View Screen Reader-Friendly Version

Kennedy Elementary School

CONSTRUCTION UPDATES | JUNE 2026

Construction Updates

Area C – New Addition

Completed:

Interior Work

  • Ceramic Tile
  • Ceiling Grid
  • Fire Suppression Rough-In
  • Painting

Exterior Work

  • Window Frame Installation

Ongoing:

  • MEP Finishes
  • Site Utilities Tie-In

Upcoming:

Interior Work

  • Door & Hardware
  • Casework
  • Bathroom Accessories
  • Acoustical Ceiling Tile Placement
  • Flooring

Exterior Work

  • Weather Tight Roofing – [Canopy]
  • Glazing Installation
  • Sidewalk at Main Entry
  • Landscape Restoration

Area - Existing Building

Completed:

Interior Work

  • Casework Demolition
  • Boiler Pad Demolition
  • Floor Slab Demolition
  • Existing Wall Door Cuts & Lintel Installation
  • Boiler Pad Infill
  • Floor Slab Infill
  • Ships Ladder Installation
  • CMU Patching / Infill

Exterior Work

  • Roof Top Unit Curbs
  • Existing Roof Top Equipment Demolition
  • Roof Patching at Existing Equipment Demolition
  • Existing Chimney Demolition

Ongoing:

  • MEP Rough-Ins
  • Mechanical/Plumbing Insulation
  • Interior Wall Framing
  • Drywall Hanging, Taping, Mudding
  • Ceiling Grid Installation
  • Flooring
  • Painting
  • Boiler Installation

Upcoming:

Exterior Work

  • Solar Tube Installation
  • Trash Enclosure
  • Roof Top Unit Installation

Area - Tunnel

Completed:

  • Plumbing Demolition

Ongoing:

  • Plumbing Rough-In Tie-In

Photos

Existing Building Exterior Work

Chimney Demolition

Existing Building Interior Work

Above Ceiling Mechanical & Fire Suppression Rough-In; Air Handling Unit and Mechanical Duct Rough-In; Ceiling Grid and Mechanical Duct Insulation; CMU Infill; Concrete Boiler Pad Pour Back
Drywall, Mudding, and Taping; Existing Boiler Pad Demolition; In-Wall Electrical Rough-In; Door Cut and Lintel Installation; Slab Demolition; Wall Framing; Ships Ladder

New Addition Exterior Work

Utilities Tie-In and Window Frame Installation

New Addition Interior Work

Drywall, Mudding, and Taping; Ceiling Grid; Wall Painting; Tile Work

Weather

Construction Days Lost to Weather This Month: 0

Total Construction Days Lost to Weather: 2

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 100

Project Team

Kraus-Anderson Construction Company

Jeff Femling | Project Superintendent | jeff.femling@krausanderson.com

Mike Stafford | Project Manager | mike.stafford@krausanderson.com

Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com

I&S Group

Carter Burroughs | Carter.Burroughs@ISGInc.com

EDI-Dolejs

Mike Dolejs | mdolejs@edi-dolejs.com

Ronda Natysin |  rnatysin@edi-dolejs.com