Progress Update
Curb and Gutter are installed throughout the project and the binder is down throughout. The final plat for lots 1-7 has been submitted. We have received building permits for the first 43 homes and the first 27 slabs have been poured. There are now 18 homes dried in and another 12 where framing is substantially complete. Our Property Management Company has been on-boarded and we are working on a marketing package, pre-leasing to commence January 15th and we plan to have one of the Models staged with a full time leasing on site by February 1st.