Construction Updates
Area C – New Addition
Completed:
Interior Work
- Above Ceiling Sheathing and Sound Proofing
- Above Ceiling and In Wall MEP Rough-Ins
- Hollow Metal Door Frame Installation
- In Wall Insulation
- In Wall Wood Blocking
- Drywall Hanging, Taping, Mudding
Exterior Work
- Exterior Brick Installation
- Metal Soffits and Panels at Canopy
- Weather Tight Roofing – New Addition
Ongoing:
- Paint
Upcoming:
Interior Work
- Ceramic Tile
- Ceiling Grid
- Fire Suppression Rough-In
- Door & Hardware
- Casework
- Bathroom Accessories
- MEP Finishes
Exterior Work
- Weather Tight Roofing – [Canopy]
- Window Frame and Glazing Installation
Area - Existing Building
Completed:
Interior Work
- Boiler Abatement
- Boiler Demolition
- Floor Protection
- Ceiling Grid Demolition
- MEP Demolition
- Abatement
Exterior Work
- Underground Electrical Tie-In at Mechanical Room
- Transformer Concrete Slab Poured
- Electrical Transformer Installation
Ongoing:
- Casework Demolition
- MEP Rough-Ins
Upcoming:
Interior Work
- Fire Protection Rough-Ins
- Interior Wall Framing
- Drywall Hanging, Taping, Mudding
- Interior Wall Painting
- Ceiling Grid Installation
Exterior Work
- Solar Tube Installation
Area - Tunnel
Completed:
- HVAC Tubing Installation
- Electrical Conduit Installation
- Electrical Wiring
Ongoing:
- Plumbing Demolition
Photos
Existing Building Exterior Work
Existing Building Interior Work
New Addition Exterior Work
New Addition Interior Work
Weather
Construction Days Lost to Weather This Month: 0
Total Construction Days Lost to Weather: 2
Safety
Lost Time Days: 0
Days Worked Without Lost Time Accident: 70
Project Team
Kraus-Anderson Construction Company
Jeff Femling | Project Superintendent | jeff.femling@krausanderson.com
Mike Stafford | Project Manager | mike.stafford@krausanderson.com
Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com
I&S Group
Carter Burroughs | Carter.Burroughs@ISGInc.com
EDI-Dolejs
Mike Dolejs | mdolejs@edi-dolejs.com
Ronda Natysin | rnatysin@edi-dolejs.com