Westonka High School

Construction Updates

About the Project

  • Construction at Westonka High School began in April 2025 and is scheduled to be complete in fall 2026. This transformative project will redesign nearly the entire school, optimizing spaces to better meet the needs of today’s students.
  • Interior upgrades will revitalize the 1971 building, incorporating thoughtful design improvements and modern finishes throughout.
  • The scope includes four additions to the building: expanded classrooms, a redesigned student services and administration area, a new weight room/fitness facility, and an expanded cafeteria. The expanded classroom space will allow for right-sizing undersized classrooms and will accommodate new vocational programming. The new fitness area will double as a storm shelter, enhancing safety for students, staff and visitors.
  • The project also includes a comprehensive overhaul of the building’s mechanical, electrical, plumbing, and fire protection systems, including the installation of a new mechanical mezzanine.
  • Exterior work includes the demolition of the existing tennis courts to expand the parking lot, reconfiguring traffic flow for improved safety and efficiency, as well as utility upgrades and pavement work. The high school stadium project is currently in the design phase, with construction expected to begin in spring 2026.

Construction Phasing Schedule

Ground Breaking

Construction Updates

Work in June

Exterior Envelope (Phase 3)

  • Substantial completion

Site Work (Phase 1)

  • Cement stabilize subgrade

Site Work (Phase 2)

  • Demo road and curbs
  • Install water service
  • Grading for infiltration pond

Site Work (Phase 3)

  • Demo parking lot
  • Install water service
  • Install storm service
  • Install storm basin
  • Level subgrade

Site Work (Phase 4)

  • Demo road and curbs
  • Install water service
  • Install storm sewer
  • Install grading

Site Work (Phase 5)

  • Demo road and crubs
  • Install water service

Gym (Phase 6)

  • Painting
  • Install doors and hardware
  • Install MEP overhead finishes

Existing Admin (Phase 7)

  • Paint
  • MEP rough-in
  • Framing
  • Drywall and taping

Bathroom (Phase 8)

  • Install CMU
  • Framing
  • MEP rough-in
  • Drywall and taping
  • Begin tile Installation

LRC, School Store (Phase 8)

  • Shoring
  • Demo above

TV Studio (Phase 9)

  • Demolition
  • Sawcutting
  • MEP underground
  • MEP rough-ins
  • Framing
  • Install ceiling grid
  • Paint
  • MEP finishes
  • Flooring and finishes
  • Doors/frames/hardware

Woodshop, Fabrication, Robotics (Phase 9)

  • Abatement
  • Demolition
  • Sawcutting
  • MEP underground
  • Concrete pourback
  • MEP rough-ins
  • Framing
  • Install CMU

Arts, Band, Choir (Phase 9)

  • Abatement
  • Demolition
  • Framing
  • Masonry Patch
  • MEP rough-ins
  • Paint
  • Install ceiling grid
  • Doors, frames, and hardware

Cafeteria (Phase 9)

  • Abatement
  • Demolition
  • Install CMU
  • MEP rough-ins

Little Theater (Phase 10)

  • Demo ramp and stairs outside theater
  • Shoring to penthouse
  • Demo penthouse floor

LL Storm Shelter (Phase 11)

  • Install shoring

Boiler Room

  • Install Boilers
  • Mechanical rough-in

Upcoming Work in July

Site Work (Red, Phase 2)

  • Install underground electrical
  • Install curbs
  • Install base course

Site Work (Blue, Phase 3)

  • Grading
  • Install curbs
  • Install underground electrical
  • Install area drains
  • Install concrete walks
  • Install base course
  • Install wear course

Site Work (Purple, Phase 4)

  • Install underground electrical
  • Install curbs
  • Install base course

Gym (Phase 6)

  • Overhead gym equipment (North half)
  • Overhead gym equipment (South half)
  • Install doors and hardware
  • Install gym floor

Existing Admin (Phase 7)

  • Paint
  • Ceiling grid install
  • MEP finishes

Bathroom (Phase 8)

  • Tile
  • Install ceilings
  • MEP finishes
  • Doors and hardware

LRC, School Store (Phase 8)

  • Framing
  • CMU framing
  • MEP rough-in
  • Drywall/tape

TV Studio (Phase 9)

  • Concrete pourback
  • Framing
  • Install ceiling grid
  • Paint
  • MEP finishes
  • Flooring and finishes
  • Doors/frames/hardware

Woodshop, Fabrication, Robotics (Phase 9)

  • MEP finishes
  • Flooring
  • Casework install
  • Doors, frames, and hardware
  • Machine shop setup
  • Glass and glazing
  • Pad out ceilings
  • Final clean

Arts, Band, Choir (Phase 9)

  • Paint
  • Flooring
  • Pad out ceilings
  • Final clean

Cafeteria (Phase 9)

  • MEP rough-ins
  • Paint
  • Install ceiling grid
  • Install overhead coiling doors
  • MEP finishes
  • Flooring

Little Theater (Phase 10)

  • Remove shoring
  • Pourback concrete ramp (common area)
  • Concrete ramp and stairs (interior)
  • Framing

LL Storm Shelter (Phase 11)

  • Excavation and export
  • Underpinning

Safety

  • Lost Time Days: 0

Weather

  • Lost Time Days: 17

Latest Drone Footage

Progress Photos

June 2026

Gym

Existing Admin

Bathroom

LRC, School Store

TV Studio

Woodshop, Fabrication, Robotics

Arts, Band, Choir

Cafeteria

Little Theater

LL Storm Shelter

May 2026

Site Work

CTE Machine Shop

Phase 3 (New Admin)

Phase 6 (Gym)

Phase 7 (LRC, Existing Admin)

Phase 8 (LRC, School Store, Bathroom)

Phase 11 (LL Storm Shelter)

April 2026

Courtyard Demo

CTE Machine Shop

Little Theater Demo

LRC Demo

Phase 3 Exterior

Phase 3 New Admin

Phase 6 Gym

Phase 7 EMT Existing Admin

Phase 12 Corridors

March 2026

Old Tennis Courts Demo

Phase 3 Exterior

Phase 3 Lower Level

Phase 3 Main Level

Phase 3 Media Center

February 2026

Exterior

Phase 3 Lower Level

Phase 3 Upper Level

Phase 3 Media Center

January 2026

Northeast Stairways

Phase 3

Administration and Student Services
Media Center

December 2025

Phase 3

Administration and Student Services
Media Center

Phase 4

November 2025

Phase 3
Phase 4

October 2025

Phase 3

September 2025

Phase 1
Phase 2: Genius Bars and Breakout Rooms
Phase 2: Math Classrooms
Phase 2: Science Classrooms
Phase 2: Social Studies Classrooms
Phase 2: World Language Classrooms
Phase 3

August 2025

Phase 3
Watermain Work

July 2025

Phase 2 Framing and Rough-ins
Phase 2 Plumbing Trenches
Phase 3
Phase 4

June 2025

Classroom Move-Out and Light Demo
Heavy Demo Begins

May 2025

April 2025

March 2025

Project Team

Kraus-Anderson Construction Company

Gary Zifco, Project Executive

Ike Iverson, Senior Project Manager

Griffin Christensen, Assistant Project Manager

Ariel Corbett, Project Engineer

Nathan Wagner, Project Superintendent

Rob Schloeder, Project Superintendent

Scott Kolb, Project Superintendent

Tasha McFarland, Project Coordinator

Wold Architects & Engineers

Andrew Dahlquist, Associate/Architect

Elizabeth Thordson, Architectural

Matt Gump, Architectural

Alex Ng, Mechanical Engineering

Bradley Johannsen, Electrical Engineering

Construction updates created and managed by Kraus-Anderson Construction