONSTRUCTION UPDATES | APRIL 2026

Construction Updates

Area C – New Addition

Completed:

Building Structure

  • Grading & Foundation Excavation
  • Footing Forms & Pours
  • Foundation Wall Forms & Pour
  • Steel Erection
  • Steel Detailing
  • Steel Decking

Interior Work

  • Underground Electrical and Plumbing

Exterior Work

  • Exterior Wall Framing
  • Exterior Wall Sheathing
  • Exterior Wall Weather Proofing
  • Roof and Window Blocking
  • Roof Parapet Wall

Ongoing:

  • Weather Tight Roofing

Upcoming:

Interior Work

  • Concrete Slab Pour
  • Interior Wall Framing
  • Hollow Metal Door Frame Installation
  • Above Ceiling and In Wall MEP Rough-Ins
  • Drywall Hanging, Taping, and Mudding
  • Painting
  • Ceramic Tile

Exterior Work

  • Brick Installation
  • Window Frame and Glazing Installation

Area - Existing Building

Completed:

Interior Work

  • Temp Wall Installation at Existing Main Entrance
  • Existing Store Front Demolition
  • Existing Vestibule MEP Demolition
  • Existing Acoustical Ceiling Tile and Ceiling Grid Demolition
  • Electrical Switch Installation at Electrical Box

Exterior Work

  • Underground Electrical Tie-In at Mechanical Room

Ongoing:

  • Boiler Abatement

Upcoming:

Interior Work

  • Floor Protection
  • Ceiling Demolition
  • MEP Demolition

Exterior Work

  • Electrical Transformer Concrete Pad Form & Pour
  • Electrical Transformer Installation
  • Electrical Gas Meter Relocation

Area - Tunnel

Completed:

  • Electrical Conduit Installation
  • Debris Removal

Ongoing:

  • Plastic Floor Protectant Installation

Upcoming:

  • Sanitary Line Piping Installation

Photos

Existing Building

MEP and Ceiling Demolition, Electrical Switch at Electrical Box, Underground Electrical Tie-In and Underground Electrical Piping Connecting to Existing Building at Boiler Room

New Addition Exterior

Structural Steel and Wall Framing, Wall Sheathing, and Wall and Window Weather Proofing
Parapet Walls, Roof Decking, and Roof Vapor Barrier

New Addition MEP

Underground Electrical & Plumbing Installations

Weather

Construction Days Lost to Weather This Month: 1

Total Construction Days Lost to Weather: 3

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 40

Project Team

Kraus-Anderson Construction Company

Jared Sammon | Project Superintendent | jared.sammon@krausanderson.com

Mike Stafford | Project Manager | mike.stafford@krausanderson.com

Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com

I&S Group

Carter Burroughs | Carter.Burroughs@ISGInc.com

EDI-Dolejs

Mike Dolejs | mdolejs@edi-dolejs.com

Ronda Natysin | rnatysin@edi-dolejs.com