View Screen Reader-Friendly Version

Westonka High School

Construction Updates

About the Project

  • Construction at Westonka High School began in April 2025 and is scheduled to be complete in fall 2026. This transformative project will redesign nearly the entire school, optimizing spaces to better meet the needs of today’s students.
  • Interior upgrades will revitalize the 1971 building, incorporating thoughtful design improvements and modern finishes throughout.
  • The scope includes four additions to the building: expanded classrooms, a redesigned student services and administration area, a new weight room/fitness facility, and an expanded cafeteria. The expanded classroom space will allow for right-sizing undersized classrooms and will accommodate new vocational programming. The new fitness area will double as a storm shelter, enhancing safety for students, staff and visitors.
  • The project also includes a comprehensive overhaul of the building’s mechanical, electrical, plumbing, and fire protection systems, including the installation of a new mechanical mezzanine.
  • Exterior work includes the demolition of the existing tennis courts to expand the parking lot, reconfiguring traffic flow for improved safety and efficiency, as well as utility upgrades and pavement work. The high school stadium project is currently in the design phase, with construction expected to begin in spring 2026.

Construction Phasing Schedule

Ground Breaking

Construction Updates

Work in March

Phase 1 (Science Wing)

  • Install corridor flooring

Phase 3 (Admin)

  • Spray foam exterior walls
  • Layout & framing
  • MEP rough-in
  • Drywall & taping
  • Painting lower level
  • Interior brick
  • Restroom tile install
  • Exterior water barrier
  • Exterior glazing
  • Casework install
  • Lower level ceiling install

Phase 3 (Media Center)

  • Finish ceilings in media center
  • Glass installation
  • Casework
  • Door & hardware install
  • Furniture install
  • Punch list walkthrough
  • Final clean media center

Phase 6 (Gym)

  • Demolition

Phase 12 (Corridors)

  • Demo tile & floor leveling

Penthouse

  • Installing new chiller piping

Boiler Room

  • Demolition

Sitework

  • Old tennis court demo

Upcoming Work in April

Phase 3 (Admin)

  • Painting main level
  • Casework install
  • MEP finishes
  • Install ceiling grid on main level
  • Interior glazing
  • Doors/hardware
  • Flooring
  • Finishes
  • Ceiling pad out
  • Final clean
  • Punchlist walkthrough
  • Air handler start up and commissioning

Phase 6 (Gym)

  • Abatement

Phase 12 (Corridors)

  • Ceiling grid install
  • Floor tile

Boiler Room

  • Demolition

Penthouse

  • Installing new chiller piping

Safety

  • Lost Time Days: 0

Weather

  • Lost Time Days: 16

Progress Photos

March 2026

Old Tennis Courts Demo

Phase 3 Exterior

Phase 3 Lower Level

Phase 3 Main Level

Phase 3 Media Center

February 2026

Exterior

Phase 3 Lower Level

Phase 3 Upper Level

Phase 3 Media Center

January 2026

Northeast Stairways

Phase 3

Administration and Student Services
Media Center

December 2025

Phase 3

Administration and Student Services
Media Center

Phase 4

November 2025

Phase 3
Phase 4

October 2025

Phase 3

September 2025

Phase 1
Phase 2: Genius Bars and Breakout Rooms
Phase 2: Math Classrooms
Phase 2: Science Classrooms
Phase 2: Social Studies Classrooms
Phase 2: World Language Classrooms
Phase 3

August 2025

Phase 3
Watermain Work

July 2025

Phase 2 Framing and Rough-ins
Phase 2 Plumbing Trenches
Phase 3
Phase 4

June 2025

Classroom Move-Out and Light Demo
Heavy Demo Begins

May 2025

April 2025

March 2025

Project Team

Kraus-Anderson Construction Company

Gary Zifco, Project Executive

Ike Iverson, Project Manager

Griffin Christensen, Assistant Project Manager

Ariel Corbett, Project Engineer

Nathan Wagner, Project Superintendent

Rob Schloeder, Project Superintendent

Tasha McFarland, Project Coordinator

Wold Architects & Engineers

Andrew Dahlquist, Associate/Architect

Elizabeth Thordson, Architectural

Matt Gump, Architectural

Alex Ng, Mechanical Engineering

Bradley Johannsen, Electrical Engineering

Construction updates created and managed by Kraus-Anderson Construction