Kennedy Elementary School

CONSTRUCTION UPDATES | MAY 2026

Construction Updates

Area C – New Addition

Completed:

Interior Work

  • Above Ceiling Sheathing and Sound Proofing
  • Above Ceiling and In Wall MEP Rough-Ins
  • Hollow Metal Door Frame Installation
  • In Wall Insulation
  • In Wall Wood Blocking
  • Drywall Hanging, Taping, Mudding

Exterior Work

  • Exterior Brick Installation
  • Metal Soffits and Panels at Canopy
  • Weather Tight Roofing – New Addition

Ongoing:

  • Paint

Upcoming:

Interior Work

  • Ceramic Tile
  • Ceiling Grid
  • Fire Suppression Rough-In
  • Door & Hardware
  • Casework
  • Bathroom Accessories
  • MEP Finishes

Exterior Work

  • Weather Tight Roofing – [Canopy]
  • Window Frame and Glazing Installation

Area - Existing Building

Completed:

Interior Work

  • Boiler Abatement
  • Boiler Demolition
  • Floor Protection
  • Ceiling Grid Demolition
  • MEP Demolition
  • Abatement

Exterior Work

  • Underground Electrical Tie-In at Mechanical Room
  • Transformer Concrete Slab Poured
  • Electrical Transformer Installation

Ongoing:

  • Casework Demolition
  • MEP Rough-Ins

Upcoming:

Interior Work

  • Fire Protection Rough-Ins
  • Interior Wall Framing
  • Drywall Hanging, Taping, Mudding
  • Interior Wall Painting
  • Ceiling Grid Installation

Exterior Work

  • Solar Tube Installation

Area - Tunnel

Completed:

  • HVAC Tubing Installation
  • Electrical Conduit Installation
  • Electrical Wiring

Ongoing:

  • Plumbing Demolition

Photos

Existing Building Exterior Work

Electrical Transformer Concrete Slab & Mechanical Demolition

Existing Building Interior Work

Abatement, Above Ceiling Demolition, Above Ceiling Mechanical Ductwork Rough-Ins, Boiler Abatement and Demolition, Floor Protection, and Mechanical Demolition

New Addition Exterior Work

Exterior Brick, Metal Soffit Panels at Canopy, and Weather Tight Roofing

New Addition Interior Work

Above Ceiling Plumbing, Drywall, Mudding, and Taping, In Wall Electrical Rough-Ins and Insulation, and MEP Above Ceiling and In Wall Rough-Ins

Weather

Construction Days Lost to Weather This Month: 0

Total Construction Days Lost to Weather: 2

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 70

Project Team

Kraus-Anderson Construction Company

Jeff Femling | Project Superintendent | jeff.femling@krausanderson.com

Mike Stafford | Project Manager | mike.stafford@krausanderson.com

Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com

I&S Group

Carter Burroughs | Carter.Burroughs@ISGInc.com

EDI-Dolejs

Mike Dolejs | mdolejs@edi-dolejs.com

Ronda Natysin |  rnatysin@edi-dolejs.com