Kennedy Elementary School

CONSTRUCTION UPDATES | APRIL 2026

Construction Updates

Area C – New Addition

Completed:

Building Structure

  • Grading & Foundation Excavation
  • Footing Forms & Pours
  • Foundation Wall Forms & Pours
  • Steel Erection
  • Steel Detailing
  • Steel Decking

Interior Work

  • Underground Plumbing & Electrical
  • Concrete Slab Pour
  • Interior Wall Framing

Exterior Work

  • Exterior Wall Framing
  • Exterior Wall Sheathing
  • Exterior Wall Weather Proofing
  • Roof Blocking
  • Parapet Walls

Ongoing:

  • Exterior Brick Installation
  • Above Ceiling Sheathing and Sound Proofing
  • Above Ceiling and In Wall MEP Rough-Ins

Upcoming:

Interior Work

  • Hollow Metal Door Frame Installation
  • Drywall Hanging, Taping, Mudding
  • Paint
  • Ceramic Tile

Exterior Work

  • Weather Tight Roofing
  • Window Frame and Glazing Installation
  • Metal Soffits and Panels

Area - Existing Building

Completed:

Interior Work

  • Temp Wall Installation at Existing Main Entrance
  • Existing Store Front Demolition
  • Existing Vestibule MEP Demolition
  • Existing Vestibule Acoustical Ceiling Tile and Ceiling Grid Demolition
  • Electrical Switch Installation at Electrical Box

Exterior Work

  • Underground Electrical Tie-In at Mechanical Room

Ongoing:

  • Boiler Abatement

Upcoming:

Interior Work

  • Floor Protection
  • Ceiling Demolition
  • MEP Demolition

Exterior Work

  • Electrical Transformer Concrete Pad Form & Pour
  • Electrical Transformer Installation

Area - Tunnel

Completed:

  • Electrical Conduit Placement
  • Sanitary Plumbing Line Installation

Photos

Existing Building Work

Temp Wall, Underground Electrical Conduit Tie-In and Electrical Conduit

New Addition Exterior Work

Structural Steel Erection, Framing, Brick Starting, Wall Sheathing, and Weather Barrier
Parapet Roof Framing, Mechanical Curb, and Roof Decking

New Addition Interior Work

Above Ceiling Sheathing and Sound Proofing, Concrete Slab Rebar and Vapor Barrier, Concrete Slab Pour and Cuts, and Wall Framing

MEP Work

Electrical Switch Added to Electrical Box and Underground Plumbing Installation

Weather

Construction Days Lost to Weather This Month: 2

Total Construction Days Lost to Weather: 2

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 40

Project Team

Kraus-Anderson Construction Company

Jeff Femling | Project Superintendent | jeff.femling@krausanderson.com

Mike Stafford | Project Manager | mike.stafford@krausanderson.com

Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com

I&S Group

Carter Burroughs | Carter.Burroughs@ISGInc.com

EDI-Dolejs

Mike Dolejs | mdolejs@edi-dolejs.com

Ronda Natysin |  rnatysin@edi-dolejs.com