Hoover Elementary School

CONSTRUCTION UPDATES | MARCH 2026

Construction Updates

Area C – New Addition

Completed:

Site Mobilization

  • Site Fencing Around Construction Perimeter
  • Rock Entrance at Construction Entrance
  • Installed Erosion Control
  • Jobsite Trailer Set Up

Site Clearing/Demolition

  • Tree Removal
  • Flagpole Removed
  • Concrete Sidewalk Demolition
  • Existing Vestibule Ceiling Tile & Misc Demo

Building Structure

  • Grading & Foundation Excavation
  • Footing Forms & Pours

Ongoing:

  • Foundation Wall Forms & Pour
  • Underground Plumbing

Upcoming:

Building Structure

  • Steel Erection
  • Steel Detailing
  • Steel Decking

Area - Tunnel

Ongoing:

  • Electrical Conduit Placement

Photos

(L-R) Footing Form and Rebar Placement at New Addition, Site Walk Demolition at New Addition, and Tree Removal
Plumbing Sleeve in Footings and Plumbing Sleeve Install at New Addition
Rock Entrance at Construction Entrance and Site Fencing at Construction Perimeter

Weather

Construction Days Lost to Weather This Month: 0

Total Construction Days Lost to Weather: 0

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 10

Project Team

Kraus-Anderson Construction Company

Jared Sammon | Project Superintendent | jared.sammon@krausanderson.com

Mike Stafford | Project Manager | mike.stafford@krausanderson.com

Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com

I&S Group

Carter Burroughs | Carter.Burroughs@ISGInc.com

EDI-Dolejs

Mike Dolejs | mdolejs@edi-dolejs.com

Ronda Natysin | rnatysin@edi-dolejs.com