Kennedy Elementary School

CONSTRUCTION UPDATES | MARCH 2026

Construction Updates

Area C – New Addition

Completed:

Site Mobilization

  • Site Fencing Around Construction Perimeter
  • Rock Entrance at Construction Entrance
  • Installed Erosion Control
  • Jobsite Trailer Set Up

Site Clearing/Demolition

  • Tree Removal
  • Flagpole Removed
  • Concrete Sidewalk Demolition
  • Existing Vestibule Ceiling Tile & Misc Demo

Building Structure

  • Grading & Foundation Excavation
  • Footing Forms & Pours
  • Foundation Wall Forms & Pours

Upcoming:

Building Structure

  • Underground Plumbing
  • Steel Erection
  • Steel Detailing
  • Steel Decking

Area - Tunnel

Ongoing:

  • Electrical Conduit Placement
  • Sanitary Plumbing Line Installation

Photos

(L-R, T-B) Footing Forms & Rebar Placement, Foundation Excavation at New Addition, and Foundation Wall Forms at New Addition
(L-R, T-B) Jobsite Trailer Set Up, Rock Entrance at Construction Entrance, and Site Fencing at Construction Perimeter
Sanitary Piping & Electrical Conduit Installment In Tunnel

Weather

Construction Days Lost to Weather This Month: 0

Total Construction Days Lost to Weather: 0

Safety

Lost Time Days: 0

Days Worked Without Lost Time Accident: 10

Project Team

Kraus-Anderson Construction Company

Jeff Femling | Project Superintendent | jeff.femling@krausanderson.com

Mike Stafford | Project Manager | mike.stafford@krausanderson.com

Justin Marschinke | Project Engineer | justin.marschinke@krausanderson.com

I&S Group

Carter Burroughs | Carter.Burroughs@ISGInc.com

EDI-Dolejs

Mike Dolejs | mdolejs@edi-dolejs.com

Ronda Natysin |  rnatysin@edi-dolejs.com