Hilltop Primary School
This project will replace aging mechanical systems throughout the building while completing the electrical, plumbing, and structural work needed to support the new equipment. Areas impacted by construction will receive new finishes, including flooring, painting, ceilings, and restoration of existing casework where applicable. Exterior improvements include pavement replacement, new fencing, basketball court improvements, grading, and landscaping to improve the safety and longevity of the site.
Shirley Hills Primary School
This project focuses on deferred maintenance improvements that replace aging building systems and update building infrastructure. Work includes mechanical, electrical, plumbing, and structural improvements, along with restoration of interior finishes affected by construction. The goal is to improve the reliability and long-term performance of the facility while minimizing impacts to the school environment.
Construction Updates
Work in June
Hilltop Primary School
- Demo windows
- Roof demo
- MEP demo
- Flooring demo
- MEP rough-ins
- Boilers replaced and set
- Piping
- Water pumps set
- RTU’s demo
Shirley Hills Primary School
- Demo utilities and bathroom walls
- Bituminous demo
- Tunnel demo for piping
- Roof demo
- MEP demo
- Casework demo
- MEP rough-in
Upcoming Work in July
Hilltop Primary School
- Roof demo
- Install new fencing
- MEP rough-ins
- Patch masonry
- Install new door frames
- Install carpet
- Painting
- Casework install
- Reinstall salvaged materials
- Window install
Shirley Hills Primary School
- Site grading
- Curb and gutters
- Turf
- Steel install
- MEP rough-ins
- Seeding
- Set mechanical equipment
- Install new door frames
- Painting
- Install carpet
- Casework install
- Reinstall salvaged materials
Safety
- Lost Time Days: 0
Weather
- Lost Time Days: 0
Progress Photos
June 2026
Hilltop Primary School
Shirley Hills Primary School
Project Team
Kraus-Anderson Construction Company
Gary Zifco, Project Executive
Ike Iverson, Senior Project Manager
Michael Janssen, Project Manager
Ariel Corbett, Project Engineer
Fladger Phenix, Project Superintendent
Tasha McFarland, Project Coordinator
Wold Architects & Engineers
Andrew Dahlquist, Associate/Architect
Elizabeth Thordson, Architectural
Matt Gump, Architectural
Alex Ng, Mechanical Engineering
Bradley Johannsen, Electrical Engineering
Construction updates created and managed by Kraus-Anderson Construction