View Screen Reader-Friendly Version

Westonka Primary Schools

Construction Updates

About the Projects

Hilltop Primary School

This project will replace aging mechanical systems throughout the building while completing the electrical, plumbing, and structural work needed to support the new equipment. Areas impacted by construction will receive new finishes, including flooring, painting, ceilings, and restoration of existing casework where applicable. Exterior improvements include pavement replacement, new fencing, basketball court improvements, grading, and landscaping to improve the safety and longevity of the site.

Shirley Hills Primary School

This project focuses on deferred maintenance improvements that replace aging building systems and update building infrastructure. Work includes mechanical, electrical, plumbing, and structural improvements, along with restoration of interior finishes affected by construction. The goal is to improve the reliability and long-term performance of the facility while minimizing impacts to the school environment.

Construction Updates

Work in June

Hilltop Primary School

  • Demo windows
  • Roof demo
  • MEP demo
  • Flooring demo
  • MEP rough-ins
  • Boilers replaced and set
  • Piping
  • Water pumps set
  • RTU’s demo

Shirley Hills Primary School

  • Demo utilities and bathroom walls
  • Bituminous demo
  • Tunnel demo for piping
  • Roof demo
  • MEP demo
  • Casework demo
  • MEP rough-in

Upcoming Work in July

Hilltop Primary School

  • Roof demo
  • Install new fencing
  • MEP rough-ins
  • Patch masonry
  • Install new door frames
  • Install carpet
  • Painting
  • Casework install
  • Reinstall salvaged materials
  • Window install

Shirley Hills Primary School

  • Site grading
  • Curb and gutters
  • Turf
  • Steel install
  • MEP rough-ins
  • Seeding
  • Set mechanical equipment
  • Install new door frames
  • Painting
  • Install carpet
  • Casework install
  • Reinstall salvaged materials

Safety

  • Lost Time Days: 0

Weather

  • Lost Time Days: 0

Progress Photos

June 2026

Hilltop Primary School

Shirley Hills Primary School

Project Team

Kraus-Anderson Construction Company

Gary Zifco, Project Executive

Ike Iverson, Senior Project Manager

Michael Janssen, Project Manager

Ariel Corbett, Project Engineer

Fladger Phenix, Project Superintendent

Tasha McFarland, Project Coordinator

Wold Architects & Engineers

Andrew Dahlquist, Associate/Architect

Elizabeth Thordson, Architectural

Matt Gump, Architectural

Alex Ng, Mechanical Engineering

Bradley Johannsen, Electrical Engineering

Construction updates created and managed by Kraus-Anderson Construction