Hoover Elementary School

CONSTRUCTION UPDATES | MAY 2026

Construction Updates

Area C – New Addition

Completed:

Interior Work

  • Concrete Slab Pour
  • Interior Wall Framing
  • Hollow Metal Door Frame Installation
  • Above Ceiling and In Wall MEP Rough-Ins
  • Drywall Hanging

Exterior Work

  • Brick Installation
  • Weather Tight Roofing
  • Metal Panel Soffit at Canopy

Ongoing:

  • Drywall Mudding and Taping

Upcoming:

Interior Work

  • Painting
  • Ceramic Tile
  • Fire Suppression Rough-In
  • Ceiling Grid
  • Casework
  • MEP Finishes

Exterior Work

  • Window Frame and Glazing Installation

Area - Existing Building

Completed:

Interior Work

  • Boiler Abatement
  • Boiler Demolition
  • Floor Protection
  • Ceiling Grid Demolition
  • MEP Demolition
  • Abatement

Exterior Work

  • Transformer Concrete Slab Poured
  • Electrical Transformer Installation
  • Electrical Gas Meter Relocation

Ongoing:

  • MEP Rough-Ins
  • Solar Tube Installation

Upcoming:

Interior Work

  • Fire Protection Rough-Ins
  • Interior Wall Framing
  • Drywall Hanging, Taping, Mudding
  • Interior Wall Painting
  • Ceiling Grid Installation

Exterior Work

  • Electrical Transformer Concrete Pad Form & Pour
  • Electrical Transformer Installation
  • Electrical Gas Meter Relocation

Area - Tunnel

Completed:

  • Masonite & Poly Floor Protectant Installation
  • Electrical Conduit Installation

Ongoing:

  • Electrical Wiring
  • Plumbing Demolition
  • HVAC Piping Installation

Photos

Existing Building Exterior

Transformer Concrete Slab and Tubular Daylight Replacement Installation on Rooftop

Existing Building Interior

Abatement, Above Ceiling Demolition and Ductwork Rough-In, Boiler Demolition, Ceiling Demolition, Floor Protection, and Mechanical Demolition

New Addition Exterior

Metal Panel Soffit at Canopy and Water Tight Roofing

New Addition Interior

Above Ceiling Ductwork, Plumbing, Mechanical, and Sheathing, Concrete Slab Pour, Drywall Hanging and In Wall Insulation, Hollow Metal Door Frames, Drywall, and Above Ceiling Ductwork, In Wall Backing, Interior Wall Framing, and MEP Rough-Ins

Tunnel

Tunnel Reinforcement

Weather

Construction Days Lost to Weather This Month: 0

Total Construction Days Lost to Weather: 4

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 70

Project Team

Kraus-Anderson Construction Company

Jared Sammon | Project Superintendent | jared.sammon@krausanderson.com

Mike Stafford | Project Manager | mike.stafford@krausanderson.com

Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com

I&S Group

Carter Burroughs | Carter.Burroughs@ISGInc.com

EDI-Dolejs

Mike Dolejs | mdolejs@edi-dolejs.com

Ronda Natysin | rnatysin@edi-dolejs.com