Westonka Stadium

Construction Updates

About the Project

Construction of the new stadium improvements at Westonka High School is anticipated to begin in spring 2026 and is scheduled for completion in spring of 2027. The project will transform the school’s athletic complex into a modern, multi-purpose facility designed to better support students, athletes, staff, and the community. The scope of work includes the construction of a new athletic stadium featuring a synthetic turf field, upgraded track and field facilities, new bleachers, press box, concessions and ticketing areas, team storage spaces, and enhanced spectator amenities. The improvements are designed to elevate the game-day experience while supporting year-round athletic and community use. Site improvements will include new sidewalks, parking lot modifications, utility upgrades, improved drainage infrastructure, and reconfigured circulation for safer and more efficient traffic flow throughout the campus. The project also includes extensive grading, landscaping, and stormwater management enhancements to improve long-term site performance and sustainability. In preparation for the new construction, portions of the existing site will be demolished, including sections of pavement, fencing, utilities, and other outdated athletic infrastructure. Environmental and wetland mitigation measures are also incorporated into the project to protect surrounding natural resources during construction.

Stadium Rendering

Construction Updates

Work in June

Site Work

  • Strip topsoil (South)
  • One way export topsoil (South)
  • Cut/fill common (South)
  • Storm sewer install (North)
  • Sanitary install (North)
  • Install site electrical
  • Started retaining wall
  • Grading and moving elevations

Buildings (Concessions, Entrance, Ticket Booth, Canopy)

  • Underground utilities
  • Footings and foundations
  • Below grade CMU
  • Backfill
  • CMU above grade

Upcoming Work in July

Site Work

  • Install concrete
  • Install sanitary pipe (South)
  • Storm sewer pipe (North)
  • Install base stone (North)
  • Dig bleacher footings
  • Pour bleacher footings
  • Install Finish stone (North)
  • Install collector (South)
  • Install fence south mowstrip
  • Install turf (North)
  • South site work

Buildings (Concessions, Entrance, Ticket Booth, Canopy)

  • Install steel
  • Install weather barrier on CMU
  • Install brick veneer
  • Install awning/canopy
  • Install roof blocking
  • MEP rough-in

Grandstand/Bleachers

  • Grandstand foundations

Safety

  • Lost Time Days: 0

Weather

  • Lost Time Days: 3

Latest Drone Footage

Progress Photos

June 2026

Site Work

Buildings

May 2026

Site Work

April 2026

Site Work

Project Team

Kraus-Anderson Construction Company

Gary Zifco, Project Executive

Ike Iverson, Senior Project Manager

Michael Janssen, Project Manager

Ariel Corbett, Project Engineer

Nathan Wagner, Project Superintendent

Tasha McFarland, Project Coordinator

Wold Architects & Engineers

Andrew Dahlquist, Associate/Architect

Elizabeth Thordson, Architectural

Matt Gump, Architectural

Alex Ng, Mechanical Engineering

Bradley Johannsen, Electrical Engineering

Construction updates created and managed by Kraus-Anderson Construction