View Screen Reader-Friendly Version

Westonka High School

Construction Updates

About the Project

  • Construction at Westonka High School began in April 2025 and is scheduled to be complete in fall 2026. This transformative project will redesign nearly the entire school, optimizing spaces to better meet the needs of today’s students.
  • Interior upgrades will revitalize the 1971 building, incorporating thoughtful design improvements and modern finishes throughout.
  • The scope includes four additions to the building: expanded classrooms, a redesigned student services and administration area, a new weight room/fitness facility, and an expanded cafeteria. The expanded classroom space will allow for right-sizing undersized classrooms and will accommodate new vocational programming. The new fitness area will double as a storm shelter, enhancing safety for students, staff and visitors.
  • The project also includes a comprehensive overhaul of the building’s mechanical, electrical, plumbing, and fire protection systems, including the installation of a new mechanical mezzanine.
  • Exterior work includes the demolition of the existing tennis courts to expand the parking lot, reconfiguring traffic flow for improved safety and efficiency, as well as utility upgrades and pavement work. The high school stadium project is currently in the design phase, with construction expected to begin in spring 2026.

Construction Phasing Schedule

Ground Breaking

Construction Updates

Work in May

Phase 3 (Admin)

  • Exterior Metal Panels
  • Area turnover
  • Punchlist

Site Work

  • Storm sewer install
  • Water service
  • Demo road and curbs
  • Area drains
  • Water main work
  • Sanitary sewer

Phase 6 (Gym)

  • Abatement
  • MEP overhead
  • Demo basketball hoops and curtains
  • CMU Walls
  • Saw cutting and concrete pour back for electrical
  • Roofing
  • Overhead painting

Phase 7 (LRC/Existing Admin)

  • Demolition
  • Temporary barricades
  • CMU install
  • MEP underground
  • Concrete pour back
  • Framing
  • MEP rough-in

Phase 8 (LRC, School Store)

  • Temp Walls/Enclosure
  • MEP underground
  • Concrete pour back
  • Shoring
  • Abatement

Phase 10 (Little Theater)

  • Demo interior

Phase 11 (LL Storm Shelter)

  • Roof Demolition
  • Glass abatement
  • Temporary barricades

Boiler Room

  • Demolition

Upcoming Work in June

Phase 3 (Exterior Envelope)

  • Substantial completion

Site Work (Phase 1)

  • Underground electrical
  • Install curbing
  • Install base course
  • Install temp striping

Site Work (Phase 2)

  • Demo road and curbs
  • Install water service
  • Grading for infiltration pond
  • Install grading

Site Work (Phase 3)

  • Demo parking lot
  • Install water service
  • Install storm service
  • Install storm basin
  • Install grading

Site Work (Phase 4)

  • Demo road and curbs
  • Install water service
  • Install storm sewer
  • Install grading

Site Work (Phase 5)

  • Demo road and curbs
  • Install water service

Phase 6 (Gym)

  • Overhead gym equipment
  • Install doors and hardware
  • Install MEP overhead finishes

Phase 7 (LRC/Existing Admin)

  • Paint
  • MEP rough-in
  • Drywall and taping

Phase 8 (Bathroom)

  • Install CMU
  • Framing -
  • MEP Rough-in
  • Drywall and taping

Phase 8 (LRC, School Store)

  • Shoring
  • Demo above

Phase 9 (TV Studio)

  • Demolition
  • Sawcutting
  • MEP underground
  • Concrete pourback
  • MEP rough-ins
  • Framing
  • Install ceiling grid
  • Paint
  • MEP finishes
  • Flooring and finishes
  • Doors/frames/hardware

Phase 9 (Woodshop, Fabrication, Robotics)

  • Abatement
  • Demolition
  • Sawcutting
  • MEP underground
  • Concrete pourback
  • MEP rough-ins
  • Framing
  • Install CMU

Phase 9 (Arts, Band, and Choir)

  • Abatement
  • Demolition
  • Framing
  • Masonry Patch
  • MEP Rough-ins
  • Drywall and tape
  • Paint
  • Install ceiling grid
  • Doors/frames/hardware

Phase 9 (Cafeteria)

  • Abatement
  • Demolition
  • Install CMU
  • MEP Rough-ins

Phase 10 (Little Theater)

  • Demo ramp and stairs outside theater
  • Shoring to penthouse
  • Demo penthouse floor

Phase 11 (LL Storm Shelter)

  • Install shoring

Boiler Room

  • Demolition
  • Mechanical rough-in

Safety

  • Lost Time Days: 0

Weather

  • Lost Time Days: 16

Latest Drone Footage

Progress Photos

May 2026

Site Work

CTE Machine Shop

Phase 3 (New Admin)

Phase 6 (Gym)

Phase 7 (LRC, Existing Admin)

Phase 8 (LRC, School Store, Bathroom)

Phase 11 (LL Storm Shelter)

April 2026

Courtyard Demo

CTE Machine Shop

Little Theater Demo

LRC Demo

Phase 3 Exterior

Phase 3 New Admin

Phase 6 Gym

Phase 7 EMT Existing Admin

Phase 12 Corridors

March 2026

Old Tennis Courts Demo

Phase 3 Exterior

Phase 3 Lower Level

Phase 3 Main Level

Phase 3 Media Center

February 2026

Exterior

Phase 3 Lower Level

Phase 3 Upper Level

Phase 3 Media Center

January 2026

Northeast Stairways

Phase 3

Administration and Student Services
Media Center

December 2025

Phase 3

Administration and Student Services
Media Center

Phase 4

November 2025

Phase 3
Phase 4

October 2025

Phase 3

September 2025

Phase 1
Phase 2: Genius Bars and Breakout Rooms
Phase 2: Math Classrooms
Phase 2: Science Classrooms
Phase 2: Social Studies Classrooms
Phase 2: World Language Classrooms
Phase 3

August 2025

Phase 3
Watermain Work

July 2025

Phase 2 Framing and Rough-ins
Phase 2 Plumbing Trenches
Phase 3
Phase 4

June 2025

Classroom Move-Out and Light Demo
Heavy Demo Begins

May 2025

April 2025

March 2025

Project Team

Kraus-Anderson Construction Company

Gary Zifco, Project Executive

Ike Iverson, Senior Project Manager

Griffin Christensen, Assistant Project Manager

Ariel Corbett, Project Engineer

Nathan Wagner, Project Superintendent

Rob Schloeder, Project Superintendent

Scott Kolb, Project Superintendent

Tasha McFarland, Project Coordinator

Wold Architects & Engineers

Andrew Dahlquist, Associate/Architect

Elizabeth Thordson, Architectural

Matt Gump, Architectural

Alex Ng, Mechanical Engineering

Bradley Johannsen, Electrical Engineering

Construction updates created and managed by Kraus-Anderson Construction