Construction Updates
Area C – New Addition
Completed:
Interior Work
- Painting
- Ceramic Tile
- Fire Suppression Rough-In
- Ceiling Grid
- Drywall Mudding and Taping
- Bathroom Accessories
Exterior Work
- Window Frame Installation
- Sheet Metal Flashing at Rooftop
Ongoing:
- MEP Finishes
- Site Utilities Tie-In
Upcoming:
Interior Work
- Casework
- Door & Hardware
- Flooring
Exterior Work
- Glazing Installation
Area - Existing Building
Completed:
Interior Work
- Casework Demolition
- Interior Wall Demolition
- Air Handling Unit Installation
- CMU Block Infill
- Existing Boiler Pad Demolition
- New Boiler Pad Pour Back
Exterior Work
- Solar Tube Installation
- Chimney Demolition
- Existing Roof Top Equipment Demolition
- Roof Patching at Existing Equipment Demolition
Ongoing:
- Structural Steel Support
- MEP Rough-Ins
- Mechanical/Plumbing Insulation
- Interior Wall Framing
- Drywall Hanging, Taping, Mudding
- Ceiling Grid Installation
- Painting
- Boiler Installation
Upcoming:
Interior Work
- Flooring
- Ships Ladder
Exterior Work
- Roof Top Unit Placement
- Roof Top Curb Installation
Area - Tunnel
Completed:
- Plumbing Demolition
- Electrical Wiring
Ongoing:
- HVAC Piping Installation
Photos
Existing Building Exterior
Existing Building Interior
New Addition Exterior
New Addition Interior
Weather
Construction Days Lost to Weather This Month: 0
Total Construction Days Lost to Weather: 4
Safety
Lost Time Days: 0
Days Worked Without Lost Time Accident: 100
Project Team
Kraus-Anderson Construction Company
Jared Sammon | Project Superintendent | jared.sammon@krausanderson.com
Mike Stafford | Project Manager | mike.stafford@krausanderson.com
Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com
I&S Group
Carter Burroughs | Carter.Burroughs@ISGInc.com
EDI-Dolejs
Mike Dolejs | mdolejs@edi-dolejs.com
Ronda Natysin | rnatysin@edi-dolejs.com