Construction Updates
Area C – New Addition
Completed:
Interior Work
- Ceramic Tile
- Ceiling Grid
- Fire Suppression Rough-In
- Painting
Exterior Work
- Window Frame Installation
Ongoing:
- MEP Finishes
- Site Utilities Tie-In
Upcoming:
Interior Work
- Door & Hardware
- Casework
- Bathroom Accessories
- Acoustical Ceiling Tile Placement
- Flooring
Exterior Work
- Weather Tight Roofing – [Canopy]
- Glazing Installation
- Sidewalk at Main Entry
- Landscape Restoration
Area - Existing Building
Completed:
Interior Work
- Casework Demolition
- Boiler Pad Demolition
- Floor Slab Demolition
- Existing Wall Door Cuts & Lintel Installation
- Boiler Pad Infill
- Floor Slab Infill
- Ships Ladder Installation
- CMU Patching / Infill
Exterior Work
- Roof Top Unit Curbs
- Existing Roof Top Equipment Demolition
- Roof Patching at Existing Equipment Demolition
- Existing Chimney Demolition
Ongoing:
- MEP Rough-Ins
- Mechanical/Plumbing Insulation
- Interior Wall Framing
- Drywall Hanging, Taping, Mudding
- Ceiling Grid Installation
- Flooring
- Painting
- Boiler Installation
Upcoming:
Exterior Work
- Solar Tube Installation
- Trash Enclosure
- Roof Top Unit Installation
Area - Tunnel
Completed:
- Plumbing Demolition
Ongoing:
- Plumbing Rough-In Tie-In
New Addition Exterior Work
New Addition Interior Work
Weather
Construction Days Lost to Weather This Month: 0
Total Construction Days Lost to Weather: 2
Safety
Lost Time Days: 0
Days Worked Without Lost Time Accident: 100
Project Team
Kraus-Anderson Construction Company
Jeff Femling | Project Superintendent | jeff.femling@krausanderson.com
Mike Stafford | Project Manager | mike.stafford@krausanderson.com
Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com
I&S Group
Carter Burroughs | Carter.Burroughs@ISGInc.com
EDI-Dolejs
Mike Dolejs | mdolejs@edi-dolejs.com
Ronda Natysin | rnatysin@edi-dolejs.com